Freese v. Town of Alburnett

125 N.W.2d 790, 255 Iowa 1264, 1964 Iowa Sup. LEXIS 721
CourtSupreme Court of Iowa
DecidedJanuary 14, 1964
Docket51193
StatusPublished
Cited by19 cases

This text of 125 N.W.2d 790 (Freese v. Town of Alburnett) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Freese v. Town of Alburnett, 125 N.W.2d 790, 255 Iowa 1264, 1964 Iowa Sup. LEXIS 721 (iowa 1964).

Opinion

Larson, J.

Plaintiff-contractor brought this action to recover the sum of $500 against the defendant, Town of Albur-nett, Iowa, under a well drilling contract. His claim is for extra work performed under authority of an “extra work” order issued to him by the Town, through its engineer, pursuant to terms of the contract.

The issues themselves are simple. They are: (1) Was the work for which plaintiff seeks recovery actually extra work or was it work required under the basic contract price? (2) Did the plaintiff establish that he was entitled to the sum of $500 for extra work? The trial court found that the contract was ambiguous, that the work in issue was extra work, that the claimed amount was established under the contract, and overruled defendant’s motion to dismiss and rendered judgment in favor of plaintiff for $500 plus interest.

Pursuant to a written contract, Exhibit 1, dated September 30, 1960, plaintiff drilled a deep well for defendant. Upon the completion of the actual drilling he was directed by the defendant’s engineer to test pump the well under provisions of section 5 of the contract entitled “Testing”. During the course of this test the well caved, allowing clay to come into the well preventing further testing. Under an extra work order, the test pump was removed, the well reamed and cleaned, a 10-inch I. D. easing was installed, and the well was tested a second time, to the satisfaction of the engineer. Although the claim for extra compensation for the second testing operation was approved by the engineer, it was refused by defendant and this action followed. Plaintiff contends that under the terms of the original contract the basic price included but one testing, that the extra work order for the second testing was properly issued by the engineer and the compensation properly agreed upon under the general specifications and schedule of prices of the contract. Other relative facts will be referred to as needed.

*1267 I. In its first brief point appellant asserts that work required to be performed by a written contract must be paid for at tbe contract price, and additional compensation may not be recovered for work within the provisions of the contract. McCauley v. Des Moines, 83 Iowa 212, 48 N.W. 1028; Marsh & Co. v. Light & Power Co. of St. Ansgar, 196 Iowa 926, 195 N.W. 754; 17 A C. J. S., Contracts, section 364, “Extra Work”, page 368.

Appellee does not deny this proposition, but asserts the provisions of the contract relating to test pumping being ambiguous must be interpreted by the court. In Division I of his brief he asserts correctly that if a contract is not free from indefiniteness and ambiguity, it must be interpreted by the court, and in such cases the court must determine the intention of the parties at the time the contract was executed (Harvey Construction Co. v. Parmele, 253 Iowa 731, 113 N.W.2d 760); that ambiguity appears when a genuine doubt appears as to the meaning of a contract, and the instrument must be construed as an entirety, Pedersen v. Bring, 254 Iowa 288, 117 N.W.2d 509. With these rules in mind we examine the relevant provisions of the contract, Exhibit 1. Under the Schedule of Prices, P-2 2, appears the following: “7. * * * Furnish and install all equipment for test pumping. Lump sum $500.00.” Appellant contends this language is free from indefiniteness and doubt and that it requires the appellee to test pump this well as many times as was necessary to satisfy the Town’s engineer, for the sum of $500, in order to complete his basic contract. Appellee disagrees, contending this clause requires the expensive installation of test pumping equipment only once. Considering the evidence that this is a time-consuming and costly operation and that the contractor was required to follow implicitly the directions of the engineer, the trial court found considerable doubt as to the meaning of this contract provision. We must agree. It considered the second testing came within the contract’s provision for extra work, which provided:

“Without invalidating the contract, the Town may, through the engineer, order extra work deemed necessary. Such extra work shall be executed under the conditions of the original con *1268 tract. Such extra work shall be done only on written order by the engineer. Said order shall be explicit and shall be dated and signed by the engineer. * * * The Town’s copy of said work order shall be receipted for by the contractor’s representative. * # * »

It appears from the record that this contract was prepared by Mr. Raymond Rystrom, the Town’s engineer, that the test pump was obtained from a concern in Rockford, Illinois, which furnished two men to assist in its installation and removal, at a total cost to plaintiff of $650, that it took some 98 man-hours of labor for each installation and, in placing the lump sum figure of $500 in the original contract, the engineer considered that figure was for one test only.

