Hutson v. Chambless

295 S.W.2d 723, 1956 Tex. App. LEXIS 1953
CourtCourt of Appeals of Texas
DecidedNovember 8, 1956
Docket3395
StatusPublished
Cited by4 cases

This text of 295 S.W.2d 723 (Hutson v. Chambless) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hutson v. Chambless, 295 S.W.2d 723, 1956 Tex. App. LEXIS 1953 (Tex. Ct. App. 1956).

Opinion

McDONALD, Chief Justice.

This case involves a controversy over the construction of a house. Parties will be referred to as in the Trial Court. Defendant Hutson, a building contractor, agreed to build plaintiff Chambless a house for $16,750 (less $900 and agreement plaintiff to do the painting). The parties entered into a written contract, and as part of the agreement there were written specifications and a set of plans. Plaintiff contended that defendant did not build the house according to the contract, and filed this suit for damages for breach of contract. Plaintiff alleged that defendant did not construct the house in accordance with F.H.A. requirements (as called for by the contract) ; deviated from plans and specifications; and failed to construct the house in a workmanlike manner. Plaintiff further alleged that the defects and deviations could be corrected for $9,015, and asked judgment for this amount. Defendant answered by general denial; alleged there were no substantial deviations from the contract except such as were agreed to or waived by plaintiff; and by way of cross action alleged that plaintiff owed $16,750, less $900 for painting, and less $9,500 which had been paid on the contract by plaintiff; and prayed for judgment against plaintiff for $6,804.25, interest and attorney’s fees, and for $338.30 for extras, and for foreclosure of lien on the property.

Trial was to a jury which, in answer to special issues submitted, found:

1) Defendant failed to construct the house in a workmanlike manner and in accord with minimum F.H.A. requirements.

2) The reasonable cost of remedying the defects in the house was $6,000.

3) That the defects in the house could be remedied without impairing the building as a whole.

4) The reasonable cash market value of the building in the condition it is now in is $9,650.

5) That the reasonable cash market value of the building, if constructed according to contract, would have been $16,750.

*726 6) Defendant deviated from the terms of the contract in construction of the house.

7, 8, 9, 9A) Some deviations were with plaintiff’s consent; and some deviations were made without plaintiff’s consent; that plaintiff by his conduct had not waived his rights to complain as to deviations he had not consented to.

9B) That the reasonable cost of changing deviations not' consented to or waived was $6,000.

10) That defendant, in the construction of the house, did not substantially comply with the contract.

11) That plaintiff and defendant agreed on certain “extras” to be done by defendant.

12) That defendant did certain extras..

13) That plaintiff owes defendant $303 for such extras performed.

The Trial Court entered a modified and corrected judgment on the foregoing verdict, finding that plaintiff was entitled to a recovery of $6,000; that plaintiff owed defendant a note for $16,750; less $900 credit for the painting; less $5,000 paid on such note; less $4,045.75 paid on the principal of such note; leaving a principal balance of $6,804.25 due on the note. The court further found defendant was due $303 for extras, making a total due defendant of $7,107.25. The court then credited such amount with the $6,000 allowed plaintiff and entered a judgment for defendant for $1,-107.25, plus attorney’s fees thereon in the sum of $110.72, such judgment of the Trial Court being for the total sum of $1,217.97 in favor of defendant and against plaintiff. The Trial Court further decreed foreclosure of the lien to satisfy the judgment, and taxed costs one-half against each party.

The defendant appeals, contending:

1)The Trial Court erred in submitting the case to the jury on three separate theories whereby the jury found: a) Defendant failed to construct the house in a workmanlike manner and that it would cost $6,-000 to remedy the defects; b) The.difference in value of the house as it was and what it would have been if constructed according to contract was $7,150; and c) The cost of changing deviations from the contract would amount to $6,000.

2) The Trial Court erred in submitting Issue No. 4 in the language used, and in submitting No. 5; and the evidence is insufficient to support the jury’s finding thereto.

3) The Trial Court erred in submitting Issues 1 and 2 whereby the jury were instructed to find what lump sum cost would be to change the 20 separate failures to perform the contract.

4) The Trial Court erred in submitting Issues 6, 7, 8, 9, 9A and 9B to the jury because the jury were instructed to find what the lump sum cost would be of changing deviations from the contract, and because the jury was not limited in its findings to material and substantial deviations.

5) The Trial Court erred in allowing plaintiff a recovery of $6,000 and in applying such as a credit on the note owed defendant, thereby reducing defendant’s recovery for attorney’s fees.

Reverting to defendant’s 1st contention— that the Trial Court erred in submitting the case to the jury on three separate theories, whereby the jury found: a) Defendant failed to construct the house in a workmanlike manner and it would cost. $6,000 to remedy the defects; b) The difference in the value of the house as constructed, and what it would have been if constructed ac-. cording to the contract was $7,150; c) The cost of changing unauthorized deviations from the contract would amount to $6,000.

From a review of the record we conclude that plaintiff plead and proved that the defendant contracted to build the house according to certain plans and specifications; to include workmanship which would *727 be in accordance with minimum F.H.A. requirements. Plaintiff's evidence reflects, among other things, that the vertical joints were not filled with mortar; no flashing under one window; some walls out of plumb; there were 12 weepholes; should have been 60; 48 head joints with visible openings; cracks in the mortar; room measurements not as called for by plans; foundation of insufficient strength; poor workmanship; inferior material; house turned down by F.H.A. because quality of construction and material did not meet minimum F.H.A. requirements. Plaintiff further plead and tendered evidence on some -20 separate items of failure of defendant to perform the contract which reflected the cost necessary to correct such failures to be $9,015. Defendant, on the other hand, admitted executing the building contract and specifications ; said he was not personally acquainted with F.H.A. requirements, and that he did not instruct the sub-contractors that the Rouse was to be built F.H.A. requirements. Some of the evidence in the record tended to indicate that the defects and deviations were so numerous and so serious that they could not be corrected without impairing the building as a whole. On the ■other hand, there was an abundance of evidence to the effect that the defects and deviations could be corrected by taking certain steps at a specified cost — and which tended to show that the defects were not such as would impair the building as a whole.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schmidt v. Kuper
324 S.W.2d 307 (Court of Appeals of Texas, 1959)
Loggins v. Gates
301 S.W.2d 525 (Court of Appeals of Texas, 1957)
Hutson v. Chambless
300 S.W.2d 943 (Texas Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
295 S.W.2d 723, 1956 Tex. App. LEXIS 1953, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hutson-v-chambless-texapp-1956.