Volkman v. Eakman

496 S.W.2d 752, 1973 Tex. App. LEXIS 2893
CourtCourt of Appeals of Texas
DecidedJune 8, 1973
Docket17412
StatusPublished
Cited by9 cases

This text of 496 S.W.2d 752 (Volkman v. Eakman) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Volkman v. Eakman, 496 S.W.2d 752, 1973 Tex. App. LEXIS 2893 (Tex. Ct. App. 1973).

Opinion

OPINION

BREWSTER, Justice.

The plaintiff, J. C. Volkman (contractor) sued the defendants, James L. Eak-man and wife, Jannette Eakman (owners) for damages for an alleged breach of a mechanic’s lien contract, attorney’s fees, foreclosure of the mechanic’s lien, punitive damages, and, in the alternative, on quantum meruit for damages.

The Eakmans filed an answer and a cross-action seeking to cancel the lien involved and to recover damages from Volk-man for an alleged breach of the mechanic’s lien contract in failing to build the house involved in a good and workmanlike manner.

The trial was before a jury which returned a verdict for the Eakmans. On receipt of this verdict the trial court rendered judgment that plaintiff, Volkman, take nothing by his suit and that the Eak-mans recover $300.00 on their cross-action from Volkman. The judgment also canceled the mechanic’s lien involved and removed it as a cloud on the title to the Eak-man land. All other relief sought by either party was denied. The plaintiff has appealed from the judgment and the Eak-mans urge cross-points contending that the court erred in only awarding them a judgment for $300.00 against the plaintiff on their cross-action instead of a larger sum.

The undisputed evidence shows that Volkman and the Eakmans entered into a mechanic’s lien contract wherein Volkman agreed to build a three bedroom brick veneer dwelling on six acres of land owned by the Eakmans. It was agreed that the house would be built in a good and workmanlike manner in accordance with the plans and specifications agreed on by the parties. For this Volkman was to be paid $24,950.00. Liens were given to secure the payment of a note to Volkman in this amount.

The following facts are also undisputed: Volkman’s men began construction of the foundation of the house; they set the forms for the foundation and poured the concrete for the piers and beams; when they finished the first day of work on this foundation the Eakmans saw the foundation as it had been constructed to that point and became very alarmed about it; and they inquired of Volkman as to what else he planned to do to the foundation before it would be finished and Volkman, in substance, advised that it would be prettied up by grouting it; and it was undisputed that the grouting would, to some extent, help the appearance of the foundation but would not add to its strength. The Eak-mans then advised Volkman, in substance, that if adding grout to the foundation was all he planned to do to remedy what they deemed to be many defects that he should take his belongings and get off of the property. Volkman, at the insistence of the Eakmans, did thereafter quit the job and he then filed this suit.

Plaintiff’s first three points are argued together. They are in substance that the court erred: (1) in failing to render judgment for plaintiff notwithstanding the verdict because it is undisputed that defendants kept plaintiff from substantially performing the contract; (2) in failing to disregard the jury’s answer to Issue No. 2 finding that Volkman was not prevented from substantial performance of the contract by defendants’ conduct because defendants admitted they ran plaintiff off *755 the job thus preventing him from substantially performing; and (3) in failing to disregard this same jury finding, because since defendants admitted that they ran plaintiff off the job, there is no evidence to support the jury’s answer to Issue No. 2.

We overrule plaintiff’s first three points of error.

Issue No. 1 inquired: “Do you find from a preponderance of the evidence that there was substantial performance by J. C. Volkman of the contract, as evidenced by the plans and specifications, in the partial construction of the foundation in question?” The jury answered: “There was not.”

Issue No. 2 was submitted conditionally on a “There was not” answer to Issue No. 1 and it inquired: “Do you find from a preponderance of the evidence that J. C. Volkman was prevented from the substantial performance, ... by the acts and conduct of the defendants?” The jury answered: “He was not.”

The court’s charge defined “substantial performance” as meaning “there has been no wilful departure from the terms of the agreement, and no omission in essential points, and that the agreement has been honestly and faithfully performed in its material and substantial parts, and the only variance from a strict and literal performance consists of technical or unimportant details, and that the omissions and defects could have been remedied without impairing the use for which the foundation was intended.”

The record reveals that Issues Nos. 1 and 2 and the definition of substantial performance were placed in the charge at plaintiff’s request.

There is much evidence in the record that supports the jury’s finding that plaintiff Volkman did not substantially perform the contract in his partial construction of the foundation in question.

Some of the strongest of such evidence are the pictures of this foundation introduced by defendants showing how it looked at the time the work was stopped.

Plaintiff and his employees admitted that they planned to do nothing further to the foundation except to grout it and the evidence showed that this would only aid the looks some and would add nothing to the strength of the foundation.

The undisputed evidence showed that the Eakmans in no way interfered with the work done by Volkman in the partial construction of the foundation that is inquired about in Issue No. 1. It was not until that work was completed that the Eakmans became alarmed and intervened. The jury’s answer to Issue No. 1 thus established that prior to the time the Eakmans intervened to prevent further performance of the contract by Volkman, Volkman had already breached the contract by not substantially performing it in the partial construction of the foundation that he did build.

Plaintiff’s first three points of error are based on the erroneous assumption that the undisputed evidence shows that the Eak-mans prevented him from substantially performing the building of the part of the foundation that Volkman did build.

This assumption is wrong and it is contrary to the jury’s finding in answer to Issue No. 2, which finding has strong support in the evidence.

From what we have said, it follows that plaintiff’s contention, made in his first three points, that it was the conduct of the Eakmans that prevented Volkman from substantially performing the contract, is without merit and that those three points should be overruled.

Plaintiff’s point of error No. 4 is that the Court erred in failing to consider the sums spent by plaintiff for labor and materials in the construction of items about which the Eakmans had no complaint.

We overrule this point.

*756 The burden was on the plaintiff to prove and to obtain proper jury findings establishing the facts necessary to entitle him to recover for such items. The record does not show that plaintiff requested that the court submit any issues to the jury presenting this feature of the case. Volk-man was the plaintiff, an interested party, and his testimony about this part of the case, even if undisputed, only created fact issues.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TA Operating Corp. v. Solar Applications Engineering, Inc.
191 S.W.3d 173 (Court of Appeals of Texas, 2006)
Bookout v. Bookout
165 S.W.3d 904 (Court of Appeals of Texas, 2005)
Donald Wesley v. State
Court of Appeals of Texas, 2005
Fidelity & Deposit Co. of Maryland v. Stool
607 S.W.2d 17 (Court of Appeals of Texas, 1980)
Estate of Arrington v. Fields
578 S.W.2d 173 (Court of Appeals of Texas, 1979)
Crawford Chevrolet, Inc. v. McLarty
519 S.W.2d 656 (Court of Appeals of Texas, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
496 S.W.2d 752, 1973 Tex. App. LEXIS 2893, Counsel Stack Legal Research, https://law.counselstack.com/opinion/volkman-v-eakman-texapp-1973.