City of Mobile v. Shea

127 F. 521, 62 C.C.A. 319, 1904 U.S. App. LEXIS 3802
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 5, 1904
DocketNo. 1,277
StatusPublished
Cited by4 cases

This text of 127 F. 521 (City of Mobile v. Shea) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Mobile v. Shea, 127 F. 521, 62 C.C.A. 319, 1904 U.S. App. LEXIS 3802 (5th Cir. 1904).

Opinion

McCORMICK, Circuit Judge,

after stating the case as above, delivered the opinion of the court. :

The questions presented on this writ of error depend upon the proper construction of the written contract entered into by the parties, the material parts of which are shown in the foregoing statement of the case. We have to gather from the rulings on the pleadings the construction placed upon this contract by the learned judge who tried the case in the Circuit Court. The record brought up does not show, as it was not necessary that it should show, any of the incidents of the trial or the action of the trial judge between the final rulings on the demurrers and •the entry of the final judgment. The first two lines of the judgment inform us that, “the evidence and argument being concluded, the jury is now charged by the court, and the case submitted to them.” In order to clearly see and fully present the views of the judge, we have thought it necessary, or at least proper, to state with unusual fullness the provisions of the written contract and the pleadings of the respective parties. It appears with sufficient clearness on the face of the contract, itself that it was made by the parties with full knowledge that the city of Mobile had been engaged, and was then engaged, in an effort to procure authority to issue bonds for a fixed amount to pay for a system of waterworks, and also for a system of sewers, and, in support of her application to the Legislature for that authority, had caused a survey to be made, and plans and specifications for the construction of a system of sewerage for the city to be prepared, and had received sealed proposals for the construction thereof, from the defendant in error, at least, if not from others, in advance of the Legislature’s action, and as inducement to the granting of the authority sought. This is shown by the eleventh section of the contract, read in connection with the terms of the three writings which evidence the agreement of the parties. The prices of all work, labor, materials, and transportation to be done and furnished in constructing the sewerage system, stipulated in Schedule A attached to the specifications, were the prices and figures on the approximate quantities as proposed by the defendant in error in his bid for the construction of the sewers and appurtenances thereto. It hears date October II, 1898. The specifications required that the bids for the construction of the system of sewers should be made on the form of proposal furnished by the engineer, and attached to the specifications. Bidders were advised that, before tendering proposals, they should visit the locality and acquaint themselves with the physical conditions, and that their tender of proposals should be understood as having been made with full and complete knowledge thereof, and that the engineer’s [528]*528estimate of quantities contained in the specifications should be understood to be approximate and might be increased or diminished. The written specifications which the contractor was required to sign, to evidence his full understanding of the definitions contained therein; the contractor’s bid, showing the prices and figures on the approximate quantities, for the sum of which he proposed to undertake and complete all of the work, set out in tabulated form, and authenticated by the due execution thereof by each of the parties, bearing date, as we have already said, October n, 1898; and the final writing, as shown in the statement of the case, dated October 21, 1898 — each duly executed by the respective parties — constitute the written contract, and fill more than 20 closely printed octavo pages. These writings all have relation to a complex system of public improvement of large extent, and it is difficult to believe that it was at any time in the contemplation of either of the parties that this projected improvement should be made without any written evidence of a contract to guide them in the construction of the work, and in making their partial and final settlement. The theory of the plaintiff’s pleadings appears to be that, notwithstanding all these elaborate preparations, and the solemn execution of these writings by the parties, when the work was about to commence, and the office of the writings to begin to have effect, they were wholly set aside, and the work, so far as any work was done, was prosecuted, and settlements therefor made, under a verbal contract, which did not stipulate for definite prices, but left the parties at large to settle on the basis of the reasonable value of the work, materials, labor, and transportation used, and that the writings retain efficiency only as to that, part of the work which was never done. The pleadings of the plaintiff do not state what amount of money he received from the city on this work of constructing the sewer system, nor does the record anywhere show the amounts paid him during the progress of the work, or at the conclusion thereof; and, in the absence of bills of exception, we have no record evidence of the testimony offered and admitted on the trial.

In the brief submitted by counsel for the defendant in error, it is stated that the court overlooked the issue made in the replication to the second and third pleas to the first five counts of the complaint, so far as they related to the work and labor done and material furnished in making extra excavations as incident to the increased depths of the sewer system, and charged the jury that the plaintiff could not recover for such work and labor done and material furnished, and the amount of the verdict shows that the-jury responded to these instructions, and found for the plaintiff only under the sixth and seventh counts of the complaint. The sixth count of the complaint only claims $2,973.39 for extra work and material on the manholes required by the alleged changes of plan and specifications, and furnished by the defendant in error. The seventh count in the complaint claims only the sum of $13,990, alleged loss of profit on work alleged to have been contracted to be done, which the city afterwards, refused to have done. The verdict of the jury, with which the defendant in error appears to be satisfied, must embrace only these claims, and the interest that had accrued thereon, prior to the date of the verdict. • It would appear from these [529]*529undisputed features of the case that the changes in the proposed plan and specifications had not been radical.

We have fully examined and considered the cases cited on the brief submitted for the defendant in error, and relied upon in support of his contentions. Our attention has been most carefully given to the cases of Wood v. Ft. Wayne, 119 U. S. 312, 7 Sup. Ct. 219, 30 L. Ed. 416; Henderson Bridge Company v. McGrath, 134 U. S. 260, 10 Sup. Ct. 730, 33 L. Ed. 934; Wyandotte & D. R. Ry. v. King Bridge Company, 100 Fed. 197, 40 C. C. A. 325; County of Cook v. Henry Harms, 108 Ill. 151; and Salt Rake City v. Smith, 104 Fed. 451, 43 C. C. A. 637. We do not deem it necessary to review these cases, and specifically point out wherein the contracts and work and pleadings of the contractor in each of them materially differ from the contract and work and pleadings of the parties involved in the case before us. We do not think that the contractor has brought his claims within the authority of the cases he has cited. ■ On the contrary, it seems to us that the case made by him does not vary materially from those before the Supreme Court in Kihlberg v. United States, 97 U. S. 398, 24 L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Willis Bancroft, Inc. v. Millcreek Township
6 A.2d 916 (Supreme Court of Pennsylvania, 1939)
Interstate Power Co. v. Forest City
281 N.W. 207 (Supreme Court of Iowa, 1938)
Corporation of Charles Town v. Ligon
67 F.2d 238 (Fourth Circuit, 1933)
Whitworth v. Webb City
103 S.W. 86 (Supreme Court of Missouri, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
127 F. 521, 62 C.C.A. 319, 1904 U.S. App. LEXIS 3802, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-mobile-v-shea-ca5-1904.