Inwood Construction Co. v. Huntington Corp.

400 S.W.2d 372
CourtCourt of Appeals of Texas
DecidedDecember 7, 1965
Docket7665
StatusPublished
Cited by3 cases

This text of 400 S.W.2d 372 (Inwood Construction Co. v. Huntington Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Inwood Construction Co. v. Huntington Corp., 400 S.W.2d 372 (Tex. Ct. App. 1965).

Opinion

CHADICK, Chief Justice.

This is a suit for damages occasioned by the breach of a construction contract. The judgment entered in the trial court is reversed and the case remanded for retrial.

Huntington Corporation and Inwood Construction Company, a corporation, entered into a cost-plus contract that obligated Inwood to construct buildings and facilities, including paved parking areas, at sites ties, including paved parkink areas, at sites in Texarkana, Marshall, and Vernon, Texas, under development as shopping centers. This action is concerned only with the paving at Texarkana and Marshall. Huntington as plaintiff sued Inwood, and that company’s performance bond surety, Trinity Universal Insurance Company, as defendants. The trial petition alleged that the paving at Texarkana and Marshall was not constructed in accordance with plans and specifications, and specified fourteen particulars in which the contract was violated.

Huntington’s petition alleged that notice was served upon Inwood of “the complete failure of the paving to meet plans and specifications at the Marshall and Texar-kana sites; of the absence in the paving at the Marshall and Texarkana sites of good and workmanlike performance; of the failure of Inwood as contractor to furnish its best skill and judgment in the paving at Marshall and Texarkana sites; of the failure of Inwood to furnish efficient superintendence during the paving at the Marshall and Texarkana sites; of the failure of In-wood to secure the paving work’s execution in the best and soundest way and at the most expeditious and economical manner consistent with the interest of Huntington Corporation; and the violation by the defendant Inwood of the trust and confidence placed in Inwood under the terms of the contract.” Coupled with the quoted notice is the further allegation that demand was made upon Inwood to reimburse Huntington $52,383.36, the amount Huntington paid for the two paving jobs, less credits aggregating $7,733.12 that Huntington acknowledged as due to Inwood.

The jury determined by answer to the several special issues submitted to it that Inwood failed to either fully or substantially “construct and deliver” asphaltic concrete and flexible base as specified in the contract at the Texarkana site. It found *374 the reasonable cost of remedying defects and omissions that would put the paving at the Texarkana project into conformity with specifications would total $17,460.00. The jury’s findings referable to the Marshall job were similar except a finding that In-wood substantially performed its contract to construct and deliver asphaltic concrete as specified and that the reasonable cost at Marshall of remedying defects, etc., would be $34,740.00. The trial court judgment allowed Inwood a stipulated offset of $9,953.57 and awarded Huntington a recovery of $42,246.43, with interest from the judgment date.

The foregoing summary leaves unmentioned much of the record containing a transcript of 322 pages, a statement of facts in 8 volumes, an excess of 100 exhibits, with briefs in proportion. Other explanations will be added as the opinion progresses. The adequacy of the measure of damages used in submitting this case to the jury is the paramount question for decision.

The case was submitted to the jury on the theory that the appropriate measure of damage is the reasonable cost of remedying defects and omissions in the asphaltic concrete and flexible base so as to bring the paving into conformity with contractual specifications. The jury was instructed to apply this measure of damage if it found Inwood failed to fully perform its contractual obligations in every detail, and regardless of whether Inwood’s performance was substantial or less than substantial. It has been recited that the jury found Inwood did not fully perform nor substantially perform except as to the asphaltic concrete at the Marshall site.- The jury was not required to separately ascertain the cost of bringing the Marshall asphaltic concrete up to specifications. The concrete that the jury found to substantially conform was laid over a flexible base, which was found not to substantially conform, and became the outer surface and binding agent of the pavement. Suggestion is not made how the Marshall base might be remedied without first destroying the asphalt surface. Testimony was introduced that paving as specified at both sites could be accomplished only by completely removing that constructed by Inwood and beginning anew.

No effort will be made to reconcile or choose between theories expressed by various Texas courts and those of other jurisdictions bearing upon the measure of damage problem as the Supreme Court performed that task in Hutson v. Chambless, 157 Tex. 193, 300 S.W.2d 943. The opinion in the case by Chief Justice Hickman in part sayss

“Our study of the involved record in this case has convinced us that one question of law is decisive of the character of judgment which should be rendered here, and our statement will be limited to the essential facts relevant to that question. That decisive question is the proper rule for measuring the damages for the breach of a contract to construct a house.”

Further along the opinion pronounced the general rule applicable in the absence of substantial performance of a building contract in this manner, to-wit:

“ * * * It is stated by the Supreme Court of Washington in White v. Mitchell, 123 Wash. 630, 213 P. 10, 13, in this language:
* * * Generally, where there has not been * * * substantial performance, the measure of the owner’s damage is the difference between the value of the building as constructed and its value had it been constructed in accordance with the contract. Such a recovery would be just to both parties. It is manifest that to measure the owner’s damage by the cost necessary to make the building conform to the contract would often be an injustice, because in many instances such cost would amount to almost as much as the original contract price.’
“That rule was followed in Totten v. Houghton, Tex.Civ.App., 2 S.W.2d 530, *375 no writ history, and authorities therein cited. It is announced in practically the same language in 9 American Jurisprudence, Building and Construction Contracts, Sec. 43, p. 33. Many authorities supporting the rule are annotated in 23 A.L.R. 1436, 38 A.L.R. 1383, and 65 A. L.R. 1298.”

Huntington endeavors to justify the submission of damages as made on three grounds. These grounds will next be discussed in order.

The Parties Contracted for A Rule of Damage.

Subdivision XIV of the Construction Contract reads:

“Any cost due to the negligence of the CONTRACTOR or anyone directly employed by him either for the making good of defective work, disposal of material wrongly supplied, making good of damage to property, or excess costs for material or labor, or otherwise, shall be borne by the CONTRACTOR, and the OWNER may withhold money due the CONTRACTOR to cover any such cost already paid by him as a part of the cost of the work.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A. B. C. Truck Rental & Leasing Co. v. Pletz
540 S.W.2d 532 (Court of Appeals of Texas, 1976)
Huntington Corp. v. Inwood Construction Co.
472 S.W.2d 804 (Court of Appeals of Texas, 1971)
Goad-Boles Motors, Inc. v. Victoria Paving Co.
408 S.W.2d 943 (Court of Appeals of Texas, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
400 S.W.2d 372, Counsel Stack Legal Research, https://law.counselstack.com/opinion/inwood-construction-co-v-huntington-corp-texapp-1965.