Tucker v. Northcutt

248 S.W.2d 750, 1952 Tex. App. LEXIS 2105
CourtCourt of Appeals of Texas
DecidedApril 17, 1952
Docket3013
StatusPublished
Cited by11 cases

This text of 248 S.W.2d 750 (Tucker v. Northcutt) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tucker v. Northcutt, 248 S.W.2d 750, 1952 Tex. App. LEXIS 2105 (Tex. Ct. App. 1952).

Opinion

HALE, Justice.

Appellant, a building contractor, entered into a mechanic’s lien contract with appel-lees to build a house according to certain plans and specifications for $6,900. During the progress of the work appellees paid $3,450 to appellant but when the building was finally tendered to them they refused to accept the same or to make any further payment under the contract, upon the ground that the house had not been constructed in accordance with the plans and specifications agreed upon. Appellees then brought this suit against appellant as an action in trespass to try title and in the alternative, by way of a second count in their trial petition, they alleged that it would reasonably require $3,450 to complete the house according to the contract so as to meet the standard of ordinary good workmanship in the community and prayed that their land be cleared of the mechanic’s lien.

Appellant answered the first count in the petition of appellees with a plea of not guilty, the second count with certain special exceptions and a general denial, and by way of cross-action he sought to recover the balance of $3,450 alleged to be due him under the mechanic’s lien contract and to foreclose his asserted lien on the premises in dispute. .

The case was tried before the court without a jury. The court expressly found in the judgment that the house was not •completed according to the contract and that it would reasonably require an additional expenditure. by appellees of $3,500 to complete the same in a good, workmanlike manner and in accordance with the plans and specifications agreed upon by the parties. The court accordingly decreed in the judgment that the note and mechanic’s lien held by appellant be can-celled and that appellant be denied any recovery on his cross-action.

Under the three points upon which his appeal is predicated, appellant says in substance that the trial court erred (1) in applying an incorrect, legal measure of the damages, sustained by appellees, (2) in finding that it would reasonably require an additional expenditure of $3,500 to complete the building of the house in. accordance with the plans and specifications agreed upon, and (3) in overruling his special exceptions to the pleadings of ap-pellees.

Appellant contends that the correct measure of the damages suffered by appellees herein is not the amount of money which would be reasonably required to complete the house according to the contract but is the difference between the value of the house as constructed and its value.had it been constructed according to the plans and specifications agreed upon by the parties. In support of his contention he cites the following cases: Atkinson v. Jackson Bros., Tex.Com.App., 270 S.W. 848, 38 A.L.R. 1377; McBurnett 'v. Smith & McCallin, Tex.Civ.App., 286 S.W. 599; Totten v. Houghton, Tex.Civ. App., 2 S.W.2d 530; Roberts v. Roberts, Tex.Civ.App., 27 S.W.2d 880. The. general rule announced in these cases is that the correct measure of damages resulting from the breach of a building contract is ordinarily the reasonable cost of remedying the defects which constitute a breach of the contract, provided such contract has been “substantially performed” and the de- . fects in its performance can be remedied without impairing the building as a whole; but if such defects cannot be remedied without impairing the structural efficiency of the building, the measure of the damages is the differenqe between the value of the *752 building as constructed and its value had it been constructed according to plans and specifications. However, under the record before us in this case, we cannot say the court below applied an incorrect legal measure of the damages sustained by ap-pellees or that the court erred in denying any recovery to appellant on his cross-action.

In the absence of any express finding to the contrary, this court must presume that the trial court found all issuable facts tendered by the evidence in such manner as to support the judgment. Under the conflicting evidence adduced by the respective parties, it' appears' to us that the facts determinative of whether the contract was or was not fully performed, or as to whether or not it was ■ substantially performed, as well as'the nature and extent of the' defects, if any, in the performance thereof, were issuable." The trial court found that the house and improvements had not been completed in substantial compliance with .the plans and specifications, but he made no express finding as to whether the defects in the performance thereof could or could not be remedied without impairing the structural efficiency of the building. Therefore, for the purposes of this appeal we must assume that the court found by implication that the nature and extent of the defects in the performance of the contract were such as could be remedied by the additional expenditure of $3,500 without impairing the structural efficiency of the building as a whole.

Furthermore, -the mechanic’s lien contract involved in this suit provides in part as follows: “It is further agreed that a failure to complete said improvements, or failure to complete the same according to contract, shall not defeat said indebtedness and lien, but in such case the indebtedness and lien upon said premises and improvements shall exist in favor of said party of the second part, his heirs and assigns, for said contract price, less such an amount as would be reasonably necessary to complete said improvements according to said plans and specifications.” Since the measure of appellant’s recovery, if any, and conversely, the measure of ap-pellees’ damages, if any, was thus fixed by agreement of the parties, we see no valid reason why either party should be heard to complain because the court in disposing of the conflicting rights asserted under the contract applied the measure of recovery and damages which both parties had mutually agreed upon. Harrop v. N-ational Loan & Investment Co., Tex.Civ.App., 204 S.W. 878, (er. ref.) ; Galbraith-Foxworth Lumber Co. v. Long, • Tex.Civ.App., 5 S.W. 2d 162, (er. ref.) ; North American Bldg. & Loan Ass’n v. Bell, Tex.Civ.App., 88 S.W.2d 633; Mathes v. Williams, Tex. Civ.App., 134 S.W.2d 853.

Under the second point in his brief, appellant says the finding of the trial court to the effect that appellees’ damages were $3,500 was against the great wéight and preponderance of the evidence to such extent as manifestly to be wrong. We cannot agree with this contention. None of "the witnesses tendered'by appellant testified what it would cost to complete the building according to the contract, their ' testimony being in substance that the building had been completed in frill compliance with the plans and- specifications agreed upon. On the other hand, W. E. Darden, Roy Driver, E. O. Moser, R. M. Brook-shire and others testified on behalf of ap-pellees that the building had not been constructed in conformity with reasonable standards of good workmanship and they testified to the amount of money which in their opinion would be reasonably required to remedy such defects and complete the building according to such standards and 'the terms of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rita Mary Gause v. Thomas X. Gause
496 S.W.3d 913 (Court of Appeals of Texas, 2016)
TA Operating Corp. v. Solar Applications Engineering, Inc.
191 S.W.3d 173 (Court of Appeals of Texas, 2006)
Fidelity & Deposit Co. of Maryland v. Stool
607 S.W.2d 17 (Court of Appeals of Texas, 1980)
Volkman v. Eakman
496 S.W.2d 752 (Court of Appeals of Texas, 1973)
King v. King
393 S.W.2d 421 (Court of Appeals of Texas, 1965)
Cooper Concrete Company v. Hendricks
386 S.W.2d 221 (Court of Appeals of Texas, 1965)
Arrow Chemical Corporation v. Anderson
386 S.W.2d 309 (Court of Appeals of Texas, 1965)
Buhler v. McIntire
365 S.W.2d 237 (Court of Appeals of Texas, 1963)
Loggins v. Gates
301 S.W.2d 525 (Court of Appeals of Texas, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
248 S.W.2d 750, 1952 Tex. App. LEXIS 2105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tucker-v-northcutt-texapp-1952.