Brian Construction & Development Co. v. Brighenti

405 A.2d 72, 176 Conn. 162, 1978 Conn. LEXIS 1009
Supreme Court of Connecticut·Decided September 19, 1978·Published·Cited by 22 cases

Opinion

Loiselle, J.

The plaintiff, a contractor, brought this action for damages against the defendant, a subcontractor, alleging that the defendant had breached a contract under which he had promised *163 to perform certain excavation work for the plaintiff. The defendant counterclaimed. The court rendered judgment for the defendant on the plaintiff’s claim and for the plaintiff on the defendant’s counterclaim. Prom the judgment for the defendant, the plaintiff has appealed.

The relevant facts as found by the court are as follows: In early 1968, Joseph E. Bennett, doing business as Joseph E. Bennett Company, entered into a contract with Seymour B. Levine (hereinafter the owner) for the construction of a post office building in Bristol. Shortly thereafter, Bennett assigned the contract to the plaintiff, who, on October 10, 1968, entered into a written subcontract with the defendant. Pursuant to that contract, consisting of a standard subcontract agreement plus specifications, the defendant agreed to perform “all Excavation, Grading, Site Work, Asphalt Pavement, Landscaping, and Concrete Work” and “everything requisite and necessary to finish the entire work properly.” In return, the defendant was to receive $104,326.

The defendant commenced excavation of the premises on October 15, 1968, at which time he discovered considerable debris below the surface, consisting in part of concrete foundation walls, slab floors, underground tanks, twisted metals and various combustible materials. Apparently, the discovered walls and floor had been part of the basement of an old factory which had previously been located on the site. The plaintiff had previously taken test borings of the excavation site, the results of which had been given to the defendant prior to the execution of the subcontract. The defendant had relied upon those results, although they proved *164 to be grossly inaccurate. Neither party had been aware of the rubble and, consequently, its removal was not specifically called for by the plans and specifications included in the subcontract, nor was the cost of its removal included in the contract price. Nonetheless, the existence of the rubble necessitated excavation beyond the depth anticipated in the plans and specifications and the post office building could not be constructed without its removal.

A provision of the general contract between the owner and Bennett provided that “no extra work or change shall be made unless in pursuance of a written order from the Owner signed or countersigned by the Architect, or a written order from the Architect stating that the Owner has authorized the extra work or change.” A separate provision of the contract specified that each subcontractor was to make all claims for extras “to the Contractor in the manner provided in the General Conditions of the Contract . . . for like claims by the Contractor upon the Owner.” A provision of the subcontract reiterated this requirement, adding that “no extra work or other change will be commenced by the Sub-Contractor without the Contractor’s prior approval in writing.” Similarly, both contracts included provisions under which the subcontractor agreed to be bound to the contractor by the terms of the general contract and to assume toward the contractor all those obligations which he, under the contract, assumed towards the owner.

Upon discovery of the unanticipated debris, the plaintiff notified the architect, the attorney for the owner, representatives of the Bristol redevelopment agency, which owned the building site, and representatives of the postal service of the existence *165 of the rubble. 1 All agreed that removal of the rubble was requisite for completion of the building, yet none would issue written authorization for its removal.

On October 21,1968, the defendant ceased working on the excavation site and notified the plaintiff of his refusal to continue. Subsequently, the defendant offered to complete the subcontract if the plaintiff would have the unsuitable material removed. The plaintiff refused this offer. He then ordered the defendant to remove the rubble as part of “everything requisite and necessary” under the subcontract. The defendant refused. When the plaintiff was confronted with this situation, and no one would take the responsibility to authorize the removal of the rubble, although its removal was necessary for the contractor to complete his contract, he chose to enter into a further agreement with the defendant for work not included in the subcontract. The plaintiff and the defendant orally agreed that the defendant would be paid his costs for removing the unanticipated rubble, plus 10 percent. By letter dated November 7, 1968, the plaintiff confirmed this oral agreement. Although requested in the letter to do so, the defendant failed to sign and return a copy of the letter to the plaintiff. Nonetheless, the defendant returned to work, continuing until about November 18, 1968, at which point he left the job, refusing to return despite the plaintiff’s request that he complete the work. The plaintiff completed his own contract with the owner, suffering, as a result of the defendant’s abandonment, considerable damages.

*166 On appeal to this court, most of the plaintiff’s claims of error focus upon the court’s conclusion that, by interpreting the terms of the general contract as being incorporated into the subcontract, the issuance of a written extra work order signed b$- the architect was a condition precedent to the defendant’s obligation to remove the rubble. The plaintiff’s final claim, however, raises the issue of whether the oral agreement between it and the defendant constituted a valid agreement obligating the defendant to remove the unexpected rubble. Because we find this issue to be dispositive of the appeal, the other claims need not be specifically addressed.

