Harrington v. McCarthy

420 P.2d 790, 91 Idaho 307, 1966 Ida. LEXIS 277
CourtIdaho Supreme Court
DecidedNovember 28, 1966
Docket9831
StatusPublished
Cited by19 cases

This text of 420 P.2d 790 (Harrington v. McCarthy) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harrington v. McCarthy, 420 P.2d 790, 91 Idaho 307, 1966 Ida. LEXIS 277 (Idaho 1966).

Opinion

SPEAR, Justice.

Robert Harrington, respondent herein, initiated proceedings in the district court, Nez Perce County, to foreclose a material-man’s lien for work and materials furnished in the construction of a home in Lewiston for Leslie T. and V. Leone McCarthy, husband and wife, appellants herein, for which payment had not been received. The contract between the parties provided that Harrington would construct the house for $26,000.00 and that where the owners (McCarthy and wife) ordered in writing changes in the work, the contract sum would be adjusted accordingly, but that all claims for extra costs must be made in writing before executing the work involved. The district court found that the specifications and plans for the construction of the house were changed and that the respondent performed work and installed materials in addition to those shown in the original plans and specifications at the special instance and request of the appellants, either directly or by and through their authorized agent (Parr, the architect), for which the respondent was entitled to be reimbursed in the sum of $1,147.55 for the reasonable value of the extra work involved. However appellants contend that no written claim for extra work in the sum demanded by respondent was made in accord with the stipulation entered into by the parties, that such provision was never waived, and therefore recovery for such extra costs as were incurred was, for that reason, precluded.

The provision in the contract material to the litigation between the parties at bar is article 8 of that contract and is as follows:

“Changes in Work: The owner may order changes in the work, the contract sum being adjusted accordingly. All such orders and adjustments shall be in writing. Claims by the contractor for extra costs must be made in writing before executing the work involved.”

Appellants, in the summer of 1963, obtained a mail order set of plans for the proposed construction of a residence in Lewis-ton, Idaho. The plans were discussed with William Parr, the architect retained by appellants. Parr told appellants to go ahead and obtain bids on the plans since the changes he contemplated would be minor. Sometime thereafter, appellants met with Mr. West, a local realtor, and gave him one set of the plans and a list of certain items wanted in the house which were changes from the original plans. This set of plans and the list of alterations Harrington (respondent) received from West for the purpose of submitting a bid for the construction of the McCarthy home.

The plans delivered to respondent and used by him to prepare his bid did not contain a list of materials for use in the home construction. There were, respondent explains, no specifications upon which to bid other than those which appeared in the blueprint and on the list of changes which were delivered with the plans. The plans, for example, specified sliding glass doors, but there was no specification for any particular type. Harrington submitted his bid in the sum of $26,000.00 based solely upon the plans and the list of changes which he had received. He obtained bids from various craftsmen and suppliers for the materials and craft services necessary to construct the house and to that total estimate added a cost factor for labor to reach the $26,000.-00 bid price.

On October 28, 1963, respondent met with appellants at their home to discuss building the new house and to sign a contract. The parties ■ at that time agreed upon certain changes requested by appellants. Pursuant to article 8 of the contract, supra, one of the changes from the plans bid on was written into the contract; the other, however, was not. The parties agreed, and the contract provided, that Parr, appellants’ architect, would supervise the construction.

*309 Construction started on or about December 12, 1963. In accord with the contract agreement of the parties, Parr prepared and revised drawings and supervised the construction. Throughout the major construction of the home respondent was without the plans upon which he submitted his bid. Respondent turned the plans originally in his possession over to the city building inspector for the purpose of obtaining a permit for construction. Harrington testified that when he asked for an additional set of plans from which he could work he was told there were not enough sets of plans available and that he was to use the working drawings prepared by Parr. It is admitted by appellants that respondent constructed the building from the working drawings or plans prepared by Parr and submitted to respondent.

