Smith v. Washburn-Wilson Seed Co.

34 P.2d 969, 54 Idaho 659, 1934 Ida. LEXIS 58
CourtIdaho Supreme Court
DecidedJuly 12, 1934
DocketNo. 6138.
StatusPublished
Cited by12 cases

This text of 34 P.2d 969 (Smith v. Washburn-Wilson Seed Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Washburn-Wilson Seed Co., 34 P.2d 969, 54 Idaho 659, 1934 Ida. LEXIS 58 (Idaho 1934).

Opinion

WERNETTE, J.

This is an action for damages for breach' of contract. On January 13, 1933, respondent, Charles M. Smith, and appellant, Washburn-Wilson Seed Company, entered into a written contract for the growing of peas. Appellant was to furnish seed of the Alaska variety to respondent for the planting of 140 acres of land. The respondent, on his part, was to plant the peas, cultivate, care for, and harvest the crop raised with such seed in a good farmerlike manner, and deliver the peas so raised to the appellant company which was to pay him 1%$ per pound for all peas raised, less the amount furnished respondent for seed. The contract contained the following provision: ‘ ‘ Subject to approval as to land and condition, by Mr. Kennard.” Mr. Kennard was the vice-president of appellant company, *661 in charge of production. Some time between the first and fifteenth of April, 1933, respondent interviewed Kennard with reference to the delivery of the seed. In such conversation Kennard told respondent that appellant would not furnish the Alaska variety because of the lateness of the season, the ground not having been prepared for seeding, and because respondent with his equipment would be unable to get the Alaska variety seeded in time. At the same time Mr. Kennard informed respondent that appellant company would furnish him with a variety of peas known as White Canadas, which was a much later variety. It appears that the appellant company had had wide experience in the planting and growing of peas, and recommended that the White Canada variety be planted fifty pounds to the acre. After some protest by respondent he finally agreed to plant the White Canada variety, and appellant company furnished him with sufficient seed to plant 140 acres at fifty pounds to the acre, but with the equipment respondent had he was unable to sow the peas lighter than sixty-eight pounds to the acre. This left a balance of twenty acres unseeded to peas. The respondent then requested appellant to furnish him with seed for the other twenty acres, but was informed that appellant had no more seed available. Respondent then planted fourteen of the remaining twenty acres in oats.

Respondent instituted this action on the ground that the White Canada variety of peas did not yield as heavily as would the said Alaska variety which appellant company had contracted to furnish, and respondent did not make as much profit from the oats sowed on the fourteen-acre patch as he would have made if appellant company had furnished the Alaska pea seed to sow the remaining twenty acres to be sown; that by virtue of appellant company’s failure and refusal to supply sufficient pea seed of the Alaska variety for respondent to' properly seed the 140 acres, respondent was damaged in the sum of $1,708.

Appellant filed a general demurrer to the complaint, which was overruled. Appellant answered, and in due time the case was tried to a jury. At the close of respondent’s testi *662 mony the appellant moved for a nonsuit. This motion was denied, and the appellant rested, then renewed the motion for nonsuit, which was denied. The jury returned a verdict in favor of respondent for the sum of $676, from which judgment this appeal is taken.

Error is predicated upon two grounds: 1. That the court erred in overruling appellant’s demurrer, on the ground that the complaint shows on its face that the contract sued on was subject to approval by an officer of the appellant company, to wit, Mr. Kennard, and shows that Kennard refused to approve said writing; upon the further ground that the complaint shows on its face that respondent consented to accept and plant and did accept and plant ■ White Canada peas in lieu of Alaskas. 2. That the court erred in overruling appellant’s motion for nonsuit, on the grounds that the evidence shows that the contract was not approved, and that the evidence further shows that the contract to furnish Alaska seed peas was superseded and set aside by subsequent agreement of the parties to substitute White Canada peas in lieu of Alaskas. ■

The disposition of this case rests upon the determination of but one question: Was there such a modification of the original contract, by the mutual consent of the parties, that the respondent is precluded from suing on such contract as originally made?

