F. E. Marsh & Co. v. Light & Power Co.

196 Iowa 926
CourtSupreme Court of Iowa
DecidedNovember 16, 1923
StatusPublished
Cited by12 cases

This text of 196 Iowa 926 (F. E. Marsh & Co. v. Light & Power Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. E. Marsh & Co. v. Light & Power Co., 196 Iowa 926 (iowa 1923).

Opinion

Arthur, J.

I. Appellee Light & Power Company, desiring to construct a power plant on the Cedar River, employed George D. Dobson, of Des Moines, as engineer, to design the plant. The contract between the company and Dobson provided that Dobson should make plans and specifications for the dam and power house at the site selected; that Dobson should make “necessary soundings, to ascertain the character of the foundation at the dam site; to be present and assist the committee in receiving bids and awarding the contract; ’ ’ and, ‘ ‘ after completion of the structure, to make final inspection of same.” In pursuance of this contract, Dobson prepared plans and specifications. Appellant was the successful bidder, and the job was awarded to it. On or about the 3d of July, 1919, the parties entered into a written contract, whereby appellant agreed to furnish the materials and perform the work for the erection and completion of a power house and concrete dam across the Cedar River, at the site selected, for the agreed price of $30,000. Appellant began work on the project about July 20, 1919, and the dam, sometimes referred to in the record as “the spillway,” 150 feet in length, built in three sections of 50 feet each, was completed, by pouring the last concrete into the center section, on February 7, 1920. The lower portion of the power house, together with the penstocks and water gates, had not been completed, and the superstructure of the power house had not been completed, at the time the concrete was poured into the center section of the dam. About the 11th of March, 1920, there .came a thaw, and the river rose, and at midnight on March 16th washed around the west end of the dam and under a diversion wall which had been built, under a separate contract, from the northwest abutment, some 65 feet to the northwest. Thereafter, appellant completed the superstructure of the power house, and called upon Dobson, the engineer, to inspect the project. At [928]*928the request of 0. II. Koch, secretary of appellee company, the next morning after the disaster, Dobson went to the plant, and met with the committee of appellees, and visited the site, and made a general inspection of the conditions as they existed. At that time, there was some criticism by the committee as to the quality of the work, and appellant was told by the committee representing the owners to> go ahead and complete the work, and that, when they got through, they would be paid. The top of the spillway was to be repaired, where it had been damaged by the ice gorge, and the power house completed, and then Dob-son was again to inspect the plant. On April 23, 1920, after certain repairs had been made, as directed by the engineer, and after the power house had been completed, another meeting was held, at which were present a representative of the contractor, the owners, and Dobson, engineer; and at that time, Dobson again examined the work, and gave orders for certain further work to be done by the contractor. Dobson had been employed by appellees’ committee to prepare plans to close up the gap made by the river around the west end of the dam; and after the preparation' of same, he returned to St. Ansgar, and made a further inspection of the dam. At this time, Dobson looked over the project with Stinson, construction engineer of appellant, and directed Stinson to make repairs to the surface of the concrete in the spillway, and other repairs. On April 23, 1920, Stinson wrote to Dobson, stating:

“They followed your instructions in patching the top of the St. Ansgar dam. They completed the same; also repaired the break in the center section you reported. This I believe completes the same.”

After Stinson had so notified Dobson, Dobson inspected the plant, and addressed to O. H. Koch, secretary of appellee company, on May 7, 1920, the following letter:

“I beg to report that I visited the site-of the Light & Power Company dam and power house on the Cedar River on May 5, 1920, to make final inspection of the same. I find that Mr. Stinson, foreman for F. E. Marsh & Company, has complied with my order given him on April 23 st and has made the required repairs to the spillway to replace the damaged concrete, and that the contractor has substantially complied with the [929]*929plans and specifications, and that the contract has been fulfilled.”

After said approval of the structure by Dobson, as “designing engineer for the Light & Power Company of St. Ans-gar, Iowa,” that “the contractor has 'substantially complied with the plans and specifications and that the contract has been fulfilled,” appellant demanded balance of the money due him under the original contract and the subsequent contracts, and appellees refused t-o pay same. Certain negotiations of settlement were made by the parties, but not completed. Thereafter, appellant filed its claim for mechanics’ lien, claiming a balance due on its account, of $12,507.84, and later instituted this suit, demanding on the account, and praying for establishment of its mechanics’ lien against the plant.

In addition to the contract price of $30,000, appellant includes in its account charges for materials and labor for certain extras which it claims were not covered in the original contract. It is not necessary to set forth all of the items claimed as extras. It is sufficient to say that claims for extras were allowed in the amount of $3,039, and the court denied recovery for other items' of extras claimed. Appellees have paid appellant $28,572 on the original contract. The court found for appellant, that it was entitled to recover the original contract price of $30,000, and extras to the extent of $3,039, making a total amount of $33,039 that appellant was entitled to recover.

The items for extras claimed by appellant, which the court refused to allow and which are claimed by appellant on this appeal, are for concrete, with re-enforcing steel, and for loose rock -excavation, due to increased depth of about two feet for foundation of the dam, which appellant claims it was not obliged to build, under the contract, in the amount of approximately $6,000. Some liens claimed by materialmen, which were conceded by appellant at the trial, were charged against appellant, and are not involved in either appeal. The court found that appellant is liable, and should be charged with the cost of reconstructing the west abutment of the dam, in the amount of $4,195; for the cost of repairing the power house, in the amount of $5,020; and for the cost of repairing the dam, or spillway, $19,835. Appellant takes the position that it has substantially complied with the plans and specifications, and that the accept[930]*930anee and approval of the structure by the designing engineer is final, and settles the question of compliance with the contract, and that the court was in error in charging appellant with any amount for reconstruction 'and repair of the plant. Subject to such contention, appellant urges on its appeal that the amounts allowed and charged to it by the court below for reconstruction and repair are excessive, and if allowed at all, should be allowed in much smaller amounts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Service Unlimited, Inc. v. Elder
542 N.W.2d 855 (Court of Appeals of Iowa, 1995)
Busker v. Sokolowski
203 N.W.2d 301 (Supreme Court of Iowa, 1972)
Elliott Consolidated School District v. Busboom
227 F. Supp. 858 (S.D. Iowa, 1964)
Freese v. Town of Alburnett
125 N.W.2d 790 (Supreme Court of Iowa, 1964)
City of Granville v. Kovash, Incorporated
118 N.W.2d 354 (North Dakota Supreme Court, 1962)
Town of Milford v. O'Neil Bros., Inc.
8 Conn. Super. Ct. 403 (Connecticut Superior Court, 1940)
R. Lee Tolley Co. v. Marr
12 Tenn. App. 505 (Court of Appeals of Tennessee, 1931)
Hayes v. Ramsey
217 N.W. 808 (Supreme Court of Iowa, 1928)
Van Dyck Heating & Plumbing Co. v. Central Iowa Building Co.
205 N.W. 650 (Supreme Court of Iowa, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
196 Iowa 926, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-e-marsh-co-v-light-power-co-iowa-1923.