It further appears the engineer knew the contractor had drilled through a clay deposit, and considered the danger of a caye-in. However, in an effort to save the expenses to the Town of some $480 in easing off that area, he took a calculated risk and ordered the test pumping operation prior to issuing an order to install casing as is provided for in the general contract. This provision of the contract stated: “Though not anticipated the following unit prices shall apply if ordered by the Engineer: Drill for and install 10" I. D. casing; $12.00 per foot.” The contract also provided: “No deviation from the plans and specifications will be permitted without the written consent of the Town Council or the Engineer.”

In the light of these circumstances we are satisfied there was at least a fair doubt as to what the parties actually had in mind when they used the language expressed in Item 7 relating to test pumping.

II. This being true, we apply the rule that from the situation of the parties, the objects they were trying to accomplish, and any other facts in evidence, the actual intention of the parties must be determined. Harvey Construction Co. v. Parmele, supra, 253 Iowa 731, 739, 113 N.W.2d 760, 765. Other general rules applicable in this situation too well known to require citations are, that an agreement will not be construed so as to give one party an unfair, oppressive or inequitable advantage over the other, that unless the terms of the contract *1269 clearly require it au interpretation will not be given wbicb places one party at the mercy ol the other, that courts will endeavor to give the contract that interpretation most equitable to the parties, and that the contract will be construed most strictly against the one who drew it. Marty v. Champlin Refining Co., 240 Iowa 325, 335, 36 N.W.2d 360, 365; Harvey Construction Co. v. Parmele, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker Manufacturing, Inc. v. Hoffmann, Inc.
220 F. Supp. 2d 1024 (N.D. Iowa, 2002)
Cooper v. Amana
Third Circuit, 1995
Iowa Realty of Pella v. Boomsma's, Inc.
533 N.W.2d 549 (Supreme Court of Iowa, 1995)
Home Federal Savings & Loan Ass'n of Algona v. Campney
357 N.W.2d 613 (Supreme Court of Iowa, 1984)
Insurance Agents, Inc. v. Abel
338 N.W.2d 531 (Court of Appeals of Iowa, 1983)
Midwest Management Corp. v. Stephens
291 N.W.2d 896 (Supreme Court of Iowa, 1980)
Carmichael v. Iowa State Highway Commission
219 N.W.2d 658 (Supreme Court of Iowa, 1974)
Holden v. Construction MacHinery Company
202 N.W.2d 348 (Supreme Court of Iowa, 1972)
Webb v. Lake Mills Community School District
344 F. Supp. 791 (N.D. Iowa, 1972)
Hilgenberg v. Iowa Beef Packers, Inc.
175 N.W.2d 353 (Supreme Court of Iowa, 1970)
Langer v. Iowa Beef Packers, Inc.
420 F.2d 365 (Eighth Circuit, 1970)
Mopper v. Circle Key Life Insurance Company
172 N.W.2d 118 (Supreme Court of Iowa, 1969)
Modern Heat & Power Company v. Paul
158 N.W.2d 8 (Supreme Court of Iowa, 1968)
LaFontaine v. Developers & Builders, Inc.
156 N.W.2d 651 (Supreme Court of Iowa, 1968)
TEIG & JOHNSON v. Speelmon
153 N.W.2d 818 (Supreme Court of Iowa, 1967)
Theobald v. Weber
143 N.W.2d 418 (Supreme Court of Iowa, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
125 N.W.2d 790, 255 Iowa 1264, 1964 Iowa Sup. LEXIS 721, Counsel Stack Legal Research, https://law.counselstack.com/opinion/freese-v-town-of-alburnett-iowa-1964.