Fidelity & Deposit Co. of Maryland v. Stool

607 S.W.2d 17, 1980 Tex. App. LEXIS 3936
CourtCourt of Appeals of Texas
DecidedSeptember 25, 1980
Docket1351
StatusPublished
Cited by37 cases

This text of 607 S.W.2d 17 (Fidelity & Deposit Co. of Maryland v. Stool) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. of Maryland v. Stool, 607 S.W.2d 17, 1980 Tex. App. LEXIS 3936 (Tex. Ct. App. 1980).

Opinion

McKAY, Justice.

On September 29, 1972, Dr. Newsom Stool entered into a standard AIA Construction Contract with Jess and Jack May-field d/b/a Mayfield Construction Company (hereinafter Mayfield) for the construction of a residence in San Antonio, Texas. The final contract price for the project was $120,335.00 with a time for completion of 200 days. Fidelity & Deposit Company of Maryland (hereafter F & D) issued payment and performance bonds on the project.

Dr. Stool financed the residence through the San Antonio Savings Association (hereinafter SASA) which agreed to lend Dr. Stool $90,000 toward cost of building a home at an interest rate of 7½%. SASA agreed that it would hold the 7½% interest commitment open until August, 1973. Because of the interest commitment deadline and interim financing costs, Dr. Stool and Mayfield added a provision to the construction contract that if Mayfield completed the residence in less than 200 days, Dr. Stool would pay Mayfield a bonus of $50.00 per day for every day prior to the 200 day period in which the residence was to be completed, but if Mayfield completed the residence in more than 200 days, $50.00 per day would be deducted from the contract price for a period not to exceed 60 days. In August, 1973, when the loan commitment was about to expire, the residence was approximately 75% complete but SASA extended the loan commitment to September 1, 1973. However, on September 1, 1973, the residence was still incomplete, and the interest rate was raised to 8%. On November 29, 1973, the loan was closed.

During September, 1973, it became apparent that Dr. Stool was dissatisfied with the quality of the work, and during that month, an extensive punch list was compiled of various items of work that had yet to be completed or were unsatisfactorily completed. From about December 26,1973, Dr. Stool occupied the residence, and during January, 1974, the majority of the items of work on the list was completed; however, Dr. Stool was still dissatisfied with the condition of the residence and refused to tender the balance due under the contract. On September 30, 1974, Mayfield instituted an action to recover the balance due under the contract in the amount of approximately $4,000.00. Dr. Stool filed a counterclaim against Mayfield and F & D alleging that the contract had not been substantially performed, that the construction of the residence was not done in a good and workmanlike manner, that the delay in completion of the residence caused him to pay a greater rate of interest, and that he should recover damages in the sum of $60,000.00 which was the reasonable and necessary cost of repairing the defective work.

During the period of late 1974 through March of 1978, both parties engaged in negotiations concerning the reasonable and necessary repairs to Dr. Stool’s home. In March, 1978, Mayfield finally refused to perform any work on the residence, and on May 22, 1978, Dr. Stool entered into a contract with S & H Remodeling Company of San Antonio. In that contract S & H Remodeling agreed to remedy the defects in the residence for the sum of $57,660.04. At the time of trial, all of the work had not yet been completed.

On January 9, 1979, trial was had before a jury, and judgment was rendered against Mayfield for the reasonable and necessary cost to correct the defects in the residence and for damages resulting from Mayfield’s failure to complete the residence by the contract date. Additionally, judgment was rendered in favor of F & D against May-field for indemnity of any and all amounts which F & D would be required to pay to Stool as a result of the judgment. Both Mayfield and F & D filed motions for judgment non obstante veredicto and for a new trial, all of which were denied. Appellants have duly perfected this appeal.

The determinative issue in this appeal concerns the proper measure of damages for the breach of a construction contract. *20 In twenty-one points of error appellants complain of the measure of damages submitted to the jury by the trial court.

In response to special issues the jury found that:

1. The contract of September 29, 1972, to construct the Newsom Stool home was not substantially performed by Mayfield Construction Company. 1
2. The Mayfield Construction Company failed to construct Newsom Stool’s family home in a good and workmanlike manner pursuant to the contract of September 29, 1972.
3. Mayfield Construction Company failed to correct the defects caused by its failure to construct the family home for Newsom Stool in a good and workmanlike manner.
4. The reasonable and necessary cost to correct the defects in the construction of Newsom Stool’s family home in March, 1978, was $35,-381.80.
5. Newsom Stool suffered damages in the amount of $3,794.96 for increased interest expense as a result of the Mayfield Construction Company’s failure to complete the family home by June 28, 1973.

6,7 & 8. Appellant Fidelity & Deposit Company of Maryland should not be awarded its attorney’s fees for litigation in the trial court or appeal to the court of civil appeals or appeal to the Supreme Court of Texas.

Appellants contend that under the record the correct measure of damages was the difference in value of the building as constructed and its value had it been constructed according to the contract.

Restatement of Contracts, § 346 (1932), states that where the contractor breaches the contract because of defective or unfinished construction, the owner may recover:

“(i) the reasonable cost of construction and completion in accordance with the contract, if this is possible and does not involve unreasonable economic waste; or
(ii) the difference between the value that the product contracted for would have had and the value of the performance that has been received by the plaintiff, if construction and completion in accordance • with the contract would involve unreasonable economic waste.” § 346 at 573.

Texas courts have long held that where defects in construction of a building may be remedied, the measure of damages for the owner is the cost of such remedy or repair, but where such defects cannot be remedied without injury to the structural efficiency of the building as a whole, the measure of damages is the difference between the value of the building as constructed and its value had it been constructed according to the contract. Atkinson v. Jackson Bros., 259 S.W. 280, 284 (Tex.Civ.App.-Austin 1924), 270 S.W. 848, 850 (Tex.Comm’n App. 1925, holding approved); McBurnett v. Smith & McCallin, 286 S.W. 599, 601 (Tex.Civ.App.-Austin 1926, no writ); Totten v. Houghton, 2 S.W.2d 530, 534 (Tex.Civ.App.-Eastland 1927, no writ); Tucker v. Northcutt, 248 S.W.2d 750, 751 (Tex.Civ.App-Waco 1952, no writ); Builders Supply, Inc. v. Anderson, 281 S.W.2d 649, 650-1 (Tex.Civ.App.-San Antonio 1955, writ ref’d n. r. e.). Usually, a finding of substantial per *21

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Ply, Inc. v. ARCI, Ltd.
Court of Appeals of Texas, 2019
Gulf Liquids New River Project, LLC v. Gulsby Engineering, Inc.
356 S.W.3d 54 (Court of Appeals of Texas, 2011)
GARZA DE ESCABEDO v. Haygood
283 S.W.3d 3 (Court of Appeals of Texas, 2009)
TA Operating Corp. v. Solar Applications Engineering, Inc.
191 S.W.3d 173 (Court of Appeals of Texas, 2006)
Lone Star Ford, Inc. v. McCormick
838 S.W.2d 734 (Court of Appeals of Texas, 1992)
Bank One, Texas, N.A. v. Taylor
970 F.2d 16 (Fifth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
607 S.W.2d 17, 1980 Tex. App. LEXIS 3936, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-of-maryland-v-stool-texapp-1980.