Elliott Consolidated School District v. Busboom

227 F. Supp. 858, 1964 U.S. Dist. LEXIS 7237
CourtDistrict Court, S.D. Iowa
DecidedApril 3, 1964
DocketCiv. 2-438
StatusPublished
Cited by13 cases

This text of 227 F. Supp. 858 (Elliott Consolidated School District v. Busboom) is published on Counsel Stack Legal Research, covering District Court, S.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elliott Consolidated School District v. Busboom, 227 F. Supp. 858, 1964 U.S. Dist. LEXIS 7237 (S.D. Iowa 1964).

Opinion

HANSON, District Judge.

The plaintiff entered into a contract with defendant Busboom for the construction of an elementary school building. The defendant Busboom sub-let the construction of the roof of the said elementary school building to the third-party defendants, Nebraska Sheet Metal Contractors, Inc. and/or Nebraska Sheet Metal and Roofing Contractors, under an agreement that said roof was to be constructed by the third-party defendants in accordance with the plans and specifications furnished. This is admitted in the pleadings.

These agreements in part read as follows:

Contract for Building

“This agreement made this 7th day of September, 1957, by and between John G. Busboom, an individual d/b/a John G. Busboom, General Contractor (Salina, Kansas) (herein called Contractor), and Elliott Consolidated School District, Elliott, Iowa (herein called Owner), provides that: in consideration of the payments to be made by the Owner to the Contractor as provided for in the specifications, the Contractor does hereby contract and agree to erect and complete the General Construction of the Owner’s proposed new Elementary School Building in Elliott, Iowa, in a good, substantial and workmanlike manner, in accordance with the plans and specifications-(which are admitted to be a part of this contract), prepared by Chas. W. and John A. Shaver, Architects, Sa-lina, Kansas; and to the satisfaction of and under the inspection of the said Architect.
And the said Contractor hereby agrees to furnish and pay for all necessary labor, materials, tools and equipment, and to erect complete in every detail the construction work above-mentioned, on or before the-time mentioned in the Specifications.”

Performance Bond

“Know all men by these presents; That we, John G. Busboom, an individual d/b/a John G. Busboom,. General Contractor (Salina, Kansas), as Principal, and United Pacific Insui'ance Company, a corporation, as Surety, with its principal office in the City of Tacoma, Washington,, and authorized to do a surety business in the State of Iowa, are held and firmly bound unto Elliott Consolidated School District of Elliott, Iowa, as obligee(s), in the full and just sum of One Hundred Fifty-three Thousand Five Hundred and No/100 Dollars ($153,500.00), for the payment of which we hereby bind ourselves, our heirs, administrators, executors, receivers, successors, and assigns, jointly and severally, firmly by these presents * *.
“Now therefore, if the Principal shall well and truly perform and comply with the said contract and any and all duly authorized modifications subsequent thereto, with or without notice to the Surety, (except that notice shall be given to the Surety for any modifications that increase the amount of the contract by twenty per cent or more of the original contract price) and pay over, *861 make good or reimburse the Obligee(s) for any and all loss sustained by the Obligee(s) and caused by the Principal’s failure to comply with said contract, then this obligation shall be null and void, otherwise to be and remain in full force and effect.”

The specifications contain the following clause:

“ * * * No certificate given, or payments made under the contract, nor occupancy of the building either partially or entirely by the Owner, shall be considered as evidence or acceptance of any workmanship or materials that are not in strict accordance with the plans, specifications and contract; and the Owner shall have the right to enter and occupy the building when same is in suitable stage of completion for occupancy, whether or not the final acceptance and settlement have been effected.”

The plaintiff in paragraph 8 of their petition claims that the roof on the building was not built according to the specifications, although the defendants reported to the plaintiff that all the plans and specifications were complied with, inducing plaintiff to pay the defendant the contract price.

In paragraph 10 of the petition, it is alleged that the faulty work and material used were concealed and could be discovered only by removing cross-sections of the roof. In paragraph 11, it is alleged that the defendant defrauded the plaintiff.

The plaintiff claims that by reason of the deceitful and fraudulent acts in putting on the inferior roof,' it was necessary to replace the roof at a cost of $15,-000.00 and that water came through the roof and damaged the interior of the building in the amount of $1,500.00.

The plaintiff pleaded two claims in the same count, one for breach of the agreement to build the building according to the specifications and the other for fraud. These should have been put in separate counts but no motion for more specific statement or motion to recast was made. In his opening statement, counsel for plaintiff made this clear and the case was tried on these two theories.

The United Pacific Insurance Company agreed to pay for any and all loss sustained by the obligee, Elliott Consolidated School District, and caused by the failure of the Principal, John G. Bus-boom, to comply with the contract. The principal question in the action on the bond is whether or not the contract was breached. Busboom contracted to erect and complete the building in a good, substantial and workmanlike manner, in accordance with the plans and specifications. Whether or not it was so completed is the first question as to the bondsman’s liability and the second question is the extent of the loss to the obligee.

The certificates given or payments made under the contract are no defense for two reasons. One is the clause in the specifications which says payment or certificates are not acceptance of defects in workmanship or failures to comply with specifications. This is in the specifications, but the specifications are incorporated into the contract when it is agreed that the contract will be performed in accordance with the plans and specifications. This is not in conflict with that part of the contract which says the work is to be done to the satisfaction of and under the inspection of the architect.

The second reason is that given by the Iowa court in City of Osceola v. Gjelle-fald Const. Co., 225 Iowa 215, 279 N.W. 590;

“Under such circumstances the principle of law is, as laid down by courts throughout the country, that in the absence of fraud or mistake acceptance of the work bars and estops the city for defects known or discoverable by reasonable attention on the part of the engineer in the performance of his duty in inspecting the work. * * *
*862 “We are of the opinion that the fair and reasonable intent and meaning of the contract, as well as of the statutory provisions of the bond, to be that, in so far as undiscovered and unknown defects are concerned, the acceptance of the work should not operate as a bar to recovery for damages on account of such defects. While not plainly expressed, this must be held to be an implied condition of the bond.”

This is the general rule. 13 Am.Jur.2d, See. 55, P. 59.

United Pacific does not actually plead acceptance as a defense.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goebel v. Dean & Associates
91 F. Supp. 2d 1268 (N.D. Iowa, 2000)
Williams v. Dudley Trust Foundation
675 A.2d 45 (District of Columbia Court of Appeals, 1996)
Phenix-Georgetown, Inc. v. Chas. H. Tompkins Co.
477 A.2d 215 (District of Columbia Court of Appeals, 1984)
Trushcheff v. Abell-Howe Co.
239 N.W.2d 116 (Supreme Court of Iowa, 1976)
Nordin Construction Company v. City of Nome
489 P.2d 455 (Alaska Supreme Court, 1971)
Peters v. Lyons
168 N.W.2d 759 (Supreme Court of Iowa, 1969)
City of Midland v. Waller
430 S.W.2d 473 (Texas Supreme Court, 1968)
Lennon v. Aluminum Co. of America
285 F. Supp. 70 (S.D. Iowa, 1968)
GLARRATANO v. Weitz Company
147 N.W.2d 824 (Supreme Court of Iowa, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
227 F. Supp. 858, 1964 U.S. Dist. LEXIS 7237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elliott-consolidated-school-district-v-busboom-iasd-1964.