McCaffrey v. Groton & Stonington Street Railway Co.

84 A. 284, 85 Conn. 584, 1912 Conn. LEXIS 170
CourtSupreme Court of Connecticut
DecidedJuly 19, 1912
StatusPublished
Cited by9 cases

This text of 84 A. 284 (McCaffrey v. Groton & Stonington Street Railway Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCaffrey v. Groton & Stonington Street Railway Co., 84 A. 284, 85 Conn. 584, 1912 Conn. LEXIS 170 (Colo. 1912).

Opinion

Wheeler, J.

This is an action to recover for labor furnished, brought on the common counts, with a bill of particulars specifying the items of labor for which recovery is sought, to which a general denial is pleaded.

The defendant contracted with one Serrato for the overhead construction of the defendant’s railway from Groton to the Rhode Island line in Stonington. Subsequently the plaintiff became a subcontractor of Serrato for a part of this work, agreeing with him to *587 perform “the remainder of the overhead construction work” on said railway “according to the specifications and under the directions of Messrs. Daboll & Crandall,” the engineers for the defendant.

These specifications were a part of the contract between Serrato and the defendant. The defendant accepted an order upon it drawn by Serrato in favor of the plaintiff for the consideration agreed upon by Serrato and the plaintiff for the construction of said “remainder,” and this order recited the making of the subcontract between Serrato and the defendant, and its performance according to the specifications of the contract between Serrato and the defendant and to the satisfaction of the engineers of the defendant.

The court correctly instructed the jury that through .this order the plaintiff entered into direct contract relations with the defendant, and, though a subcontractor to Serrato, he became a principal contractor with the defendant.

This subcontract was intended to embrace the performance of a part of the original contract of the defendant with Serrato. Hence the plaintiff was chargeable with notice of the provisions of that contract, and is bound by such of its provisions as are applicable to the work required under the contract'of the plaintiff and Serrato. Shaw v. First Baptist Church, 44 Minn. 22, 46 N. W. 146; Green & Co. v. Jackson & Co., 66 Ga. 250.

One provision of these specifications was: “Any claim for extra work due to change of location or grade or to any unforeseen cause, will not be allowed unless the same has been agreed upon in writing in form of a supplementary contract signed by the contractor and the engineers, in which the price to be paid the contractor for said extra work is stated.”

The plaintiff was therefore bound to secure payment for extras included within these specifications in the *588 manner therein provided, unless there were present something to take the case out of this limitation.

The defendant complains that the court took the case out of this limitation by instructing the jury, first, that the defendant could not avail itself of the defense that the plaintiff had not proceeded, in securing his claim for extras, in the manner provided by the specifications, because it had not pleaded this as a defense; second, that if the jury found the plaintiff did not proceed in this method, because misled by the defendant, recovery might be had despite such failure.

Neither ground is tenable. If the extras sued for come within this provision of the contract, it was essential that the plaintiff allege and prove compliance with it, since it was a condition of the contract precedent to a recovery.

The basis for the claim that the plaintiff was misled, rested in the fact that he had been one of the bidders for the work which Serrato secured; and in the copy of the specifications handed him by ‘the engineers of the defendant this provision regarding the payment for extra work was omitted, though made a part of the specifications of the contract subsequently made between Serrato and the defendant. The plaintiff had no right to rely upon this copy, procured by him some six months before the defendant made its contract with Serrato. It was his duty to know the terms of the specifications made a part of his contract. His lack of knowledge arose from his own neglect, and not from a breach of duty owed him by the defendant. There was no possible basis on these facts for the claim that the plaintiff had been misled. Further, no such issue was raised by the pleadings.

The court instructed the jury that extra work claimed by the plaintiff was of such a character as to bring it within the extra-work limitation of, the specifications. *589 We cannot coincide with this view. The only claim for extras included within this limitation is that due “to change of location or grade, or any unforeseen cause.” The extras claimed were for work done upon order of the engineers in setting additional and larger poles, and in furnishing certain gains and crossarms. There had been no change in the grade or location of the railway requiring such poles, gains, and crossarms. The only suggested reason for the ordering of these extras was, that because of the grades and curves their use would secure a better railway construction. The existence of these grades and curves was known at the time the contract was executed. “Unforeseen” limits cause, and means that the cause was not foreknown. 39 Cyc. 685. In this sense this extra work was not “unforeseen.” Hills v. Sughrue, 15 Mees. & Weis. 253.

For this reason, rather than for those stated, we think the court was correct in refusing to comply with the several requests of the defendant to charge that the defendant’s responsibility for extra work could not be sustained until the plaintiff had proven his compliance with the method provided for securing payment for extra work, and in instructing the jury in effect that that provision was inapplicable to the circumstances of this case.

The specifications provided for the spacing of the poles over the length of the railway; hence the number of poles required was known. It also provided for the size of the poles. It also provided: “The intent of these specifications is to cover and include all labor and material, except copper conductors, necessary for the proper installation and equipment of the overhead work of the Groton and Stonington Street Railway Company, between the terminals of the road. Any apparatus, or appliances, or labor not specifically mentioned or included that may be found necessary to perfect this work or which pertains to good practice *590 of such construction shall be furnished and installed by this contractor just as if specified herein, and without extra cost to the purchaser.”

The reasonable construction of these somewhat contradictory provisions is that labor which the engineers may require of the contractor, in addition to that specifically mentioned, must be limited to that necessary to procure such reasonable degree of perfection as good practice in the construction provided for by the contract requires, and is not limited to the judgment of the engineers as to what they may think necessary to make the work absolutely perfect.

The court properly confined the recovery to such additional and larger poles and crossarms and gains as were called for beyond those required for securing a reasonable degree of perfection as good practice in such construction requires.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

T. Lippia & Son, Inc. v. Jorson
342 A.2d 910 (Connecticut Superior Court, 1975)
Lippia Son, Inc. v. Jorson
342 A.2d 910 (Connecticut Superior Court, 1975)
Randolph Construction Co. v. Kings East Corporation
334 A.2d 464 (Supreme Court of Connecticut, 1973)
Harrington v. McCarthy
420 P.2d 790 (Idaho Supreme Court, 1966)
State v. Newman
99 A.2d 110 (Supreme Court of Connecticut, 1953)
Dahl v. Edwin Moss & Son, Inc.
69 A.2d 562 (Supreme Court of Connecticut, 1949)
Thames Lumber Co. v. Cruise
164 A. 652 (Supreme Court of Connecticut, 1933)
Firszt v. Kalinowski
144 A. 894 (Supreme Court of Connecticut, 1929)
Ferrigino v. Keasbey
106 A. 445 (Supreme Court of Connecticut, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
84 A. 284, 85 Conn. 584, 1912 Conn. LEXIS 170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccaffrey-v-groton-stonington-street-railway-co-conn-1912.