The Sappho

94 F. 545, 36 C.C.A. 395, 1899 U.S. App. LEXIS 2378
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 2, 1899
DocketNo. 291
StatusPublished
Cited by15 cases

This text of 94 F. 545 (The Sappho) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Sappho, 94 F. 545, 36 C.C.A. 395, 1899 U.S. App. LEXIS 2378 (4th Cir. 1899).

Opinion

WADDILL, District Judge.

These are two libels in rem against the steamer tfappko, her tackle, apparel, etc., owned by the respondent company, the Mt. Pleasant & 8ulliyan’s Island Ferry Company, a corporation of South Carolina, conducting a ferry between the city of Charleston, Mt. Pleasant, and Sullivan’s Island, in said stale, the said steamer being- employed in that service. The controversy arose ont of a contract for repairs to be made upon the said steamer. The claim of Samuel J. Pregnall, libelant, contractor and shipwright, is for a balance due on account for repairs, labor, and supplies in the sum of ,82,230.82. The claim of William M. Bird & Co., libelants, merchants, is for !|>807.43 for materials furnished for the steamer in mak[546]*546ing such, repairs. In the lower court all of the testimony was taken before a special examiner, appointed for the purpose, and upon the depositions so taken the two causes were heard together, and the district court, by order of the 30th of August, 1808, dismissed both libels. 89 Fed. 366. The libelant Samuel J. Pregnall, on the 25th day of February, 1897, entered into a written' contract with the respondent company for making certain repairs to the said steamer Sappho, specifically set forth in said contract, and which work may be particularized as follows:

“Haul out the said steamer on the marine railway of said contractor; take out and renew all clamps; take out and renew main water-wheel beams; renew the guards, and also the mudsills all around the steamer; put in new breast hooks; put in two extra sister keelsons; put in two new extra standards, one in each side, with hog rods and one-half inch iron; strip off entire copper from bottom, reef out all old oakum, and reeaulk entire vessel to deck; remetal with yellow metal or copper; straighten and plumb vessel wljile on railway, putting in 2,172 feet timber at $1.00, putting in 3,901 feet planking at 60 cents, 820 feet ceiling at 20 cents.”

At the prices fixed in the contract, these items amounted to $6,-676.60. Under this contract, the libelant Pregnall regularly entered upon the work to be performed by him, and, after getting the steamer on the railway of his yard, and stripping her, it was found that her condition was much worse than had been anticipated, so much so that it was impracticable to go on with the work according to the contract; and thereupon, after conference with the libelant, the master of the steamer, the president of the respondent company, and the government inspector, other work was done, much of it to the hull of the steamer itself, not stipulated for in the contract, amounting to the sum of $2,539.17, made necessary by reason of the rotten, defective, and unsafe condition in which the same was found to be, in order to put said steamer in a proper and safe condition for service. No question was raised as to the performance of the work covered by the original contract, and the amount due thereon was fully paid, but the bill for the extra work was disputed as a whole, and the result was the filing of the libel herein; to which the respondents replied that all work set forth in the written contract had been fully paid for, and $308.35 in addition, and denied further liability, upon the ground that the extra work was not embraced in the written contract, and was not authorized. They further alleged that the work on libelant’s part was unskillfully performed, and that there was delay in the completion of the same, whereby damage accrued to them in the sum of $2,200. No testimony was taken by claimant tending to maintain its defense, either as to the alleged unskillful manner in which the work was performed, or that there was any delay in its execution, and the case turned in the lower court solely upon the right of the libelant, under the circumstances, to recover for the extra work done. The written contract contained a clause that no new work of any kind done on the steamer, and no work of any kind, should be considered as extra work unless a separate estimate in writing should be made for the same before its commencement, and submitted by the contractor to the respondent company, and the signature of the chairman of the board of directors obtained thereto. [547]*547The learned judge in the court below, while recognizing that this clause might be waived by the parties, and that they, either by their acquiescence in what was being done, or ratification of what had been done, might make themselves liable for extra work, was, nevertheless, of opinion that there was not sufficient evidence in the record to sustain the contention that the respondent company had ever formally abrogated the written contract,, or, in view of the said clause as to extra work, had ever authorized the libelant to do the work as charged for by him, or acquiesced in or ratified what he did so as to become liable therefor. With these conclusions we do not agree, and think, under the circumstances, the libelant is entitled to recover for the amount of the extra work performed by him. The decision of the trial cour*t upon questions of fact, where the judge saw and heard the witnesses testify, might have great and controlling weight; hut here, where the evidence was taken by an examiner, this court will more readily examine the same, and reach its own conclusions thereon. The Glendale, 26 C. C. A. 500, 81 Fed. 633, 635; Duncan v. Nicholls, 44 Fed. 302; The Ludvig Holberg, 43 Fed. 120; The Thomas Melville, 37 Fed. 271. But we do not regard this as a case depending upon conflicting evidence, or the credibility of witnesses, hut rather upon the legal effect of what it is admitted was said and done by those acting for the respondent corporation under circumstances not disputed. Thai there was a necessity for the extra work is apparent from the whole evidence, and without the extra work it would have been entirely impracticable to have carried out the written contract at all. The claimant’s witness Cherry, the master of the steamer, aud superintendent placed in charge of the repairs, thus described the condition of the steamer after she was stripped:

“I did not think she was in very hail shape after we got her on the railway until we ripped the lining off, and it was all gone underneath. The timbers would look good on top, but were all gone underneath, like the shell of an egg.”

He also stated, in answer to the question of whether he had not stated to Mr. Bird, the secretary of the company, that they would have to make a new hull:

“Tes, I told him in these words: That I thought it cheaper to pay Mr. Pregnall to cancel the obligation, and build a new hull. I thought it would be cheaper in the end.”

The United states inspector of hulls, W. H. Cannon, testified as follows :

“Question. What did she show after she was stripped? Answer. Very bad. Timbers completely gone, except eight or ten under the engine. It was necessary for them all to come out except ten or twelve. Question. Did you see any decayed knees? Answer. Some I did not count. More were there, but, when I found that Capit. Cherry had a disposition to repair the boat, I did not interfere with him.”

Witnesses Beth Ferrara and John F. Cummen, both shipwrights, and who worked upon the steamer while the repairs were being made, say that the main keelson, fore and aft, and various portions of the hull, were in a rotten and charred condition; that it was dry rot from the heat and dampness, and would not hold anything, and that it was [548]*548knocked out with a mall; and that the steamer in her condition was utterly unseaworthy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Wheeling v. John F. Casey Co.
74 F.2d 794 (Fourth Circuit, 1935)
Hunt v. Tulsa Terrazzo & Mosaic Co.
1932 OK 394 (Supreme Court of Oklahoma, 1932)
Teer v. George A. Fuller Co.
30 F.2d 30 (Fourth Circuit, 1929)
Sartoris v. Utah Const. Co.
21 F.2d 1 (Ninth Circuit, 1927)
Martin v. Richmond, F. & P. R.
3 F.2d 26 (Fourth Circuit, 1924)
The Kalfarli
277 F. 391 (Second Circuit, 1921)
Jefferson Hotel Co. v. Brumbaugh
168 F. 867 (Fourth Circuit, 1909)
Columbia Dredging Co. v. Sanford & Brooks Co.
163 F. 362 (E.D. Virginia, 1908)
The Edward Smith
135 F. 32 (Sixth Circuit, 1905)
Kent v. Addicks
126 F. 112 (Third Circuit, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
94 F. 545, 36 C.C.A. 395, 1899 U.S. App. LEXIS 2378, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-sappho-ca4-1899.