Huang International, Inc. v. Foose Construction Co.

734 P.2d 975, 1987 Wyo. LEXIS 415
CourtWyoming Supreme Court
DecidedMarch 27, 1987
Docket86-247
StatusPublished
Cited by8 cases

This text of 734 P.2d 975 (Huang International, Inc. v. Foose Construction Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huang International, Inc. v. Foose Construction Co., 734 P.2d 975, 1987 Wyo. LEXIS 415 (Wyo. 1987).

Opinion

MACY, Justice.

Foose Construction Company and Western Sheet Metal and Roofing Company, Inc. brought an action against Huang International, Inc., Huang-Lo Enterprises, Inc., and United Savings Bank of Wyoming. In their complaint against Huang, Foose and Western Sheet Metal alleged breach of contract and demanded payment of the amounts due under the contract or authorization to foreclose their liens on Huang’s property in execution of the judgment. They also requested an order adjudging their liens to have priority over mortgages on the property held by the bank.

Prior to trial, Western Sheet Metal settled its claim against Huang. A trial to the district court was held on Foose’s claims, and judgment was entered against Huang in the amount of $31,074.75. The judgment authorized Foose to foreclose upon its lien if necessary in execution of the judgment. The judgment also recited that Foose’s lien had priority over the bank’s construction money mortgage but not over the bank’s purchase money mortgage. Huang now appeals to this Court from the district court’s judgment.

We affirm.

Huang makes the following claims before this Court:

“1. Whether the Trial Court [erred] in granting attorneys fees to Plaintiff;
“2. Whether the Trial Court [erred] in finding that extra items in construction were outside the scope of the contract *976 and not required to be in writing as provided by the contract;
“3. Whether the Trial Court [erred] in finding that the Defendant agreed to pay for extra items either by words or conduct, which was contrary to the contract’s requirement that extras are to be in writing; and
“4. Whether the Trial Court [erred] in finding that some extras furnished by contract were not a voluntary act when the extras were covered by the terms of the contract.”
Foose restates the issues as follows:
“1. WHETHER THE COURT ERRED IN FINDING $7,132 AS COMPENSATION FOR EXTRA WORK OUTSIDE THE SCOPE OF THE ORIGINAL CONTRACT?
“2. WHETHER THE COURT ERRED IN ITS AWARD OF ATTORNEY FEES TO FOOSE CONSTRUCTION?”

On August 20, 1984, Huang entered into a written agreement with Foose for the construction of a Chinese restaurant in Cheyenne, Wyoming. Thereafter, on August 30, 1984, the parties entered into a second written agreement (Rider “A”) which was incorporated by reference into the original agreement. The agreements provided that Foose would reconstruct the outside of an existing building in accordance with drawings and specifications prepared for Huang by Richard Porter, a Cheyenne architectural designer. The agreements also provided that the outside work would be completed in 1984 to enable interior construction to be completed during the winter months. Under the terms of the agreements, the cost of the work was not to exceed $200,000; in the event it did exceed that amount, 50% of the excess cost was to be deducted from Foose’s fee.

Construction began in August 1984. By November, the cost of construction had exceeded $200,000. In an effort to complete construction by the first of the year, Huang and Foose entered into a third written agreement which provided that Foose would perform additional work at a cost of $47,000. Thereafter, Foose completed the work specified in the third agreement in addition to work not covered by any of the written agreements. When Foose sought payment for the work completed, Huang refused to pay the total amount, claiming that Foose had performed work beyond the scope of the written agreements. Efforts to settle the dispute failed, and Foose brought suit against Huang on June 14, 1985.

In its complaint, Foose alleged that all of the work was performed pursuant to either written or oral agreements with Huang. In response, Huang filed an answer and counterclaim alleging that Foose did not complete the contract, performed the work in an unsatisfactory manner, and charged Huang for work not required by the written agreements. Foose answered and raised the affirmative defense that Huang waived the terms of the written agreements by its own conduct.

At trial, Foose introduced evidence of 50 “extras” allegedly performed pursuant to oral agreements entered into with Huang after performance of the written agreements. Upon considering all of the evidence and testimony presented, the district court found that Foose proved by clear and convincing evidence that Huang approved extras valued at $7,171. In its decision letter, the court stated that Foose

“was entitled to the sum of $200,000.00 on the original contract, the further sum of $44,500.00 on the supplemental contract, and the additional sum of $7,171.00 for extras as specifically found above. [Foose] therefore is entitled to a total of $251,671.00. [Foose] acknowledges having received payments totaling $231,-389.00 which leaves a balance still due from [Huang] to [Foose] of $20,282.00. [Foose] further has agreed to give credit to [Huang] for the sum of $425.00 for a desk converted by [Foose] and belonging to [Huang]. This leaves the net recovery due to [Foose] from [Huang] of $19,-857.00.”

The court also awarded attorney’s fees to Foose in the amount of $11,217.75.

I

As indicated above, on appeal to this Court Huang sets forth three claims with *977 respect to the district court’s award for extra work performed by Foose beyond the scope of the parties’ written agreements. Because each of the claims in essence questions whether the district court correctly found Huang liable for the cost of that work, we will address the claims together.

The original agreement executed by Huang and Foose contained the following provisions:

“If the final working drawings and specifications have not been completed, the Contractor, the Architect/Engineer and Owner will work closely together to monitor the design so as to assure the project can be constructed within the Guaranteed Maximum Price and in accordance with the exhibits attached hereto. As these final plans and specifications are being completed, the Contractor will keep the Owner apprised of any changes in the Guaranteed Maximum Price caused by changes in the scope of the project which the Owner may request. * * * * * *
“5.2 The Owner shall designate a person who shall be fully acquainted with the scope of the Work, and has authority to approve changes in the scope of the Work, render decisions promptly, and furnish information expeditiously.
* * * * * #
“9.1 The Owner may make Changes in the Work in accordance with the General Conditions insofar as they are consistent with this Agreement. The Contractor shall be reimbursed for Changes in the Work on the basis of Cost of the Work as defined in Article 10 of this Agreement. “9.2 If changes in the Work are authorized in writing by the Owner, their estimated value shall be added to or deducted from the Guaranteed Maximum Price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KM Upstream, LLC v. Elkhorn Construction, Inc.
2012 WY 79 (Wyoming Supreme Court, 2012)
Wolin v. Walker
830 P.2d 429 (Wyoming Supreme Court, 1992)
Ferguson v. Reed
822 P.2d 1287 (Wyoming Supreme Court, 1991)
Eastline Corp. v. Marion Apartments, Ltd.
524 So. 2d 582 (Mississippi Supreme Court, 1988)
Shauers v. Board of County Com'rs of Sweetwater County
746 P.2d 444 (Wyoming Supreme Court, 1987)
Harmon v. Town of Afton
745 P.2d 889 (Wyoming Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
734 P.2d 975, 1987 Wyo. LEXIS 415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huang-international-inc-v-foose-construction-co-wyo-1987.