During the initial stages of construction, Harrington periodically received working plans which, pursuant to the instructions of appellants, he followed to build the house. A complete set of working plans were never drawn or delivered to respondent. The working plans contained a number of differences from the plans used by respondent to prepare and submit his bid. Such changes resulted in extra costs for the contractor. Harrington first became aware of the extra cost sometime in January 1964 when he discovered the use of thermo glass required in the architect’s working plans for the windows and sliding doors involved a substantial extra cost not included in his bid. Concerned, respondent contacted appellants’ mortgagee, the J. L. Cooper Company, which was dispersing the construction funds as work progressed. Thereafter a meeting was set up at McCarthy’s office. Those attending that meeting were McCul-lum, a representative of the mortgagee, West and his partner Adams (realtors), McCarthy and Harrington. McCarthy referred Harrington to Parr whom he asserted represented him in this matter, and on that same day Harrington and the others met with the architect. Parr was informed that the cost of windows, doors and several other items were exceeding the cost bid. A disagreement between Parr and Harrington ensued and Harrington was asked to leave. However Parr acknowledged to the others, after respondent had left, that costs were in excess of the cost bid and that some adjustment should be made which he would discuss with McCarthy.

This meeting took place either the latter part of February or early March 1964. Thereafter the contractor never received additional working drawings from the architect, but worked from the plans originally delivered to him and returned from the city inspector. Appellants, subsequently, requested additional changes to enlarge the patio and substitute the use of wallpaper for paint. Harrington had not as yet received compensation for the extra cost of changes previously installed. He therefore demanded that such requests be reduced to writing which was done on or about March 10, 1964. No claim at this time was made regarding additional costs of materials that respondent demanded in his complaint and claim of lien and appellants urge respondent is estopped now to claim such costs.

The house was completed April 1, 1964. The McCarthys started moving their belongings into the new house prior to its completion and finished moving on or about the Sth of April. On May 20, 1964, the attorney representing Harrington wrote a letter to appellants setting out a list of changes and the extra costs for such changes, demanding payment therefor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L & W SUPPLY CORP. v. Chartrand Family Trust
40 P.3d 96 (Idaho Supreme Court, 2002)
Electrical Wholesale Supply Co. v. Nielson
41 P.3d 242 (Idaho Supreme Court, 2001)
Rule Sales & Service, Inc. v. U.S. Bank National Ass'n
991 P.2d 857 (Idaho Court of Appeals, 1999)
Jones v. Micron Technology, Inc.
923 P.2d 486 (Idaho Court of Appeals, 1996)
Bouten Construction Co. v. M & L Land Co.
877 P.2d 928 (Idaho Court of Appeals, 1994)
Huang International, Inc. v. Foose Construction Co.
734 P.2d 975 (Wyoming Supreme Court, 1987)
Hogan v. Postin
695 P.2d 1042 (Wyoming Supreme Court, 1985)
Cutler v. Geissler
691 P.2d 1252 (Idaho Court of Appeals, 1984)
Breeden v. Edmenson
689 P.2d 211 (Idaho Court of Appeals, 1984)
Acoustic Specialties, Inc. v. Wright
651 P.2d 529 (Idaho Supreme Court, 1982)
State ex rel. Kidwell v. U. S. Marketing, Inc.
631 P.2d 622 (Idaho Supreme Court, 1981)
State Ex Rel. Kidwell v. US Marketing, Inc.
631 P.2d 622 (Idaho Supreme Court, 1981)
Reynolds v. Farber
577 P.2d 318 (Colorado Court of Appeals, 1978)
Obray v. Mitchell
567 P.2d 1284 (Idaho Supreme Court, 1977)
Coldiron v. Gaster
278 A.2d 328 (Superior Court of Delaware, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
420 P.2d 790, 91 Idaho 307, 1966 Ida. LEXIS 277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harrington-v-mccarthy-idaho-1966.