Hutson v. Chambless

300 S.W.2d 943, 157 Tex. 193, 1957 Tex. LEXIS 564
CourtTexas Supreme Court
DecidedApril 3, 1957
DocketA-6155
StatusPublished
Cited by40 cases

This text of 300 S.W.2d 943 (Hutson v. Chambless) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hutson v. Chambless, 300 S.W.2d 943, 157 Tex. 193, 1957 Tex. LEXIS 564 (Tex. 1957).

Opinions

Mr. Chief Justice Hickman

delivered the opinion of the Court.

Our study of the involved record in this case has convinced us that one question of law is decisive of the character of judgment which should be rendered here, and our statement will be limited to the essential facts relevant to that question. That [195]*195decisive question is the proper, rule for measuring the damages for the breach of a contract to construct a house.

Hutson, a building contractor, entered into a contract with Chambless for the construction of a house according to certain plans and specifications. The contract price was $16,750.00, for which Chambless executed his note to Hutson. Later, the parties agreed that Chambless would paint the house and $900.00 was deducted from the contract price on that account. After he had made two payments on the note, Chambless sued Hutson for damages for breach of contract, alleging that he did not build the house according to FHA requirements as specified in the contract; that he failed to construct the house in a workmanlike manner; and that he deviated from the plans and specifications. Hutson by cross-action sued for the balance due on the note, with foreclosure of the lien securing the same, and for certain extras. In the trial court judgment was rendered for Hutson on the note and for certain extras, but judgment was rendered in favor of Chambless for damages in the sum of $6,000.00, which amount was offset against Hutson’s recovery. The trial court’s judgment was affirmed by the Court of Civil Appeals. 295 S.W. 2d 723.

Chambless alleged twenty separate and distinct particulars in which Hutson breached his contract. Some of these were in defective workmanship and others in deviations from the specifications. The defects in workmanship and deviations are not classified as such, but are commingled in the allegations of the petition. Adding the sums alleged to be required to remedy the various defects and deviations, including $100.00 for clearing the lot of debris, the result was $9,015.00, for which Chambless sued. As we construe the petition, the damages alleged for defective workmanship amount to but a few hundred dollars. Most of the damages claimed resulted from alleged deviations from the specifications or the furnishing of inferior material. In answer to special issues the jury found that the defects in workmanship could be remedied without impairing the building as a whole at the reasonable cost of $6,000.00. It next found that the reasonable market value of the building in its then condition was $9,650.00, and that its reasonable cash market value, if constructed according to the contract, would have been $16,750.00, the difference between the two values being $7,100.00. The jury then found that Hutson deviated from the terms of the contract; that some deviations, not specified, were with the consent of Chambless and others, also not specified, were not with his consent; and that the reasonable cost of [196]*196remedying the deviations not consented to would be $6,000.00. As noted above, Chambless alleged that all defects in workmanship and deviations could be remedied for $9,015.00. The jury found that it would require $6,000.00 to remedy the defects and $6,000.00 to remedy the deviations, making a total of $12,000.00. The court rendered judgment for $6,000.00 for the damages sustained by Chambless. Whether the damages were for remedying defects in workmanship or for remedying deviations does not appear in the record. This much is clear: Judgment was not rendered for the difference in value between the building as constructed and its value had it been constructed according to contract, which the jury found to be $7,100.00.

Various objections were urged below and are brought forward here to the manner of submission of the special issues relating to the cost of remedying the defects and deviations, but under our view of the controlling question presented by the record we find it unnecessary to consider them. This for the reason that they should not have been submitted at all. It is our view that, assuming that Hutson breached the contract as alleged, and as found by the jury, the correct measure of damages suffered by Chambless is the difference in value, if any, between the house as constructed and its value had it been consructed according to contract. As noted above, the jury found in answer to special issues that the defects in workmanship in the building could be remedied without impairing the building as a whole, but there was not a like finding as to deviations. The question of whether the deviations could be remedied without impairing the physical structure of the building was not submitted to the jury.

