United Steed Co. v. Casey

262 F. 889
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 13, 1920
DocketNo. 3302
StatusPublished
Cited by19 cases

This text of 262 F. 889 (United Steed Co. v. Casey) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Steed Co. v. Casey, 262 F. 889 (6th Cir. 1920).

Opinion

DONAHUE, Circuit Judge.

On the 4th day of September, 1915, the United Steel Company entered into a contract in writing with the John F. Casey Company, by the terms of which the latter company agreed to do certain excavating, grading, back-filling, and concreting at fixed and definite prices per cubic yard. This contract was signed-[890]*890on the part of the United Steel Company by S. R. Smythe, engineer, and on the part of the Casey Company by John F. Casey.

The Casey Company completed this contract September 23, 1916, and later commenced an action against the Steel Company to recover $112,295.99 for and on account of work and labor performed and material furnished. It is admitted that, based upon the unit prices named in the written contract, there was then a balance due the Casey Company from the Steel Company of approximately $12,000. The Steel Company denied that the Casey Company was entitled to recover this balance, by reason of the fact that it had failed to complete the work at the time specified in the contract; but there is now no longer a serious dispute in reference to this amount. '

The real question in dispute is the claim of the Casey Company that on or about the 22d day of November, 1915, the Steel Company agreed with it that the unit prices named in the written contract should not be the measure of compensation for the work then or thereafter to be done, but, on the contrary, that the Steel Company would pay the Casey Company, for the work performed and material furnished, the fair and reasonable value thereof.

The Casey Company claims that the fair and reasonable value of the material furnished and the work done by it exceeds by about $100,000 the amount that would be due it, if calculated upon the unit price fixed in the contract. The Steel Company in its answer denied that any oral agreement had been made changing the prices per unit fixed in the written contract, and in its cross-petition asks damages for $500,-000 for failure to complete the work without delay and in the quickest possible time, as provided in the contract. The jury returned a verdict against the Steel Company for the sum of $68,831.56, including the amount of $12,261.73, upon which verdict a judgment was rendered accordingly. This proceeding in error is prosecuted to reverse that judgment.

It is contended on the part of the plaintiff in error that there was no consideration for the alleged oral promise of the Steel Company to pay the Casey Company a fair arid reasonable amount'for material, to be furnished, that the court erred in charging the jury that a preponderance of the evidence would be sufficient to warrant the finding that the written contract was orally modified, and that the verdict of the jury finding in favor of the plaintiff upon that issue is not sustained by clear and convincing proofs.

[ 1 ] Whether the oral contract was made as pleaded in the petition,, by the terms of which the Steel Company agreed to pay the Casey Company the fair and reasonable value of the work done and material furnished by it, instead of the unit price named in the written contract, is purely a question of fact for the jury. The correctness of this verdict in this particular involves the weight of the evidence, which this court will not consider, except in connection with the degree of proof required to establish such oral contract, the terms of which differ materially in a very important particular from the terms of the-written one. The provision in the contract that “no extras will be considered or allowed in connection with this contract, without first hav[891]*891ing an understanding and written order between John E. Casey Company and the United Steel Company,” does not in terms prohibit the making of an oral contract changing the compensation to be paid for the work and material actually covered by the written contract, but it does emphasize the fact that at the time this contract was executed it was the purpose and iptention of the parties that the rights and liabilities of each should be measured and' determined by its terms, at least as to the extent of the work to be done and the quantity of material to be furnished. While this provision applied only to extra material and labor not specified or included in the contract, nevertheless it was a fact to be considered by the jury in connection with the evidence tending to establish an oral contract, but in no wise controlling the determination of that issue.

[2] The plaintiff avers a new and distinct contract as to price, not in writing, made some months after the original written contract was made; nevertheless we know of no rule of law or evidence that requires an oral contract, or an oral modification of a written contract, to be established by clear and convincing proofs. On the contrary, the authorities seem to be unanimous that such contracts may be established by a preponderance of the evidence. Jones, Stranathan & Co. v. Greaves, 26 Ohio St. 2, 20 Am. Rep. 752; Lyon v. Fleahmann, 34 Ohio St. 151-155; Shaul v. Norman, 34 Ohio St. 157; Bell v. McGinness, 40 Ohio St. 204, 48 Am. Rep. 673; Achenbach v. Stoddard, 253 Pa. 338, 98 All. 604; Piatt’s Administrator v. U. S., 89 U. S. (22 Wall.) 496, 506, 22 U. Ed. 858.

