Willis Bancroft, Inc. v. Millcreek Township

6 A.2d 916, 335 Pa. 529, 1939 Pa. LEXIS 460
CourtSupreme Court of Pennsylvania
DecidedMay 9, 1939
DocketAppeal, 157
StatusPublished
Cited by9 cases

This text of 6 A.2d 916 (Willis Bancroft, Inc. v. Millcreek Township) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Willis Bancroft, Inc. v. Millcreek Township, 6 A.2d 916, 335 Pa. 529, 1939 Pa. LEXIS 460 (Pa. 1939).

Opinion

Opinion by

Mr. Justice Maxey,

A written contract was duly entered into by the plaintiff-appellee, Willis Bancroft, Inc., with the Township of Millcreek, the appellant, on December 4, 1934. It related to the construction of a sanitary sewer system of approximately three miles in the township, as a W.P.A. project. It required that the labor be furnished by the Federal Belief Administration, and the materials were to be furnished by the township. The work was divided into three parts. Items 1 and 3 were awarded to the appellee. These two sections were connected by a section known as Item 2, which was awarded to another contractor. The Bancroft Company, which received the award of Items 1 and 3, agreed on its part to furnish skilled supervision of the work allotted to it, in accordance with the plans and specifications, which included the construction of collection manholes and two pump stations, and to furnish for the job all necessary tools, equipment, fuel, a shelter building and shoring materials necessary for bracing trenches. The contract called for the construction work to begin “within five days after written notice to do so shall have been given to the contractor, and shall be carried on at a rate to insure its full completion within four and a half months thereafter, the rate of progress and the time of completion being essential conditions of the agreement.” (Italics supplied.) The contract price was based upon unit bids per lineal foot of different depths of sewer1 actually dug and laid. Maps, plans, profiles and specifications, containing designations of the line of the pro *531 posed sanitary setver, its grade and depth, as well as the sizes and kinds of pipe to he used, were furnished by the township to bidders, and are incorporated and are part of the contract. Provision was written into the “General Specifications” and into the body of the contract for changes as the work progressed. In Article III, the parties provided “that the unit quantities shown are only approximate and may not represent the actual amount of work to be performed. . . . The prosecution of this work is dependent entirely upon labor furnished by the Federal Relief Administration, and in case the Relief Administration fails to furnish the labor, or is discontinued, or for any other reason the labor supply from the relief administration is discontinued, the township or the supervisors thereof shall not be liable to the contractor for any damages or for any payments except for unit payments of the amount of work actually completed.”

In Article IV of the contract the parties recognized that there may be extra work for which extra pay would be given to the township. It provided that “authorized extra work shall be included in progress payments,” and in paragraph numbered 13 of the “General Specifications,” which forms a part of the contract, it is provided that “the engineer can make any alterations to, or omissions from the work . . . that he may find necessary and the same shall be acceded to by the contractor. The value of such alterations, additions or omissions shall be added to the schedule of prices contained in the proposal for this work, or in case the work . . . is not embraced in said schedule a price shall be agreed upon in writing between the council and the contractor before such alteration is made, otherwise no allowance shall be made thereof.” In the “General Specifications” is also found the provisions that “in case any dispute arises . . . or in case any claim shall be made by the contractor . . . including any claims for damages for delay in the completion of this agreement, in every such *532 case the disputed claim shall be submitted to the engineer for decision and his award or decision thereon shall be final and conclusive and binding upon all parties hereto; and such award or decision in case any question shall arise, shall be a condition precedent to the right of the contractor to receive any money hereunder.’?

The construction of the sewer system was actually started a few days before the written contract was executed. by the parties in 1934, and it continued until some time in May, 1936. The contractor had received from the township $7,495.72, in “progress payments,” on the engineer’s estimate of work completed, the final estimate being dated November 20, 1936. However, on June 11, 1936, the contractor brought this suit against the township to recover a balance of $20,603.99, which it alleged was due. A statement of claim was later filed and the parties soon after agreed to a voluntary arbitration, reserving the right of appeal on questions of law, in accordance with the Act of June 16, 1836, P. L. 715, 5 PS 1. The authority in the township supervisors to submit to arbitration under the Act of 1836 can be found in the Act of May 13, 1925, P. L. 670, sec. 2, 5 PS 181.

The majority of the arbitrators found in favor of the contractor and awarded it $7,461.54. The township excepted, the exceptions were dismissed by the court in banc, and this appeal followed.

The contractor based its cause of action on an implied contract, on a quantum meruit, to recover the reasonable value of the services of supervision, and a fair rental value of the equipment and machinery used on the project, because of the changes from the plans and specifications on which it bid. It pleaded “a complete abandonment of said contract” by reason of the material and important changes in the construction of this sewer system. It also pleaded that it was not subject to the unit prices in the contract.because “of the abandonment of the contract in its entirety” by the *533 township. It concluded its statement with the plea that “the changes of the requirements . . ■. - from the terms of the contract resulted in great financial loss and damage to the plaintiff.”' ■■

The testimony presented to the Board of Arbitration was made a part- of the record. From this testimony the court below found, and an examination of it sustains the court’s findings, that “the following are some of the cliánges required by the engineer.- The plans of Item No. 3 showed pipe on the top of the ground at a designated location. This pipe plaintiff [contractor] was required- to lay three feet deep ori trestle work through a swamp. Between stations 57-0 and 62-50 the proposal called for 550 feet of sewer 8% to 10% feet deep. This section was required to be laid from 12 feet to 14 feet deep. The final 4,000 feet of the sewer was lowered. At least on one occasion the engineer changed the grade after the ditch had been dug and some pipe laid. Along the Algeria Farm the location of the sewer was moved so near a large barn that the work had tó be done .by hand, 40 to 50 men consuming seven weeks, whereas the plans called for a location where the sewer could have been dug efficiently and expeditiously by the special machinery and power equipment furnished by the plaintiff. Sections of Item No. 3 were to be built5 over definite private rights-of-way. These rights-of-way never were acquired by the defendant and the route of the sewer was therefore changed to adjacent public roads, greatly increasing the length of the ■ sewer and adding to the amount of supervision and time consumed; : In one section of the work, 1,000 yards of fill were required due to change of location. In another the contractor was required to build a corduroy road.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roseman v. Hassler
382 F. Supp. 1328 (W.D. Pennsylvania, 1974)
J. A. & W. A. Hess, Inc. v. Hazle Township
305 A.2d 404 (Commonwealth Court of Pennsylvania, 1973)
Maryland Casualty Co. v. Darby Township
20 Pa. D. & C.2d 543 (Delaware County Court of Common Pleas, 1959)
Booker v. City of Philadelphia
86 Pa. D. & C. 126 (Pennsylvania Court of Common Pleas, 1953)
Rennard v. City of Franklin
82 Pa. D. & C. 49 (Venango County Court of Common Pleas, 1952)
Strunk v. Altoona
74 A.2d 662 (Superior Court of Pennsylvania, 1950)
Coyle v. Pittsburgh
25 A.2d 707 (Supreme Court of Pennsylvania, 1942)
Philadelphia Housing Authority v. Turner Construction Co.
23 A.2d 426 (Supreme Court of Pennsylvania, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
6 A.2d 916, 335 Pa. 529, 1939 Pa. LEXIS 460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/willis-bancroft-inc-v-millcreek-township-pa-1939.