Dahl v. Edwin Moss & Son, Inc.

69 A.2d 562, 136 Conn. 147, 1949 Conn. LEXIS 212
CourtSupreme Court of Connecticut
DecidedNovember 15, 1949
StatusPublished
Cited by19 cases

This text of 69 A.2d 562 (Dahl v. Edwin Moss & Son, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dahl v. Edwin Moss & Son, Inc., 69 A.2d 562, 136 Conn. 147, 1949 Conn. LEXIS 212 (Colo. 1949).

Opinion

Maltbie, C. J.

This is an action arising out of contract wherein the plaintiff, an electrical contractor, seeks damages from the defendant, a general contractor, for material and labor which he furnished and which he claims were not called for by the contract. *149 The complaint is in two counts. In the first, the plaintiff seeks to recover extra expenses to which he was put because he was required to install an underfloor duct of a type not called for in the contract and specifications and because of a claimed change in the plan of procedure in which the work was to be done. In the second count, recovery is sought upon the basis of an agreement by the defendant to pay the plaintiff the difference between the cost of the type of duct upon which he had figured the amount for which he would do the work and the cost of the type of duct he was required to install. The defendant has appealed from a judgment for the plaintiff.

The facts found, in which no material change can be made, present this situation: The plaintiff is an experienced and capable electrical contractor. The defendant has been engaged for many years in the general contracting business. Edwin H. Moss, the defendant’s president, and Robert S. Moss, its secretary and treasurer, are its agents for all purposes. During 1943 the Chance Vought Aircraft Division of the United Aircraft Corporation, hereinafter called Chance Vought, was engaged in constructing airplanes for the United States navy in a factory in Stratford, Connecticut. In that year it had a contract with the navy department to build a two-story factory extension, which would be owned by the navy, at its Stratford plant. In September, 1943, Chance Vought entered into a subcontract with the defendant, by the terms of which the defendant was to erect the extension. The plaintiff, at the defendant’s request, submitted a bid for the electrical work required. On October 27, 1943, the defendant signed a “Purchase Order” addressed to the plaintiff, the material portion of which was as follows: “Furnish all necessary labor and materials for a complete job of Electrical Work all in strict accordance with plans, *150 specifications, and addenda prepared by Albert Kahn Associates and subject to the approval of Albert Kahn Associates, for the sum of $103,000.00.” Albert Kahn Associates was the firm of architects in charge . of the construction of the building and we shall hereafter refer to it as the architect.

The factory was in use by Chance Vought. The specifications contained a statement that it was the intention of the owner first to complete the part of the extension extending from column lines S to J, and the plaintiff figured the amount of his bid on that basis. On the north side of the existing building was a driveway and loading dock which Chance Vought deemed necessary to the efficient operation of its factory. It required the defendant to keep the dock open and unobstructed until a new loading dock could be built elsewhere, and it ordered the defendant to change its plan of procedure to accomplish that result. This the defendant did. The plaintiff’s plan of installation had to be changed and additional financial burdens were thereby imposed upon him. The plaintiff knew of the presence of the dock but did not know that its use would interfere with the procedure in carrying on the work. He spoke to Edwin Moss about the shift in the plan of operation, stating that it would result in additional cost, and Moss said that he would have the same experience and was going to take the matter up with Chance Vought. He did ask Chance Vought to pay his company additional sums so that the plaintiff might be compensated. The plaintiff later demanded that the defendant pay him the extra expense but the defendant refused to do so.

Included in the plaintiff’s work was the laying of 10,000 feet of underfloor duet, a device for carrying ■electric and other wires beneath the floor surface. In submitting his bid, the plaintiff contemplated using a *151 round fiber duct, which would cost $1500. The plaintiff incorporated the round fiber duct in the list of materials he proposed to use, which was submitted to the architect. The architect disapproved the use of this duct, stating that in its opinion the duct did not meet the specifications, and, in the words of the finding, “would not install an underground duct system.” At a conference between the plaintiff and Edwin Moss on December 25, 1943, it was agreed that the duct which the plaintiff proposed to install met the specifications. A General Electric Company duct met the approval of the architect but would cost the plaintiff substantially more than the duct he proposed to install. He told Moss that he could not proceed with the job if the General Electric duct was required. Moss then directed the plaintiff to install the General Electric duct and said that the defendant would take care of the additional cost due to its purchase and installation and would fight the matter out with Chance Vought. The plaintiff then and thereafter protested against this installation, but, relying on the defendant’s promise, he installed the General Electric duct system. The cost to the plaintiff in buying and installing the General Electric duct with its appliances was $7800 in excess of the expense of installing a round fiber duct.

