Blakeslee v. Board of Water Commissioners

139 A. 106, 106 Conn. 642
CourtSupreme Court of Connecticut
DecidedOctober 5, 1927
StatusPublished
Cited by54 cases

This text of 139 A. 106 (Blakeslee v. Board of Water Commissioners) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blakeslee v. Board of Water Commissioners, 139 A. 106, 106 Conn. 642 (Colo. 1927).

Opinion

Maltbie, J.

This action comes before us upon a demurrer to the complaint. The first count of the complaint states the following facts: On August 23d, 1915, the plaintiffs entered into a contract with the defendant for the construction of a large dam, the price therefor being fixed in the contract at certain named sums for the various items of work to be performed. The contract provided that the work was to be completed in thirty-three months and, unless this was done, the plaintiffs were to pay the defendant as liquidated damages $100 for each day thereafter required. Both parties understood when the contract was made that the plaintiffs had to move a great amount of earth and rock, necessitating the use, in large quantities, of high explosives, of coal for the operation of steam shovels and other apparatus, of lumber, cement, iron, and *645 steel, and vitrified pipe, and of small tools and equipment; and that the plaintiffs had to employ a great number of skilled and unskilled laborers. The parties did not contemplate that this country was to become involved in the war then raging in Europe.

The complaint then proceeds to allege, in considerable detail, these further facts: Early in 1916, rumors became prevalent that this country might become embroiled in the war. Thereafter steps taken in this country in preparation for its becoming a participant therein, and in the conduct of it after war was declared, resulted in the practical impossibility of the plaintiffs procuring the laborers necessary to carry on the work under the contract, in embargoes upon the transportation of materials and supplies, in the diversion of materials and supplies for the use of the government, and in interference with the progress of the work. As a result of these conditions “the contract became impossible of performance according to its terms.” Thereupon the plaintiffs and the defendant discussed the situation, and the plaintiffs notified the defendant that because of the conditions confronting them due to the war, “it would be impossible for the plaintiffs to continue performance of said work at the prices specified in said contract.” The defendant then stated that it recognized the conditions, and that the dam under construction was for the purpose of forming a compensating reservoir from which to supply water it was under contract to furnish to various milling concerns then engaged in the production of war materials.

It is then alleged (par. 8): “Said defendant then and there agreed to and with the plaintiffs that if the plaintiffs would proceed with the work called for under said contract, it, the defendant, would waive the penalty provided for in said contract on account of *646 its non-completion within the thirty-three months’ period specified in said contract and that it would extend the time necessary for the completion of said work. The defendant informed the plaintiffs that under legislation as it then existed defendant was powerless to change the compensation provided for in said contract but defendant then and there promised and agreed to and with the plaintiffs, if legislation could be effected permitting defendant to change the compensation called for under said contract, defendant would do all in its power to so change the compensation called for under said contract as to prevent the plaintiffs from suffering any actual loss which might be occasioned through its performance. The plaintiffs, relying upon the promise and assurance of defendant to waive the penalty provided for in said contract and extend the time of its completion and relying upon the promise and assurances of defendant that, if legislation could be effected permitting it so to do, the defendant would do all in its power to alter the compensation called for under said contract so as to prevent the plaintiffs from suffering any actual loss in its completion, continued to perform the work and furnish the material and supplies called for under said contract and prosecuted said work expeditiously until the entire work called for under said contract had been completed. In view of the impossibility of performing the contract according to its terms, the new agreement mentioned in this paragraph was made between the plaintiffs and the defendant, (par. 9.) The said contract theretofore existing between the plaintiffs and defendant, was rescinded by waiving of the penalties already incurred, and also was rescinded in so far as the time limit under which the work was to be performed and the compensation to be paid therefor, were concerned by changing the effect of the last payment as a release as stated in *647 Article XXVI of the contract, and a new contract entered into whereby the time limit was to be extended and the compensation to be paid the contractor was to be the actual cost of the work, labor and material to be furnished by the plaintiffs if legislation could be effected permitting defendant to alter the compensation so as to permit it to pay the actual cost.”

