Eastern Iowa Light and Power Cooperative v. Fred R. McKenzie Doing Business as Fred R. McKenzie & Co.

296 F.2d 295
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 7, 1961
Docket16737
StatusPublished
Cited by3 cases

This text of 296 F.2d 295 (Eastern Iowa Light and Power Cooperative v. Fred R. McKenzie Doing Business as Fred R. McKenzie & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Iowa Light and Power Cooperative v. Fred R. McKenzie Doing Business as Fred R. McKenzie & Co., 296 F.2d 295 (8th Cir. 1961).

Opinions

RIDGE, Circuit Judge.

In this diversity action all jurisdictional requirements appear in the record; therefore, federal jurisdiction is premised in Section 1332(a) (1), Title 28 U.S.C.A.

Appellee commenced this action in the United States District Court for the Southern District of Iowa, by a complaint in two counts: (1) to recover an amount claimed to be due for work and labor performed under a written contract relating to a “Site Development” and (2) for declaratory judgment as to his obligation under that contract to dredge a barge channel in the Mississippi River. Appellant by answer admitted the execution of the contract, denied full performance thereof by appellee and asserted a counterclaim for costs allegedly incurred in reletting to another the work of dredging the barge channel in question. After trial before the District Court without a jury, judgment was entered in favor of appellee. This appeal followed.

The facts leading to the judgment appealed from are these:

Appellee, a contractor in heavy construction, dredging, pile-driving and [297]*297marine work, and an engineer by profession since 1922, undertook by written contract to perform “Site Development” work in relation to property of appellant upon which an electric generating plant near Montpelier Station, Muscatine County, Iowa, adjacent to the navigation channel of the Mississippi River, was to be constructed. Near the completion of that undertaking a dispute arose between the parties as to whether the contract by its terms obligated appellee to construct a barge channel in the river along the site as a part of the work undertaken to be performed by him. Hence the salient question for determination on this appeal revolves around the proper legal interpretation to be given to the written integration of the parties concerning the construction of the barge channel. Subsidiary thereto is the question, whether the District Court erred in disregarding the project engineer’s interpretation of that contract in the light of “Part 2 — General Requirements” entitled “Interpretation of Specifications,” and particularly “Section 3” thereof which reads as follows:
“Report any errors or ambiguities in specifications to engineer as soon as detected; Engineer will answer questions regarding and interpret intended meaning of specifications; his interpretation shall be final.”

Appellee’s contract with appellant is referred to in the record as “Contract 14, Site Development.” There is no dispute between the parties as to the wording thereof. Appellee was awarded the contract as a result of a lump sum bid of $282,840. That bid required him to perform a total of eleven separately enumerated items. The controversy here centers around Item 2 of the “Bid Schedule” which reads:

“Construction of Dredged Fill; quantity 120,000 (CY) Unit Price, $0.57; Extended Price, $68,400.-00.”

Pertinent parts of the contract relating to that bid item are: “Part 3 — Site Work” which specifies under the subheading “Work Included — (d) Dredging and Construction of fill, including stockpiling.” Under this same Part, 3, Paragraph 6, “Dredging and Construction of Fill,” sub-paragraph (a) provides:

“a. Includes labor, equipment, general methods, and incidental work necessary for dredging, handling, placing, shaping, etc., all materials required for construction of all fill shown. Includes the dredging, deposition in stockpile on site of material for future filling of site area by Owner to compensate for embankment settlement and for use by other contracts. Includes formation of barge channel of docking area.” (Emphasis added.)

Paragraph 6(c) of the same part reads:

“c. Obtain material for embankment by dredging from bed of Mississippi River within the area shown. Owner will obtain necessary permit for dredging operations. Dredging will conform to Corps of Engineers of the Department of the Army Regulations. Carry on dredging operations at such locations and in such manner as not to interfere with river navigation. No material shall be taken within 100' of any river bank or wing dam, except as specifically shown.”

Part 4 of the contract contained a “Description of Bid Items.” With respect to construction of the dredged fill, the contract provided as follows:

“Construction of Dredged Fill, per cubic yard: Construct all fills as specified and as shown on plans, including stockpiling, compaction, and finish grading of all fills as specified. Dredge barge channel as shown. Embankment will be measured for payment as the volume of material in place between surface of stripped and cleared embankment area and the completed embankment as determined by cross . section of the area. No payment will be made for unauthorized excavation or fill.” (Emphasis added.)

[298]*298Part 1 of the contract, entitled “Detailed Specifications” informed bidders as to “Site Development” work. Under paragraph 1(d) thereof is:

“ ‘The work’ shall mean the work to be done and the equipment, supplies and materials to be furnished under the contract, unless some other means is indicated by the context.”

Sub-paragraph 3(a) of that same part is headed “Plans” and is as follows:

“The work shall conform with the following drawings which constitute the ‘Plans’ and are an integral part of the specifications and the contract documents.”

Immediately beneath this recitation in the contract specific drawings were enumerated. Among those were Lot Layout, Drawing No. 2247-2; Site Development Sheet 1, Drawing No. 2247-4; and Site Development Sheet 2, Drawing No. 2247-5. (Photographic reproductions of these drawings appear as Plaintiff’s Exhibits 5, 7 & 8, respectively, in the record.) These drawings show a barge channel to be dredged in the Mississippi River to a minimum depth of 534 feet above sea level for the full distance between the east and west property lines of the site. Under “Part 3 — Site Work” Paragraph 7 relating to “Embankment Construction,” sub-paragraph (a) thereof provided:

“Embankments, grades to be constructed of dredged material to lines and grades shown and as staked by Engineer.”

Under (b) of that same paragraph it is stated:

“Dredged material must be free from pockets, streaks or Layers of material differing appreciably in texture of gradation from surrounding material when placed in embankment. Include no light silt, muck or other unstable material in fill; provide relief or branch line with valve for wasting unstable material. Pump off and waste any overlay of unstable mud and silt that appear in embankments.”

Subparagraph (c) reads:

“Place dredged fill such that transporting water is not trapped within fill. Provide necessary means for returning to river the transporting water and unstable material so that no unauthorized build-up of material occurs in river.” (Emphasis added.)

The contract expressly stated that it was the “Intent of Specifications” to “require contractor — to perform all work and services described in contract documents, unless otherwise specifically indicated.”

The contract contained this “Notice and Instructions to Bidders”:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
296 F.2d 295, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-iowa-light-and-power-cooperative-v-fred-r-mckenzie-doing-business-ca8-1961.