Stonehill-PRM WC I, L.P. v. Chasco Constructors, Ltd., L.L.P. and Safeco Insurance Company of America

CourtCourt of Appeals of Texas
DecidedFebruary 11, 2009
Docket03-08-00494-CV
StatusPublished

This text of Stonehill-PRM WC I, L.P. v. Chasco Constructors, Ltd., L.L.P. and Safeco Insurance Company of America (Stonehill-PRM WC I, L.P. v. Chasco Constructors, Ltd., L.L.P. and Safeco Insurance Company of America) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stonehill-PRM WC I, L.P. v. Chasco Constructors, Ltd., L.L.P. and Safeco Insurance Company of America, (Tex. Ct. App. 2009).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-08-00494-CV

Stonehill-PRM WC I, L.P., Appellant

v.

Chasco Constructors, Ltd., L.L.P. and Safeco Insurance Company of America, Appellees

FROM THE DISTRICT COURT OF TRAVIS COUNTY, 200TH JUDICIAL DISTRICT NO. D-1-GN-06-002741, HONORABLE MARGARET A. COOPER, JUDGE PRESIDING

MEMORANDUM OPINION

In this construction contract dispute, appellant Stonehill-PRM WC I, L.P.,

(“Stonehill”) appeals the district court’s judgment in favor of appellees Chasco Constructors, Ltd.,

L.L.P. (“Chasco”) and Safeco Insurance Company of America (“Safeco”). In seven issues, Stonehill

contends the district court erred when it determined the measure of damages, when it excluded

testimony from two of Stonehill’s experts and one of its owners as to the value of the proposed

construction, when it excluded evidence of the cost to complete the construction project, and when

it refused to admit an alleged copy of the contract between the parties. Because we conclude the

district court did not err in its determination of the measure of damages and that any error in the

challenged evidentiary rulings was not reversible error, we affirm the district court’s judgment. FACTUAL AND PROCEDURAL BACKGROUND

The Project

In the summer of 2005, Stonehill hired the architectural firm Page Southerland Page

Architects and Engineers (“PSP”) to design a 156-unit student housing facility (the “Project”) for

property that Stonehill owned near the University of Texas in Austin, Texas. In approximately

September 2005, Stonehill began negotiations with Chasco for Chasco to be the contractor for the

Project. The proposed scope of work included demolishing the existing structure on the property.

Chasco provided several different budgets to Stonehill including a line-item budget of $16,638,030

in December 2005. The December 2005 budget was based upon design and development drawings

that PSP issued in October 2005. PSP also issued permit plans for the Project on February 6, 2006,

and an “Addendum #1” to the permit plans in March 2006.

Stonehill and Chasco executed a “Standard Form of Agreement Between Owner and

Contractor” dated February 22, 2006 (the “Contract”).1 The Contract provides that Chasco would

be paid its costs for performing the work plus a fee with a guaranteed maximum price (“GMP”).2

1 The standard form, titled “AIA Document A111-1997,” is from the American Institute of Architects and reflects the parties’ modifications to the standard form. Section 15.1.2 of this document incorporates the standard form “AIA Document A201-1997, as modified” as the agreed “[g]eneral [c]onditions” of the Contract. 2 Article 5 of the Contract sets forth the “basis for payment.” Section 5.2.1, as modified by the parties, states:

The sum of the Cost of the Work and the Contractor’s Fee is guaranteed by the Contractor not to exceed ($ ), (see GMP addendum) subject to additions and deductions by Change Order as provided in the Contract Documents. Such maximum sum is referred to in the Contract Documents as the Guaranteed Maximum Price.

2 Neither party produced an original of the Contract, and the parties disagree whether the Contract

contained a GMP addendum and, if so, whether the GMP addendum actually contained a guaranteed

maximum price. Stonehill contends that the Contract contained a GMP addendum with a GMP of

$16,638,030, the amount Chasco provided as the budget in December 2005.3 Chasco contends that,

at the time the parties executed the Contract, the Contract did not contain a GMP addendum and

Chasco had not completed the bidding process from the permit plans to provide final cost numbers,

but that, based on a subsequent request from Stonehill’s lender that was financing the Project, two

GMP addenda were prepared. According to Chasco, both addenda contained a GMP of $16,638,030

that was not final and a sentence that the GMP “will be modified upon verification of pricing of City

of Austin permit plans dated February 6, 2006.”4

In March 2006, Safeco issued a performance and payment bond on the Project for

$16,638,030, and Chasco began the demolition work on the existing structure.5 On April 4, 2006,

Chasco notified Stonehill that construction costs based on the completion of the bidding process

from the permit plans were $30,250,000. Thereafter, Chasco sent notice to Stonehill that “[b]ased