The case of Ashley v. Henahan, 56 Ohio St. 559, 47 N. E. 573, involved a claim by the contractor for extra work done and material furnished in defiance of the express provision of the written contract that he would make no such claim except upon a written order from the architect. The other cases cited by counsel for plaintiff in error involve like questions, except the case of Hasler v. West India Steamship Co., 212 Fed. 862, 129 C. C. A. 382, in which case there was no claim made that a new oral contract, changing or modifying the terms of a written contract, had been made; but, on the contrary, the plaintiff claimed" that the terms of the contract as written had been orally waived by' agents of the other contracting party, and this without any consideration whatever paid or agreed to be paid by the party in default.

We are, therefore, of the opinion that the trial court did not err in its charge to the jury touching the degree of proof required to establish an oral modification of the terms of a written contract.

[3] The more important question, perhaps, is the claim that there is no consideration for the oral agreement. There is evidence in this record that prior to the time it is claimed this oral contract was made, and after the Casey Company had started to put its machinery in place, it was notified by telegram from Mr. Smythe, representing the Steel Company, that it had changed the location of the steel plant three hundred feet further east than as first located, and commanding him to stop all work at once in connection with erection of equipment and cable work; that this change of location necessitated the making of [892]*892a new fill, during all of which time the Casey Company was compelled to suspend operations; that after the Casey Company had relaid its tracks it was informed by the Steel Company that the change in location was 3168/iofeet, instead of 300 feet, and again the track had to be removed and placed still further east. The actual cost of these changes were paid by the Steel Company, but the Casey Company was delayed at least three weeks thereby.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brian Construction & Development Co. v. Brighenti
405 A.2d 72 (Supreme Court of Connecticut, 1978)
Hoffman v. Glock
315 A.2d 551 (Court of Special Appeals of Maryland, 1974)
Taylor v. University National Bank
282 A.2d 91 (Court of Appeals of Maryland, 1971)
Pepsi-Cola Bottling Co. of Asbury Park v. Pepsico, Inc.
282 A.2d 643 (Court of Chancery of Delaware, 1971)
Charles Burton Builders, Inc. v. L & S Construction Co.
271 A.2d 534 (Court of Appeals of Maryland, 1970)
Wilmar Marine Engineering & Sales Corp. v. M/V Perseo
278 F. Supp. 345 (E.D. Louisiana, 1967)
Warren Bros. Roads Co. v. United States
105 F. Supp. 826 (Court of Claims, 1952)
United States v. Southern Piping & Erecting Co.
92 F. Supp. 569 (E.D. Tennessee, 1950)
Hotchner v. Neon Products, Inc.
163 F.2d 672 (Sixth Circuit, 1947)
E. J. Albrecht Co. v. New Amsterdam Casualty Co.
163 F.2d 16 (Seventh Circuit, 1947)
City of Wheeling v. John F. Casey Co.
74 F.2d 794 (Fourth Circuit, 1935)
Teer v. George A. Fuller Co.
30 F.2d 30 (Fourth Circuit, 1929)
Blakeslee v. Board of Water Commissioners
139 A. 106 (Supreme Court of Connecticut, 1927)
Postell v. Joseph Brothers Lumber Co.
240 Ill. App. 384 (Appellate Court of Illinois, 1926)
John Johnson Construction Co. v. State
211 A.D. 512 (Appellate Division of the Supreme Court of New York, 1925)
Commercial Car Line v. Anderson
224 Ill. App. 187 (Appellate Court of Illinois, 1922)
J. C. Shaffer & Co. v. West Tennessee Grain Co.
271 F. 820 (Sixth Circuit, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
262 F. 889, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-steed-co-v-casey-ca6-1920.