It is a general rule of law that parties to an unperformed contract may, by mutual consent, modify it by altering, excising, or adding provisions. (13 C. J. 589.) And such modification may be by parol agreement though the contract is in writing. (American Eagle Fire Ins. Co. v. McKinnon, 36 Ariz. 409, 286 Pac. 183; Arkansas Valley Bank v. Esser, 75 Colo. 110, 224 Pac. 227; Propst v. William Hanley Co., 94 Or. 397, 185 Pac. 766; Parker v. Weber County Irr. Dist., 65 Utah, 354, 236 Pac. 1105.) In some states, however, by statute, a written agreement may be modified by oral agreement only when the oral agreement has been executed. (Klein Norton Co. v. Cohen, 107 Cal. App. 325, 290 Pac. 613; Lish v. Martin, 55 Mont. 582, 179 *663 Pac. 826; Walker v. Johnson, 102 Okl. 9, 227 Pac. 113.) We have no statute which prevents parties to a written contract from modifying the same by subsequent oral agreement.

The pleadings and evidence in this case show that the appellant company, through its agent, Mr. Kennard, informed the respondent that it would not perform the provision of the original contract for the furnishing of the Alaska seed peas. At the same time appellant offered to furnish respondent with White Canada peas. After considerable protest the respondent voluntarily accepted the offer to take the White Canada peas as a substitute for the Alaska seed peas, but did not at such time expressly reserve to himself the right to claim damages for failure to furnish Alaska peas under the original contract. Respondent then took delivery of the substitute seed, planted, harvested and delivered it to appellant company, and we must assume under the record, for it is not shown otherwise, that respondent harvested, delivered and received payment for the peas so raised by the White Canada seed, in exactly the same manner as was provided in the original contract between the parties. We believe that under the pleadings and the evidence it is conclusively shown by the acts of the respondent in accepting the substitute seed as he did, he consented to a modification of the contract as suggested by appellant. The rule of law governing in a case of this kind is stated in 13 C. J., sec. 606, p. 591, as follows:

“One party to a contract cannot alter its terms without the assent of the other; the minds of the parties must meet as to the proposed modification; .... The fact of agreement may be implied from a course of conduct in accordance with its existence. So assent may be implied from the acts of one party in accordance with the terms of a change proposed by the other. ’ ’

In Snowball v. Maney Bros. & Co., 39 Wyo. 84, 270 Pac. 167, 271 Pac. 875, 61 A. L. R. 199, plaintiff and defendant had entered into a contract by which plaintiff was to build a certain portion of a public highway. After completion of *664

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Allied Stores Corp.
679 P.2d 640 (Idaho Supreme Court, 1984)
Loomis, Inc. v. Cudahy
656 P.2d 1359 (Idaho Supreme Court, 1982)
Olson v. Quality-Pak Company
469 P.2d 45 (Idaho Supreme Court, 1970)
Harrington v. McCarthy
420 P.2d 790 (Idaho Supreme Court, 1966)
Belts v. State ex rel. Department of Highways
388 P.2d 982 (Idaho Supreme Court, 1964)
Ore-Ida Potato Products, Inc. v. Larsen
362 P.2d 384 (Idaho Supreme Court, 1961)
T. R. Miller Mill Company v. Johns
75 So. 2d 670 (Alabama Court of Appeals, 1954)
Merrill-Stevens Dry Dock & Repair Co. v. United States
96 F. Supp. 464 (Court of Claims, 1951)
Inland Empire Refineries, Inc. v. Jones
206 P.2d 519 (Idaho Supreme Court, 1949)
Ida. G. D. Crp. v. B. P. Lbr. Co.
115 P.2d 401 (Idaho Supreme Court, 1941)
Idaho Gold Dredging Corp. v. Boise Payette Lumber Co.
115 P.2d 401 (Idaho Supreme Court, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
34 P.2d 969, 54 Idaho 659, 1934 Ida. LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-washburn-wilson-seed-co-idaho-1934.