3 The addendum that Stonehill contends was contained in the Contract was titled “West Campus Student Housing” and reflects the date of “December 20, 2005.” It is identical to the line- item budget that Chasco provided to Stonehill in December 2005 and does not contain a sentence that the GMP will be modified based on verification of pricing from the permit plans. 4 Both of these addenda were admitted into evidence. They are identical except one refers to the GMP as the “Initial Guaranteed Maximum Price” and is titled “Initial Guaranteed Maximum Price Addendum to Contract,” and the other one refers to the GMP as the “Guaranteed Maximum Price” and is titled “Guaranteed Maximum Price Addendum to Contract.” 5 Chasco submitted applications for payment in March, April, and May for the demolition work that it performed on the existing structure, and Stonehill paid the requested amounts. The dispute does not involve the work that Chasco performed.

3 upon verification of pricing of the City of Austin permit plans and specifications dated February 6,

2006 and Addendum #1 dated March 9, 2006 along with our Final GMP budget and qualifications

dated April 4, 2006,” Chasco needed a written change order modifying the initial GMP to the “Final

GMP budget” of $30,250,000 to “begin construction of the new structure.” Stonehill would not

agree to a GMP of $30,250,000, and Chasco did not begin construction.

Litigation Commenced

In May 2006, Stonehill sent written notice to Safeco and Chasco that it was

“formally” terminating Chasco’s right to complete the Project and declaring a “Contractor Default”

as a result of Chasco’s failure to perform its obligations, including its failure to comply with

performance for the agreed GMP. In July 2006, Stonehill filed this suit alleging breach of the

Contract and the performance bond. Attached to Stonehill’s original petition was a copy of the

Contract that contained the version of the GMP addendum titled “Guaranteed Maximum Price

Addendum to Contract.” In July 2007, Stonehill filed a second amended petition alleging additional

claims and attaching a different copy of the Contract, one that contained the version of the addendum

titled “West Campus Student Housing” with the date “December 20, 2005.”

In its second amended response to appellees’ request for disclosure, Stonehill

disclosed that it was seeking its “expectancy damages”—the difference between the value of the

Project had it been constructed in accordance with the plans and specifications, “calculated using

appropriate rents, expenses and prevailing capitalization rates in Austin, Texas for similar apartment

structures,” and the costs that Stonehill avoided. Stonehill designated Greg Hallman, Ph.D., as its

damages valuation expert, disclosing that he would testify “about the value of the building that is the

4 subject matter of this lawsuit were it constructed pursuant to the parties’ Construction Contract.”

It was Hallman’s opinion that the value of the “resulting building” would have been in excess

of $36,000,000.

After deposing Hallman, Chasco filed a motion to exclude Hallman as Stonehill’s

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shell Oil Co. v. Khan
138 S.W.3d 288 (Texas Supreme Court, 2004)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Larson v. Downing
197 S.W.3d 303 (Texas Supreme Court, 2006)
TA Operating Corp. v. Solar Applications Engineering, Inc.
191 S.W.3d 173 (Court of Appeals of Texas, 2006)
Matheus v. Sasser
164 S.W.3d 453 (Court of Appeals of Texas, 2005)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Interstate Northborough Partnership v. State
66 S.W.3d 213 (Texas Supreme Court, 2001)
Ashley v. Bizzell
694 S.W.2d 349 (Court of Appeals of Texas, 1985)
SAS Institute, Inc. v. Breitenfeld
167 S.W.3d 840 (Texas Supreme Court, 2005)
KW Construction v. Stephens & Sons Concrete Contractors, Inc.
165 S.W.3d 874 (Court of Appeals of Texas, 2005)
Fidelity & Deposit Co. of Maryland v. Stool
607 S.W.2d 17 (Court of Appeals of Texas, 1980)
Turner, Collie & Braden, Inc. v. Brookhollow, Inc.
642 S.W.2d 160 (Texas Supreme Court, 1982)
T.O. Stanley Boot Co. v. Bank of El Paso
847 S.W.2d 218 (Texas Supreme Court, 1993)
Buhler v. McIntire
365 S.W.2d 237 (Court of Appeals of Texas, 1963)
City of Brownsville v. Alvarado
897 S.W.2d 750 (Texas Supreme Court, 1995)
Smith v. Kinslow
598 S.W.2d 910 (Court of Appeals of Texas, 1980)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Stonehill-PRM WC I, L.P. v. Chasco Constructors, Ltd., L.L.P. and Safeco Insurance Company of America, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stonehill-prm-wc-i-lp-v-chasco-constructors-ltd-ll-texapp-2009.