Teer v. George A. Fuller Co.

30 F.2d 30, 1929 U.S. App. LEXIS 2331
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 14, 1929
Docket2763
StatusPublished
Cited by11 cases

This text of 30 F.2d 30 (Teer v. George A. Fuller Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Teer v. George A. Fuller Co., 30 F.2d 30, 1929 U.S. App. LEXIS 2331 (4th Cir. 1929).

Opinion

WADDILL, Circuit Judge.

This is an appeal from the action of the United States District Court for the Eastern District of North Carolina in entering judgment for only $3,638.25 in appellant’s favor, and in dismissing as of nonsuit appellant’s claim for $25,448.45.

On December 10, 1927, appellant, Nello L. Teer, instituted an action in the superior eourt of Durham county, N. C., against the George A. Fuller Company, appellee here, to recover $31,973.58, which cause was removed to the Federal District Court at Raleigh on December 31, 1927. The complaint alleged, among other things, that the plaintiff, Teer, was engaged in the business of a grading 'contractor, and the defendant company, a corporation organized and existing under the laws of the state of New Jersey, but domesticated under the laws of the state of North Carolina, was engaged in the business of a general construction contractor; that on or about the 5th day of August, 1925, the defendant, then being general contractor for the construction of a number of buildings for Duke University, at Durham, 1SÍ. C., entered into a contract with plaintiff, whereby plaintiff was employed to do ■all the excavation work in connection with the construction of said buildings; and that in accordance with the terms of his employment, plaintiff entered upon and completed the work of excavation contracted for.

The complaint further alleged that while plaintiff was engaged in performing his contract with defendant, he was ordered and di *31 retted by defendant to do other and additional work, not included in plaintiff’s original contract of employment, and that the plaintiff and defendant entered into a second-contract, by which the plaintiff engaged to do said additional work, and defendant agreed to pay for such further work at the same unit price designated in the first contract of employment, and when no price was designated, defendant agreed to pay a reasonable compensation, viz., the cost to the plaintiff of doing such work, plus the usual and reasonable profit thereon; that, in accordance with the terms and provisions of said second contract, the plaintiff in good faith performed the additional work so agreed upon as designated by defendant’s engineers and other employes of defendant corporation, and when said work was completed defendant received and accepted the same; that during the progress of said work the plaintiff rendered detailed statements of his payrolls and costs to defendant; that by reason of the work done, which continued over a period from about August 1, 1925, to October 1, 1927, the defendant was indebted to plaintiff for the sum of $31,973.58, which was the reasonable value of the work performed by plaintiff; and that payment therefor, though demanded, had been refused. Interest on the sum sued for, from October 26,1927, was claimed.

The defendant, George A. Fuller Company, answered, denying that there was any contract except the original written contract of August 5, 1925, and denied generally the plaintiff’s claim, but set up and pleaded as a bar to plaintiff’s right of recovery the provisions of the written contract, with reference to the extra work sued for being authorized in writing. Defendant, in its answer, further stated that it had tendered plaintiff $3,467.25 for the work performed under the contract of August 5, 1925, which payment plaintiff had refused to- a ccept; and the answer denied that the extra work for which payment was claimed by plaintiff had ever been authorized by defendant.

The plaintiff, in replying, contended that the provisions of the contract were waived, and that the so-called extra work or overhaul was authorized verbally by the local superintendent in charge of defendant’s building operations at Duke University. The defendant corporation filed a rejoinder, denying the matters alleged in the plaintiff’s reply.

Upon the foregoing pleadings, the ease was tried, with the result that judgment was entered in favor of plaintiff for $3,638.-25-, admitted by defendant to be due, and the plaintiff’s cause of action as to alleged extra work was dismissed as of nonsuit. The plaintiff appealed, assigning error to the trial court’s action dismissing his claim for alleged extra work -and directing a nonsuit thereon, and also assigning error to its rulings in the admission and rejection of evidence, and in not submitting the issues between the parties to the jury for determination.

Assignments of error Nos. 1, 2, 3, and 4 are to the court’s action in permitting the introduction before the jury of extracts from certain specifications which were part of the contract between Duke University -and the defendant. The appellant’s exception to the court’s action in this respect is without merit. While doubtless the appellant was not bound by the specifications in question in the consideration of the claim for extra work, still to have refused to permit the introduction of the same might have operated prejudicially to the defendant in asserting its defense, and certainly it was not improper to permit them to bo introduced with appropriate instructions by the court as to their probative value.

Assignments Nos. 5 and 6 relate to- the action of the trial court in not allowing the plaintiff to answer two certain questions propounded to him as follows:

‘‘Q. You were asked yesterday the reason why the overhaul amounting to $24,000.00 as compared with the amount of the contract of $29',500.00, explain why that was?”

“Q. Mr. Teer, what was the actual cost to you for making this overhaul?”

—which the court likewise refused to permit to be answered. These two- assignments of error, Nos. 5 and 6, appear to us to be well founded, as the plaintiff shohld have been afforded the fullest opportunity to- make the very explanations called for. The plaintiff’s answer, preserved in the record in connection with the ruling on the exception, as under assignment 6, was as follows: “A. The actual cost to me was $23,134.87, which includes 2,285 hours for labor in spreading the dirt on the campus, amounting to $571.-25, and 28 hours use of a ten ton tractor in leveling the dumping ground between the Grand Stand and the Southgate Memorial Building, amounting to $210.00- To this actual cost of $23,134.87 I added my profit of $2,313.58, making the total of $25,448.4-5 as shown on the itemized statement attached to the complaint.” The answer clearly indicates the importance of the information sought to be elicited, as it was manifestly important *32 to the plaintiff to have the difference between the two bills in question properly explained. [3] Coming to the consideration of the case upon its merits arising upon the action of the court in withdrawing the same from the jury, and in entering judgment as of non-suit thereon, the legal questions revolve around the defendant’s plea that the plaintiff was barred the right of recovery for the work sued for, because the original contract between the plaintiff and defendant contemplated that such work should only be done upon a written order signed by a properly authorized officer or agent of the defendant, and at prices and terms agreed upon between them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Truhe v. Turnac Group, L.L.C.
1999 SD 118 (South Dakota Supreme Court, 1999)
Freeman v. Stanbern Construction Co.
106 A.2d 50 (Court of Appeals of Maryland, 1954)
Shapiro, Inc. v. Bimblich
101 A.2d 890 (District of Columbia Court of Appeals, 1954)
Buxton Limitida v. Rederi
28 F. Supp. 440 (S.D. New York, 1939)
The Argentino
28 F. Supp. 440 (S.D. New York, 1939)
Kelly v. Duke Power Co.
97 F.2d 529 (Fourth Circuit, 1938)
City of Wheeling v. John F. Casey Co.
74 F.2d 794 (Fourth Circuit, 1935)
Corporation of Charles Town v. Ligon
67 F.2d 238 (Fourth Circuit, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
30 F.2d 30, 1929 U.S. App. LEXIS 2331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/teer-v-george-a-fuller-co-ca4-1929.