It is an accepted principle of law in this state that when a party agrees to perform an obligation for another to whom that obligation is already owed, although for lesser remuneration, the second agreement does not constitute a valid, binding contract. See, e.g., Dahl v. Edwin Moss & Son, Inc., 136 Conn. 147, 69 A.2d 562; Gruber v. Klein, 102 Conn. 34, 127 A. 907; Warren v. Skinner, 20 Conn. 559. “The basis of the rule is generally made to rest upon the proposition that in such a situation he who promises the additional compensation receives nothing moré than that to which he is already entitled and he to whom the promise is made gives nothing that he was not already under legal obligation to give. 1 Williston on Contracts, § 130.” Blakeslee v. Board of Water Commissioners, 106 Conn. 642, 652, 139 A. 106. Where, however, the subsequent agreement imposes upon the one seeking greater compensation an additional obligation or burden not previously assumed, the agreement, supported by consideration, is valid and binding upon the parties. See, e.g., Simone v. Kirschner, 100 Conn. 427, 124 A. 20.

*167 In

Free access — add to your briefcase to read the full text and ask questions with AI

Brian Construction & Development Co. v. Brighenti, 405 A.2d 72, 176 Conn. 162, 1978 Conn. LEXIS 1009 (Colo. 1978).

405 A.2d 72 (Brian Construction & Development Co. v. Brighenti) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Schimenti Construction Co., LLC v. Schimenti
217 Conn. App. 224 (Connecticut Appellate Court, 2023)
Thoma v. Oxford Performance Materials, Inc.
Connecticut Appellate Court, 2014
Willamette Management Associates, Inc. v. Palczynski
38 A.3d 1212 (Connecticut Appellate Court, 2012)
M.J. Daly & Sons, Inc. v. City of West Haven
783 A.2d 1138 (Connecticut Appellate Court, 2001)
New England Rock Services, Inc. v. Empire Paving, Inc.
731 A.2d 784 (Connecticut Appellate Court, 1999)
Perlin v. Henley-Cohn, No. Cv96-0385895s (Jul. 24, 1997)
1997 Conn. Super. Ct. 7807 (Connecticut Superior Court, 1997)
Gorman v. Earmark, Inc.
968 F. Supp. 58 (D. Connecticut, 1997)
Fgb Realty Advisors v. Seven Winds Realty, No. Cv 94 0066261 (Dec. 22, 1995)
1995 Conn. Super. Ct. 14486 (Connecticut Superior Court, 1995)
Fgb Realty Advisors, Inc. v. Seven Winds, No. Cv 94 0066260 (Dec. 22, 1995)
1995 Conn. Super. Ct. 14473 (Connecticut Superior Court, 1995)
fifty/unionoreo v. Russell Sirianni Asso., No. Cv94 0356903s (Jun. 7, 1995)
1995 Conn. Super. Ct. 7199 (Connecticut Superior Court, 1995)
Daniel v. Keane Agency, Inc. v. Butterworth, No. 31 31 81 (Feb. 22, 1995)
1995 Conn. Super. Ct. 1355-E (Connecticut Superior Court, 1995)
Lattanzio v. University of Hartford, No. Cv93-0529459s (Jun. 7, 1994)
1994 Conn. Super. Ct. 6109 (Connecticut Superior Court, 1994)
Allen, Russell Allen v. Mikkelson, No. Cv 93-0457225s (May 17, 1994)
1994 Conn. Super. Ct. 5306 (Connecticut Superior Court, 1994)
Union Trust Company v. Jackson, No. Cv91 0286938s (Jul. 14, 1992)
1992 Conn. Super. Ct. 6648 (Connecticut Superior Court, 1992)
Pds Engineering Const. v. Double Rs, No. Cv90-0378684 (Dec. 19, 1991)
1991 Conn. Super. Ct. 10306 (Connecticut Superior Court, 1991)
American Home Builder's v. Blonder, No. Cv88-0040857 (Jun. 14, 1991)
1991 Conn. Super. Ct. 5624 (Connecticut Superior Court, 1991)
Thermoglaze, Inc. v. Morningside Gardens Co.
583 A.2d 1331 (Connecticut Appellate Court, 1991)
S.H.V.C., Inc. v. Roy
450 A.2d 351 (Supreme Court of Connecticut, 1982)
General Electric Supply Co. v. Southern New England Telephone Co.
441 A.2d 581 (Supreme Court of Connecticut, 1981)