Hutson objected to the submission of Special Issues Nos. 1, 2 arid 3, in answer to which the jury found that the defects in workmanship could be remedied without impairing the building as a whole at a reasonable cost of $6,000.01). One objection thereto was that they submitted an incorrect measure of damages; that the correct measure of damages would be the difference, if any, in value of the building as constructed and its value had it been constructed according to contract. He does not bring that question here in that precise form, but his first point is that it was error to submit the case on three theories. Under that point it is argued that the charge should have submitted special issues on only one theory of recovery, namely, the difference in value, if any, between the building as constructed and its value had it been constructed according to contract. We have concluded that the point and the argument thereunder [197]*197present the question of whether the court should have submitted any special issues on the cost of remedying defects or deviations. It seems clear that under the pleadings of Chambless there was one, and only one, correct measure of damages.

To remedy the alleged defects and deviations according to the pleadings of Chambless would require not only the expenditure of a large sum of money, but the rebuilding of the foundation, the tearing down of the brick veneer and rebuilding it with better materials, the rebuilding of the den at a cost of more than $3,000.00, and removing and replacing the tile in the bathroom, to mention some of the alleged requirements. It is not claimed that Hutson intentionally deviated from the contract. On the contrary, it was alleged that it was through in-advertance. Under these facts, the rule for measuring the damages is well settled. It is stated by the Supreme Court of Washington in White v. Mitchell, 213 P. 10, in this language:

“Where it is necessary, in order to make the building comply with the contract, that the structure, in whole or in material part, must be changed, or there will be damage to parts of the building, or the expense of such repair will be great, then it cannot be said that there has been a substantial performance of the contract. Generally, where there has not been such substantial performance, the measure of the owner’s damage is the difference betwen the value of the building as con-structd and its value had it been constructed in accordance with the contract. Such a recovery would be just to both parties. It is manifest that to measure the owner’s damage by the cost necessary to make the building conform to the contract would often be an injustice, because in many instances such cost would amount to almost as much as the original contract price.”

That rule was followed in Totten v. Houghton, 2 S.W. 2d 530, no writ history, and authorities therein cited.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ashford Partners, Ltd. v. Eco Resources, Inc.
401 S.W.3d 35 (Texas Supreme Court, 2012)
RAJ Partners, Ltd. v. Darco Construction Corp.
217 S.W.3d 638 (Court of Appeals of Texas, 2006)
Progressive Insurance v. Southern Star International, Inc.
6 Am. Samoa 3d 112 (High Court of American Samoa, 2002)
Transamerica Insurance Co. of Texas v. Green
797 S.W.2d 171 (Court of Appeals of Texas, 1990)
Chapa v. Reilly
733 S.W.2d 236 (Court of Appeals of Texas, 1986)
Jim Walter Homes, Inc. v. Gonzalez
686 S.W.2d 715 (Court of Appeals of Texas, 1985)
Miller v. Dickenson
677 S.W.2d 253 (Court of Appeals of Texas, 1984)
Jim Walter Homes, Inc. v. Valencia
679 S.W.2d 29 (Court of Appeals of Texas, 1984)
Precision Homes, Inc. v. Cooper
671 S.W.2d 924 (Court of Appeals of Texas, 1984)
Turner, Collie & Braden, Inc. v. Brookhollow, Inc.
642 S.W.2d 160 (Texas Supreme Court, 1982)
Sawyer v. Fitts
630 S.W.2d 872 (Court of Appeals of Texas, 1982)
Jim Walter Homes, Inc. v. Mora
622 S.W.2d 878 (Court of Appeals of Texas, 1981)
Turner, Collie & Braden, Inc. v. Brookhollow, Inc.
624 S.W.2d 203 (Court of Appeals of Texas, 1981)
Beeman v. Worrell
612 S.W.2d 953 (Court of Appeals of Texas, 1981)
Jim Walter Homes, Inc. v. Castillo
616 S.W.2d 630 (Court of Appeals of Texas, 1981)
Fidelity & Deposit Co. of Maryland v. Stool
607 S.W.2d 17 (Court of Appeals of Texas, 1980)
Greene v. Bearden Enterprises, Inc.
598 S.W.2d 649 (Court of Appeals of Texas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
300 S.W.2d 943, 157 Tex. 193, 1957 Tex. LEXIS 564, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hutson-v-chambless-tex-1957.