Huntington Corp. v. Inwood Construction Co.

348 S.W.2d 442, 1961 Tex. App. LEXIS 1851
CourtCourt of Appeals of Texas
DecidedJune 16, 1961
Docket15944
StatusPublished
Cited by14 cases

This text of 348 S.W.2d 442 (Huntington Corp. v. Inwood Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huntington Corp. v. Inwood Construction Co., 348 S.W.2d 442, 1961 Tex. App. LEXIS 1851 (Tex. Ct. App. 1961).

Opinion

YOUNG, Justice.

Appellant’s suit against Inwood Construction Company was upon a written contract for the furnishing of material and labor in construction of three shopping centers (Vernon, Marshall and Texarkana), claiming breach of contract and damages of $52,383.36 for failure to construct the Marshall and Texarkana jobs according to plans and specifications and in a good and workmanlike manner. Defendant Inwood answered by first filing its plea in abatement and motion to dismiss said cause of action, alleging that plaintiff had violated terms of the contract by bringing suit prior to arbitration of the cause. On hearing of the plea, same was sustained and the cause dismissed; or at least “abated until after a final decision in the arbitration”, followed by this appeal. Trinity Universal Insurance Company is made a party, perforce of having executed to defendant Inwood its performance and payment bond.

The written agreement between Huntington and Inwood was for a maximum contract price of $903,000 with provisions for cost plus fee payments until that maximum should be reached. In paragraph 5 of the contract and made a part thereof were “The General Conditions of the Contract *443 for the Construction of Buildings, standard form of the American Institute of Architects, Sixth addition, 1951”. Article 20 of such Standard form provides: “Correction of Work After Final Payment. — Neither the final certificate nor payment nor any provision in the Contract Documents shall relieve the Contractor of responsibility for faulty materials or workmanship and, unless otherwise specified, he shall remedy any defects due thereto and pay for any damages to other work resulting therefrom which shall appear within a period of one year from the date of substantial completion. The Owner shall give notice of observed defects with reasonable promptness. All questions arising under this article shall be decided by the Architect subject to arbitration.” Article 40 of the same Standard Form provides: “Arbitration. — All disputes, claims or questions subject to arbitration under this contract shall be submitted to arbitration in accordance with the provisions, then obtaining, of the Standard Form of Arbitration Procedure of the American Institute of Architects, and this agreement shall be specifically enforceable under the prevailing arbitration law, and judgment upon the award rendered may be entered in the court of the forum, state or federal, having jurisdiction. It is mutually agreed that the decision of the arbitrators shall be a condition precedent to any right of legal action that either party may have against the other.”

Appellant had alleged that the paving on two of these three centers had failed of which it had given appellee notice in that such paving: “ * * * had not met grade specifications; had not met flexible base specifications; had not met quality specifications as to asphaltic concrete; and had not met specifications to amount or thickness of asphaltic concrete required by the specifications all of which existed by reason of the acts of the Defendant Inwood in not constructing the same in a good and workmanlike manner and in accordance with the plans and specifications as undertaken in the construction contract.” Also alleging demands that Inwood: * * * perform its obligation under the Construction Contract to deliver to Plaintiff paving at each of such sites in accordance with the plans and specifications executed in a good and workmanlike manner or to return to Plaintiff the moneys which Plaintiff had in fact theretofore paid * * then concluding its cause of action in allegations, viz.: “Plaintiff would show the Court that by reason of the breach and violation of Inwood’s contractual undertaking to construct the paving according to plans and specifications and in a good and workmanlike manner, Defendant Inwood has occasioned the loss and damage to Plaintiff in the amount of $52,383.36, being the amount collected therefor by Inwood purporting to deliver such paving as called for in the Construction Contract while in fact delivering to Plaintiff a paving wholly worthless and useless. That the defendant Inwood is entitled to an offset in the approximate amount of $5,500 for improvements made at the instance of the Plaintiff. Defendant insurance company having bound itself and undertaken by its bond to pay all loss and damage suffered by plaintiff by reason of the failure of Defendant Inwood, the defendant insurance company is jointly and severally liable to plaintiff for its damages, along with the defendant Inwood.”