The complaint then goes on to allege that the plaintiffs caused a bill to be presented in the General Assembly authorizing municipal corporations, boards and departments thereof, to change the terms of contracts, the cost of performance of which had been increased by war interference, so as to make the compensation therefor sufficient to prevent the contractor from suffering any actual loss due to performance of his contract, and that thereafter this bill was duly passed and approved by the Governor. The complaint then continues with an allegation that the plaintiffs have fully completed the contract and have presented to the defendant a bill for $159,000, representing the actual cost of the work above the amount paid to them under the terms of the contract, and that the defendant has refused to pay it.

The defendant demurred to this count of the complaint upon five grounds, which may be briefly summarized as follows: (1) It does not appear that the contract originally made by the parties has ever been rescinded or modified in so far as the compensation to be paid the plaintiffs is concerned; (2) it does not appear that there was any consideration for any alleged agreement to increase the compensation provided by the original contract, and it does appear that the plaintiffs performed no services or furnished no material except those required under that contract; (3) it appears that when the contract was made war was already being waged in Europe and the possibility of *648 this country becoming involved then existed, that the contract had no provision for such a contingency, and that it was not impossible of performance; (4) the defendant as an agent of the city of Hartford could not lawfully, under the 24th Amendment of the Constitution of this State, increase the compensation agreed to be paid the plaintiffs beyond that specified in the contract; (5)-the Act of the General Assembly referred to in the complaint did not permit the defendant to change the- compensation of the plaintiffs provided in that contract.

With reference to the first ground of demurrer, while the allegations of the complaint are somewhat equivocal, still the plaintiffs might clearly offer evidence under them which would establish an agreement between the parties for a modification of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Willamette Management Associates, Inc. v. Palczynski
38 A.3d 1212 (Connecticut Appellate Court, 2012)
New England Rock Services, Inc. v. Empire Paving, Inc.
731 A.2d 784 (Connecticut Appellate Court, 1999)
Fgb Realty Advisors v. Seven Winds Realty, No. Cv 94 0066261 (Dec. 22, 1995)
1995 Conn. Super. Ct. 14486 (Connecticut Superior Court, 1995)
Fgb Realty Advisors, Inc. v. Seven Winds, No. Cv 94 0066260 (Dec. 22, 1995)
1995 Conn. Super. Ct. 14473 (Connecticut Superior Court, 1995)
fifty/unionoreo v. Russell Sirianni Asso., No. Cv94 0356903s (Jun. 7, 1995)
1995 Conn. Super. Ct. 7199 (Connecticut Superior Court, 1995)
Marcus v. DuPerry
611 A.2d 859 (Supreme Court of Connecticut, 1992)
Devine Pieszak v. Matthews, No. 010439 (Aug. 8, 1991)
1991 Conn. Super. Ct. 7341 (Connecticut Superior Court, 1991)
Thermoglaze, Inc. v. Morningside Gardens Co.
583 A.2d 1331 (Connecticut Appellate Court, 1991)
Stackpole Moore Tryon Co. v. Career Path, No. 354111 (Jul. 31, 1990)
1990 Conn. Super. Ct. 355 (Connecticut Superior Court, 1990)
Guilford Yacht Club Ass'n v. Northeast Dredging, Inc.
438 A.2d 478 (Supreme Judicial Court of Maine, 1981)
Brian Construction & Development Co. v. Brighenti
405 A.2d 72 (Supreme Court of Connecticut, 1978)
Taylor v. Lavietes
372 A.2d 157 (Supreme Court of Connecticut, 1976)
Broderick v. Jackman
355 A.2d 234 (Supreme Court of Connecticut, 1974)
Custer v. Bonadies
318 A.2d 639 (Connecticut Superior Court, 1974)
Charter Oak Estates, Inc. v. Kearney
280 A.2d 885 (Supreme Court of Connecticut, 1971)
R-Way Furniture Company v. Powers Interiors, Inc.
456 S.W.2d 632 (Missouri Court of Appeals, 1970)
Melcher v. Melcher
263 A.2d 91 (Connecticut Superior Court, 1970)
Jacobson Electric Co. v. Rome Fastener Corporation
238 A.2d 415 (Supreme Court of Connecticut, 1968)
Rossignol v. Danbury School of Aeronautics, Inc.
227 A.2d 418 (Supreme Court of Connecticut, 1967)
Habib v. Dome
234 A.2d 122 (Connecticut Appellate Court, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
139 A. 106, 106 Conn. 642, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blakeslee-v-board-of-water-commissioners-conn-1927.