We consider first the claim of damages due to the change in the order in which the work was to be done. The provision in the contract upon which the plaintiff relies is as follows: “It is the intention of the Owner to complete that part of the Addition first extending from column lines S to J so that this portion of the Addition can be placed in operation before the completion of the entire Addition. It is not the intention to delay the construction of the balance of the structure except to give preference to that portion between column lines S and J.” But the contract also provides: “The Con *152 tractor will continue his operations in present Building. . . . The Subcontractors are to consult with the Architect-Engineer’s Superintendent as to the methods of carrying on work so as not to interfere with Contractor’s operations, as well as to the available space for storage of materials and location of plant, places of access to the work, etc., and all is to be arranged to suit the Contractor’s requirements.” It is clear from these provisions that the first merely stated an “intention” as to the order in which the work was to be done and that the defendant was obligated to accept such a change as should be reasonably necessary to enable Chance Vought to continue its operations in the existing building; and there is no claim that the change made did not meet this requirement. The plaintiff assumed the risk that such a contingency might occur and he cannot now claim extra compensation on that account. McCaffrey v. Groton & Stonington Street Ry. Co., 85 Conn. 584, 587, 84 A. 284; Whitaker v. Cannon Mills Co., 132 Conn. 434, 440, 45 A. 2d 120; Connecticut Co. v. New York, N. H. & H. R. Co., 94 Conn. 13, 46, 107 A. 646.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New England Rock Services, Inc. v. Empire Paving, Inc.
731 A.2d 784 (Connecticut Appellate Court, 1999)
Luke F. Sweeney, Inc. v. L.C. Castlemen, Inc., No. 31 55 94 (Aug. 9, 1996)
1996 Conn. Super. Ct. 5774 (Connecticut Superior Court, 1996)
Fgb Realty Advisors v. Seven Winds Realty, No. Cv 94 0066261 (Dec. 22, 1995)
1995 Conn. Super. Ct. 14486 (Connecticut Superior Court, 1995)
Fgb Realty Advisors, Inc. v. Seven Winds, No. Cv 94 0066260 (Dec. 22, 1995)
1995 Conn. Super. Ct. 14473 (Connecticut Superior Court, 1995)
fifty/unionoreo v. Russell Sirianni Asso., No. Cv94 0356903s (Jun. 7, 1995)
1995 Conn. Super. Ct. 7199 (Connecticut Superior Court, 1995)
M & L Building Corp. v. Housing Authority
646 A.2d 244 (Connecticut Appellate Court, 1994)
John T. Brady & Co. v. City of Stamford
599 A.2d 370 (Supreme Court of Connecticut, 1991)
Thermoglaze, Inc. v. Morningside Gardens Co.
583 A.2d 1331 (Connecticut Appellate Court, 1991)
K.A. Thompson Electric v. Wesco, Inc., No. Cv-89-0700262s (Jan. 3, 1991)
1991 Conn. Super. Ct. 86 (Connecticut Superior Court, 1991)
Skolnick & Sons v. Heyman
508 A.2d 64 (Connecticut Appellate Court, 1986)
Grenier v. Compratt Construction Co.
454 A.2d 1289 (Supreme Court of Connecticut, 1983)
Guilford Yacht Club Ass'n v. Northeast Dredging, Inc.
438 A.2d 478 (Supreme Judicial Court of Maine, 1981)
Brian Construction & Development Co. v. Brighenti
405 A.2d 72 (Supreme Court of Connecticut, 1978)
State National Bank v. Dick
325 A.2d 235 (Supreme Court of Connecticut, 1973)
Charter Oak Estates, Inc. v. Kearney
280 A.2d 885 (Supreme Court of Connecticut, 1971)
Maskel Construction Co. v. Town of Glastonbury
264 A.2d 557 (Supreme Court of Connecticut, 1969)
Jacobson Electric Co. v. Rome Fastener Corporation
238 A.2d 415 (Supreme Court of Connecticut, 1968)
Friend v. Green
151 A.2d 343 (Supreme Court of Connecticut, 1959)
Terminal Const. Corp. v. Bergen, Etc., Authority
112 A.2d 762 (New Jersey Superior Court App Division, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
69 A.2d 562, 136 Conn. 147, 1949 Conn. LEXIS 212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dahl-v-edwin-moss-son-inc-conn-1949.