The trial court sustained appellees’ motion to dismiss without any testimony; the only evidence other than their pleading being copies of the contract and above mentioned general conditions of the American Institute of Architects and their Standard Form of Arbitration procedure. Following admissions not material here Inwood denied liability on the merits of plaintiff’s asserted claim; and pertinent to this suit, alleged that: “Inasmuch as the contract between plaintiff and defendant requires an arbitration decision as a prerequisite to bringing legal action and inasmuch as no arbitration decision has been rendered to support the legal action brought herein by plaintiff, plaintiff is not entitled to recover any amount from defendant.”

*444 Appellant in first point asserts error in the trial court’s judgment of dismissal for absence of a prior award under arbitration “in that the executory contract requiring’ the parties to arbitrate all future disputes as to liability as well as damages was against public policy and void for attempting to oust the courts of jurisdiction.” Upon thorough study of the record and briefs, we conclude that appellant’s point should be sustained.

“A provision in an executory contract that any disputes arising out of the contract are to be settled by arbitration is against public policy in attempting to oust the courts of jurisdiction, and when such a provision is invoked for that purpose it will be held void.” 6 Tex.Jur.2d § 20, et seq., pp. 56, 57, 58; citing Scottish Union & National Insurance Co. v. Clancy, 71 Tex. 5, 8 S.W. 630; American Central Insurance Co. v. Bass, 90 Tex. 380, 38 S.W. 1119; Quciroli v. Whitesides, Tex.Civ.App., 206 S.W. 122; Dozier v. City of Gatesville, Tex.Civ.App., 4 S.W.2d 131; International Brotherhood of Electrical Workers, Local Union No. 59, A.F.L. v. Whitley Elec. Service Co., Tex.Civ.App., 278 S.W.2d 560; Tejas Development Co. v. McGough Bros., 5 Cir., 165 F.2d 276. Appellees seek to distinguish above cases, stating that, in some there was no condition precedent clause or that the arbitration coverage here is limited to certain types of disputes. However, such limitations will be later discussed. These cited cases are in harmony with our statutes on arbitration (Arts. 224 — 249, Vernon’s Ann. Civ.St.) And in this connection see 135 A.L.R., p. 79 headed “Validity of agreement to submit all future questions to arbitration”. On page 80 of 135 A.L.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Allstate County Mutual Insurance Co.
85 S.W.3d 193 (Texas Supreme Court, 2002)
L. H. Lacy Co. v. City of Lubbock
546 S.W.2d 373 (Court of Appeals of Texas, 1976)
Standard Fire Insurance Company v. Fraiman
514 S.W.2d 343 (Court of Appeals of Texas, 1974)
Mamlin v. Susan Thomas, Incorporated
490 S.W.2d 634 (Court of Appeals of Texas, 1973)
Huntington Corp. v. Inwood Construction Co.
472 S.W.2d 804 (Court of Appeals of Texas, 1971)
Murray v. United States Fidelity and Guaranty Co.
460 S.W.2d 212 (Court of Appeals of Texas, 1970)
Carpenter v. North River Insurance Company
436 S.W.2d 549 (Court of Appeals of Texas, 1968)
Inwood Construction Co. v. Huntington Corp.
400 S.W.2d 372 (Court of Appeals of Texas, 1965)
Arrington v. El Paso Natural Gas Co.
233 F. Supp. 522 (W.D. Oklahoma, 1964)
O'MEARA v. Texas Gas Transmission Corp.
230 F. Supp. 788 (N.D. Illinois, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
348 S.W.2d 442, 1961 Tex. App. LEXIS 1851, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huntington-corp-v-inwood-construction-co-texapp-1961.