Fawcett v. Bellah

556 S.W.2d 598, 1977 Tex. App. LEXIS 3406
CourtCourt of Appeals of Texas
DecidedSeptember 22, 1977
Docket1179
StatusPublished
Cited by6 cases

This text of 556 S.W.2d 598 (Fawcett v. Bellah) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fawcett v. Bellah, 556 S.W.2d 598, 1977 Tex. App. LEXIS 3406 (Tex. Ct. App. 1977).

Opinion

OPINION

NYE, Chief Justice.

This is a contract case. Plaintiff, Charlie Bellah, brought suit against the Defendant, Clinton B. Fawcett, to recover his architect’s fees for the preparation of plans for the construction of a commercial laundry establishment. Trial was to a jury. In response to the special issues submitted and answered, the trial court entered judgment for the Plaintiff. From this judgment, Defendant has perfected his appeal to this Court.

Plaintiff is a licensed architect and engineer. In October of 1972 a Mr. Robert Evers, who is in the laundry equipment business, introduced the parties, Plaintiff and Defendant, to each other. The purpose of the meeting was to arrange for the designing by the Plaintiff architect and the building by Defendant Fawcett of a laundromat on some property owned by the Defendant. At this meeting the litigants discussed the building, the costs and the architect’s fee. The record indicates that the Plaintiff left with the Defendant a form type contract that set out in detail the architectural fees Plaintiff would be charging for his services. Later that same month the Defendant contacted the Plaintiff and requested that he go ahead and prepare the plans for the building. Based on this conversation the Plaintiff prepared the plans and performed the other services that he promised to perform which were set out in the form contract. There was no formal written contract, however, executed by the parties.

*600 After the plans had been completed, the Plaintiff submitted his bill for his services. When the Defendant failed to pay the Plaintiff for the services rendered, Plaintiff filed an affidavit of lien against the Defendant’s property and brought the present lawsuit seeking to recover his architectural fees in the amount of $4,260.00, plus interest and attorney’s fees. The Defendant filed a general denial and a cross-action in which he stated that he “was not bound under any contract to pay the cross-defendant (plaintiff Bellah) for his plans and specifications unless the building was constructed” and that he sought damages in the amount of $50,000.00 for the filing of the above described lien which he alleged was a cloud on the title to his land. He also sought to have the purported lien extinguished.

The case was tried primarily on the theory that the Plaintiff’s architectural fees were contingent upon the Defendant being able to obtain 100% financing for the construction of the building and that since he did not obtain such financing he did not owe the Plaintiff anything; therefore, the Plaintiff wrongfully placed a lien and cloud upon the title to his property for which he sought relief.

The case was submitted to the jury on the following special issues:

“SPECIAL ISSUE NO. 1
Do you find from a preponderance of the evidence that Plaintiff and Defendant had reached an agreement whereby Plaintiff was to prepare plans and specifications for the construction of a building proposed to be erected at the corner of Doddridge Street and South Staples Street?
Answer ‘Yes’ or ‘No.’ ANSWER: Yes
If you have answered Special Issue No. 1 ‘Yes,’ then answer Special Issue No. 2; otherwise, do not answer Special Issue No. 2.
SPECIAL ISSUE NO. 2
Do you find from a preponderance of the evidence that Plaintiff had completed his architectural duties up to the time of the actual construction of the proposed building?
Answer ‘Yes’ or ‘No.’ ANSWER: Yes
If you have answered Special Issue No. 2 ‘Yes,’ then answer Special Issue No. 3; otherwise, do not answer Special Issue No. 3.
SPECIAL ISSUE NO. 3
What sum of money, if any, if paid now, would reasonably compensate the Plaintiff for his services actually performed?
Answer in dollars and cents, if any.
ANSWER: $4,260.00
SPECIAL ISSUE NO. 4
What sum of money, if any, if paid now, would reasonably compensate the Plaintiff’s attorney in the trial of this case. In arriving at this figure, you shall consider the amount of time spent by Plaintiff’s attorney in the preparation of this lawsuit and the actual trial itself.
Answer in dollars and cents, if any.
ANSWER: $1.800.00 ”

Special Issue Nos. 5 and 6 concerned attorney’s fees on appeal which the jury answered zero.

Special Issue No. 7: “Do you find from a preponderance of the evidence that securing 100% construction financing was a condition precedent to the agreement, if any, between the parties?” (“condition precedent” was then defined by the court). The jury answered “No”. The jury then found that the Plaintiff filed an affidavit of lien knowing that the lien was invalid at the time it was filed (Special Issue No. 8), but that the Plaintiff did not file such a lien with malice (Special Issue No. 9). Special Issue No. 10 was conditional and not answered. The jury, in Special Issue No. 11, was then asked to find that the Plaintiff, although knowing that the lien was invalid, refused to release it at the request of the Defendant. The jury answered “No.” Special Issue No. 12, a conditional issue, was not answered. Next the jury was asked to find that the Plaintiff’s refusal to release the lien caused the Defendant to lose a sale on the property. Again the jury answered “No.” Special Issue No. 14 was a condition *601 al issue and not answered. In Special Issue No. 15, the jury found that the Defendant failed to exercise reasonable efforts to minimize the damages, if any, suffered by him.

Based on the answers to all of these issues, the trial court entered judgment awarding the Plaintiff $4,260.00, attorney’s fees in the amount of $1,800.00, plus interest and costs.

Defendant’s first point of error complains of the action of the trial court in overruling Defendant’s objection to Special Issue No. 1 set out above. Defendant’s objection was that Special Issue No. 1 was not a controlling issue to any cause of action in the case. The Defendant argues as part of his multifarious objection to the court’s charge that the issue, if answered yes by the jury, would at best constitute only a gratuitous promise by Plaintiff with no consideration forthcoming from the Defendant. This point of error is overruled.

The Plaintiff’s pleadings stated “that on or about November 1, 1972, Plaintiff entered into a contract with Defendant wherein Plaintiff agreed to prepare plans and specifications for the construction of a building . . . ” The pleadings go on to state that the plans and specifications were completed and delivered to the Defendant; that the Defendant approved and accepted the plans and specifications and has retained them; that the Plaintiff billed the Defendant for the amount of the work performed; and that the Defendant failed and refused to pay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Placencio v. Allied Industrial International, Inc.
724 S.W.2d 20 (Texas Supreme Court, 1987)
Nugent v. Utica Cutlery Co.
636 S.W.2d 805 (Court of Appeals of Texas, 1982)
Fidelity & Deposit Co. of Maryland v. Stool
607 S.W.2d 17 (Court of Appeals of Texas, 1980)
Freedom Homes of Texas, Inc. v. Dickinson
598 S.W.2d 714 (Court of Appeals of Texas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
556 S.W.2d 598, 1977 Tex. App. LEXIS 3406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fawcett-v-bellah-texapp-1977.