Corporation of Charles Town v. Ligon

67 F.2d 238, 1933 U.S. App. LEXIS 4419
CourtCourt of Appeals for the Fourth Circuit
DecidedOctober 20, 1933
DocketNo. 3440
StatusPublished
Cited by3 cases

This text of 67 F.2d 238 (Corporation of Charles Town v. Ligon) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corporation of Charles Town v. Ligon, 67 F.2d 238, 1933 U.S. App. LEXIS 4419 (4th Cir. 1933).

Opinion

PARKER, Circuit Judge.

In 1926 .the town of Charles Town, W. Va*, hereafter referred to as defendant, entered into a contract with Ligón & Ligón, hereafter referred to as plaintiffs, for the construction of sewer lines and an outfall sewer and disposal plant. The contract embraced two projects, one covering the outfall sewer and disposal plant, referred to by the parties as project A, and the other covering the sewer lines, referred to as project B. Various changes yrere made by the town engineer in the work as .covered by the two pro j eets; but both were [240]*240eventually completed, claims of the contractors for changes in and additions to the work were submitted to and passed upon by the engineer, and the balance due under his estimate was tendered by the town and accepted by the plaintiffs. It is admitted that in this estimate there was an error of $113.08, but defendant consented that judgment be entered against it for this amount and same is not involved in the appeal.

After accepting the amounts tendered by the town as the balance due under the estimate and award of the engineer, the plaintiffs instituted this action to recover on a quantum meruit additional compensation for the work done, claiming that the changes in the work weré so radical as to take it out of the contract and that for like reason they were not bound by the award of the engineer. The court below submitted the case to a jury; and as to most of the claims for additional compensation, the verdict was for the defendant. On three items, however, the jury found for plaintiffs, awarding $1,42.7.85 as additional compensation for constructing the outfall sewer, $1,200 as a return of liquidated damages for delay in project A, and $2,060 as a return of liquidated damages deducted for delay in project B. There was judgment on this verdict in favor of plaintiffs, and defendant has appealed, assigning as error the refusal of the court to direct a verdict in its favor on these items, as well as alleged error in various parts of the charge and in refusal to give requested instructions. As we are of opinion that defendant was entitled to a directed verdict, as to all the matters in dispute except the $1,200 item, we need consider only this feature of the case.

The conclusion that defendant was entitled to a directed verdict as to all matters in dispute except the $1,200 item is based on the fact that the engineer in charge of the work passed upon all disputed matters, and under the terms of the contract his award was made binding upon the parties. The position of plaintiffs is (1) that, because of departure from its terms, the contract is not binding upon them and the award of the engineer has no binding effect; and (2) that, so far as the matter of liquidated damages is concerned, this was not covered by the submission clause of the contract. We think, however, that there was no such departure from the contract as relieved the parties from its terms; that under the contract they were bound by the decisions of the engineer as to liquidated damages as well as to other matters; and that all matters covered by the verdict of the jury except the $1,200 item were concluded by his award.

The written contract, applicable to both projects, provided, among other things, that the engineer might make alterations in the line, grade, plan, form, dimensions, or materials of the work; that the contractors should bear all losses resulting on account of amount or character of the work, or because the nature of the land in or on which the work was to be done should be different from what was estimated or expected; that the contractors should do extra work when requested by the engineer, receiving cost plus 15 per cent, for such extra work; and that the decision of the engineer should be final upon all questions as to the amount and value of the extra work. It provided also that, for failure of the contractors to complete the work by the time stipulated, the town should deduct $10 per day as liquidated damages; that the engineer should make monthly estimates which should be paid by the town to the contractors, after deducting certain percentages authorized to be retained; that after the completion of the contract the engineer should make a final estimate of the amount due and the town should pay the entire sum so found less amounts previously paid and an authorized retainage; and that the acceptance by the contractors of the last payment thus made should operate to release the town from all claims of and liability to the contractors. The engineer was made arbitrator of all questions which might arise under the contract; and it was provided that his estimate and decision upon any question which might arise “touching the contract” should be a condition precedent to the right of the contractors to receive any money under same. The exact language of this provision is as follows:

“Art. 2. To prevent dispute and litigation, the engineer shall in all eases determine the amount, quality, acceptability and fitness of the several kinds of work and materials which are to be paid for under this contract, shall determine all questions in relation to said work and the construction thereof, and shall in all eases decide every question which may arise relative to the fulfillment of this contract on the part of the contractor. His estimate and decision shall be final and conclusive upon both parties to this contract, and in case any question shall arise between the parties hereto, touching this contract such estimate and decision shall be a condition precedent to the right of the contractor, to receive any money under the contract.”

Shortly after the contract was awarded* [241]*241but before work under it had commenced, the engineer changed the course of the 2,800-foot outfall sewer line of project A for a distance of about 1,800 feet, so that instead of running ova* a meadow on a concrete cradle it ran around & hillside under the ground. This eliminated some of the concrete work upon which bids had been submitted, but changed the character of excavation only to the extent that, whereas the original bid contemplated approximately 1,900 feet of the 15-inch pipe placed at a depth of 0 to 3 feet, 1,100 feet at a depth of 3 to 5 feet, and 200 feet at a depth of 5 to 7 feet, the line as constructed involved the placing of only 1,477 feet at a depth of 3 feet or less, 936 feet at a depth of 3 to 5 feet, and 380 feet at a depth of 5 to 7 feet. On project B it was found necessary to place the sanitary sewer line at a depth greater than originally contemplated and to make certain other minor changes, and these were ordered by the engineer. Plaintiffs proceeded under the contract, and at the conclusion of the work filed claims with the engineer for additional work done and additional expense incurred because of the changes. The engineer rejected some of the items of the claim and allowed others. On project A, plaintiffs asked $1,425 additional compensation for excavation for the disposal plant and were awarded $1,389. For change in the course of the outfall sewer they asked $3,728 and were allowed $637. On various claims under project B $1,421.55 was allowed. All of these amounts were carried into the final estimate for which payment was made to and accepted by plaintiffs. With respect to the claim for change in the outfall sewer, which is the only one of the claims for extra compensation involved in this appeal, the engineer in passing upon the claim of plaintiffs, said:

“Item No. 2. The location of the 15-ineh outfall sewer through the Perry property was shifted from its location at the time that the bids were submitted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northeastern Const. Co. v. City of Winston-Salem
83 F.2d 57 (Fourth Circuit, 1936)
JA La Porte Corporation v. Mayor and City Council
13 F. Supp. 795 (D. Maryland, 1936)
Jones v. Foster
70 F.2d 200 (Fourth Circuit, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
67 F.2d 238, 1933 U.S. App. LEXIS 4419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corporation-of-charles-town-v-ligon-ca4-1933.