Salt Lake City v. Smith

104 F. 457, 43 C.C.A. 637, 1900 U.S. App. LEXIS 3935
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 15, 1900
DocketNo. 1,365
StatusPublished
Cited by90 cases

This text of 104 F. 457 (Salt Lake City v. Smith) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Salt Lake City v. Smith, 104 F. 457, 43 C.C.A. 637, 1900 U.S. App. LEXIS 3935 (8th Cir. 1900).

Opinion

SANBORN, Circuit Judge,

after stating the case as above, delivered the opinion of the court.

The purpose of a written contract is to evidence the terms on which the. minds of the parties to it met when they made it, and the ascertainment of those terms, and the sense in which the parties to the agreement used them when they agreed to them, is the great desideratum and the true end of all contractual interpretation. The express terms of an agreement may not be abrogated, nullified, or modified by parol testimony; but, when their construction or extent is in question, the meaning of the terms upon which the minds of the parties met when they settled them and their intention in using them must be ascertained, and when ascertained they must prevail in the interpretation of the agreement, however broad or narrow the words in which they are expressed. In the discovery of this meaning, the intention, the situation of the parties, the facts and circumstances which surrounded and necessarily influenced them when they made their contract, the reasonableness of the respective claims under it, and, above all, the subject-matter of the agreement and the purpose of its execution, are alwrays conducive to and often as essential and controlling in the true interpretation of the contract as the mere words of its various stipulations. These are rules for the construction of contracts which commend themselves to the reason and are established by repeated decisions of the courts, and they must not be permitted to escape attention in the consideration of the contract which this case presents. Accumulator Co. v. Dubuque St. Ry. Co., 64 Fed. 70, 74, 12 C. C. A. 37, 41, 42, 27 U. S. App. 364, 372.

The great question in this case is whether the work and materials for which the plaintiffs have brought this action fall within or without their contract with the city, and that must receive its answer from an interpretation of the agreement itself. The court below (83 Fed. 784) held that, if the materials and labor in question were of the kind and of the value stated by the plaintiffs’ witnesses, they were not contemplated by the parties when they made their [463]*463agreement, and were not within and governed by the contract, and that the defendant was bound to pay their reasonable value. The defendant complains of this ruling in various ways, by numerous specifications of error, which it is unnecessary to quote. Its counsel insist that the contract specifies a price, or authorizes the city engineer to fix a price, for every item of materials and of labor contained in the plaintiffs’ claim, and that the price of every item thereof must therefore be determined and governed by the contract itself, and not by the measure of its reasonable value. They contend that the contractors agreed to construct cut-stone masonry for §12.40 per cubic yard, and that although they did this in reliance upon the city engineer’s ax>proximate estimate that only 10 cubic yards, amounting in value to §124, would be required, yet the engineer had the right to ask them to construct 8(55.44 cubic yards of this masonry, which was reasonably worth $30 per cubic yard, or $25,963.20, at the contract price of $12.40 per yard, or for $10,-731.45. They argue that the parties gave the engineer this power under section 15 of this agreement, which authorizes him to make any necessary or desirable alterations in the work before or after its commencement, and to pay the contractors for increased quantities at the contract rates, and under sections 7 and 22 of the contract, which require the contractors to do such extra work connected with that covered by the contract as the city engineer and the board of public works shall direct, and authorize the former to fix the price which the contractors shall receive for all work and material of a different nature from that specified in the agreement. They say that under these provisions the city engineer was authorized to require the contractors to construct a dam to gather and hold the waters of Parley’s creek, the concrete and cut-stone masonry in which cost more than twice the contract price per yard, and that the city was permitted to pay them in full therefor at such price as the engineer fixed, although no mention of this dam was made in the contract, or in the maps, plans, or specifications upon which the contractors made their bid; that the engineer had the right to demand that the contractors should place 2,000 cubic yards of concrete masonry in tunnels through hills and on embankments over ravines, upon a line that was never marked out before the agreement was made, for the contract price of §5.97 per cubic, yard, although that was the price bid for placing such masonry in an open trench on comparatively level ground shown on the map and by the specifications, and the cosí and value of placing it in such tunnels and on such embankments was from $12 to $20 per cubic yard; and that this contract authorized the engineer to require the contractors to construct 154.07 cubic yards of rubble masonry and to lay 1,800 lineal feet of iron pipe at the prices named therein, although their hid and agreement were based on an approximate estimate of the engineer that only 10 cubic yards of such masonry and only 200 feet of such iron pipe would be required to construct the conduit. Nor are these contentions without support in the terms of the contract. If, blind to reason, to the object of the agreement, to the situation and intention of the parties, [464]*464and to the undertaking they contemplated, we read the dry words of the contract and the specifications, it must be conceded that they are broad and comprehensive enough to sustain these arguments . of the counsel for the city. They require the work done and the -materials furnished to- be paid for at the price specified in the agreement; they require the work to be done on such lines and levels and in accordance with such verbal instructions as the city engineer shall present; they authorize the engineer to make any necessary or desirable alterations in the work; they require the contractors to perform any extra work in connection with that specified in the contract that the engineer shall require them to do; they provide that increased quantities of work and materials furnished under these provisions, of the same nature as those specified in the contract, shall bé paid for at the agreed price, and that those of a different nature shall be paid for at a price fixed by the engineer; and they make him the interpreter of the specifications, and the arbiter of all controversies which arise in reference to the contract and the work done under it. The engineer admits in his testimony that under these provisions of the agreement he required these contractors to furnish more than 53 times the estimated quantity of the most expensive work and materials specified in the contract, — the cut-stone masonry; and the witnesses of the plaintiffs testify that he required more than 86 times the estimated amount, and that the masonry thus called for was of such a character that it cost and was reasonably worth more than twice as much per cubic yard as that described in the contract, or, in the aggregate, more than 182 times the cost and value of the amount which the engineer estimated would be necessary for the undertaking before the bid was made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coulter, Inc. v. Allen
624 P.2d 1199 (Wyoming Supreme Court, 1981)
Commonwealth v. Charles
411 A.2d 527 (Superior Court of Pennsylvania, 1979)
Jasper Construction, Inc. v. Foothill Junior College District
91 Cal. App. 3d 1 (California Court of Appeal, 1979)
Anton Vaughn Evalt v. United States
359 F.2d 534 (Ninth Circuit, 1966)
Samuel Kraus Co. v. Kansas City
315 S.W.2d 758 (Supreme Court of Missouri, 1958)
Glennon v. Great Atlantic & Pacific Tea Co.
143 A.2d 282 (Supreme Court of Rhode Island, 1958)
United States v. Konovsky. United States v. Brani
202 F.2d 721 (Seventh Circuit, 1953)
Trouser Corp. of America v. Goodman & Theise, Inc.
153 F.2d 284 (Third Circuit, 1946)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)
Transbay Const. Co. v. City and County of San Francisco
35 F. Supp. 433 (N.D. California, 1940)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
Willis Bancroft, Inc. v. Millcreek Township
6 A.2d 916 (Supreme Court of Pennsylvania, 1939)
Ambursen Dam Co. v. United States
86 Ct. Cl. 478 (Court of Claims, 1938)
Six Companies, Inc. v. United States
85 Ct. Cl. 687 (Court of Claims, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
104 F. 457, 43 C.C.A. 637, 1900 U.S. App. LEXIS 3935, Counsel Stack Legal Research, https://law.counselstack.com/opinion/salt-lake-city-v-smith-ca8-1900.