McCarthy Corporation v. Stark Investment Group

CourtIdaho Supreme Court
DecidedJune 24, 2021
Docket47749
StatusPublished

This text of McCarthy Corporation v. Stark Investment Group (McCarthy Corporation v. Stark Investment Group) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCarthy Corporation v. Stark Investment Group, (Idaho 2021).

Opinion

IN THE SUPREME COURT OF THE STATE OF IDAHO

Docket No. 47749

MCCARTHY CORPORATION, an Idaho ) corporation, ) ) Boise, May 2021 Term Plaintiff-Counterdefendant- ) Appellant, ) Opinion filed: June 24, 2021 ) v. ) Melanie Gagnepain, Clerk ) STARK INVESTMENT GROUP, LLC, an ) Idaho limited liability company; CRAIG ) STARK, a married man; ) ) Defendants-Counterclaimants- ) Respondents, ) ) and ) ) U.S. BANK, N.A., a national association, ) ) Defendant-Respondent. )

Appeal from the District Court of the First Judicial District of the State of Idaho, Kootenai County. Richard S. Christensen, District Judge.

The judgment of the district court is affirmed.

Lukins & Annis, PS, Coeur d’Alene, for Appellant.

Ramsden, Marfice, Ealy & De Smet, LLP, Coeur d’Alene, for Respondents.

_______________________________________________

MOELLER, Justice.

Craig Stark entered into a contract with McCarthy Corporation to construct a storage facility for recreational vehicles and boats. The relationship began amicably but quickly turned sour after McCarthy sent Stark an invoice for work Stark believed he had already paid for in full. After the parties were unable to resolve their dispute, Stark terminated McCarthy’s contract. McCarthy then filed a lien against Stark’s property and brought suit for breach of contract and to

1 foreclose its lien. Stark, Stark Investment Group, and U.S. Bank, Stark’s construction lender on the project, counterclaimed for breach of contract, breach of the implied covenant of good faith and fair dealing, fraudulent misrepresentation, slander of title by the recording of an unjust lien, and breach of the Idaho Consumer Protection Act (“ICPA”). After a lengthy bench trial, the district court largely agreed with Stark’s counterclaims and dismissed McCarthy’s complaint. On the counterclaims, the district court found: (1) McCarthy breached the contract; (2) McCarthy breached the implied covenant of good faith and fair dealing through its erroneous billing practices, by not negotiating the billing dispute in good faith, and by improperly requesting payment upfront for services; and, (3) McCarthy violated the ICPA by engaging in misleading, false, or deceptive practices. The district court awarded damages to Stark under the breach of contract counterclaim and the ICPA violation. It also awarded Stark his reasonable attorney fees. McCarthy appealed the district court’s findings, damages award, and attorney fees award. I. FACTUAL AND PROCEDURAL BACKGROUND Factual Background Craig Stark (“Stark”) was employed at a nuclear power plant in Texas. As he neared retirement in the summer of 2017, Stark decided to retire to Idaho. Stark had some experience in real estate development, having built six homes, a storage facility in Iowa, and a Recreational Vehicle (RV) park in Texas. In March of 2017, Stark purchased approximately twenty-five acres in Kootenai County, Idaho. Stark planned to construct an RV and boat storage facility (hereinafter “the Project”) to provide him with retirement income. Before Stark purchased the property, he met with a civil engineer, Scott McArthur, from h2 Surveying and Engineering (“h2”). Stark employed McArthur and h2 to survey the property, prepare a site disturbance plan, assist with obtaining a conditional use permit (CUP), and prepare the Project’s plans and specifications. Stark also contracted with McCarthy Corporation (“McCarthy”)—a registered Idaho contractor relatively new to the excavating business—for the site preparation. McArthur introduced Stark to Jason Cheyne, a project manager and heavy equipment operator for McCarthy. Cheyne became McCarthy’s project manager on the Project. Stark acted as his own general contractor. This created challenges because Stark resided in Texas until August of 2017. As a result of the logistical challenges, Stark asked McArthur to monitor the Project in his absence. This request resulted in dual responsibilities for McArthur

2 because he was already acting as the quantities engineer with h2 so that McCarthy could prepare invoices for payment. Yet, at the same time, McArthur became Stark’s eyes, ears, and sometimes voice on the Project. The Project was divided into two “phases.” Phase 1 consisted of preparing the land to construct four buildings, an office, fencing, and parking. Phase 2 consisted of constructing five additional storage facilities. The contract between Stark and McCarthy contained a typical “change order” provision, which required any significant changes in the plans to be approved in writing in advance by Stark: Change Orders. Contractor agrees to verbal change orders provided the amount does not exceed $1000 in value; the change order amount is emailed to the Owner; and the Owner accepts the change Order amount by email or writing. The parties agree that any change order exceeding $1000 in value shall be signed by Owner and delivered to Contractor.

Prior to entering into the contract, Cheyne dug four test holes on the property for McArthur to analyze and determine whether there was sufficient quantity and quality of earthen materials on-site to be used for the Project’s site preparation. The test holes would also be used to calculate an engineer’s estimated quantities of stripped waste and other materials necessary to complete Phase 1 of the Project. Cheyne and McCarthy would also use these calculations to prepare McCarthy’s bid on the Project. McCarthy’s bid on the entire Project entailed 35 individual bid items totaling $413,551.54. Much of the conflict in this case revolves around three specific bid items, enumerated as items 3, 14, and 19:

Bid Item # Bid Item Description Estimated Units Unit Price Total Item Price 3 Stripped Waste Material 18,878 cubic $2.50 $47,195.69 yds. 4 Import/Suitable/Structural Material (compacted in 15,602 cubic $4.03 $62,877.67 place) yds. 19 4” compacted base rock – ¾” crushed/angular rock 2,867 tons $17.70 $50,571.50 (placed and compacted)

3 The Project plans called for McCarthy to first strip the waste material from the property (Bid item 3), then replace it with fill material (Bid item 4), and finally, cover part of the area with 4 inches of compacted base rock and 3/4 inches of crushed angular rock (Bid item 19). Regarding Bid item 4, it was anticipated that this would be accomplished by McCarthy taking material from an on-site borrow pit to raise the building pad elevations to satisfy the CUP requirements. Bid item 19 was intended to serve as the subbase layer for the asphalt. The first step of the site preparation called for removing the trees on the property. McCarthy subcontracted with Mendenhall Logging to complete this work, which was completed by the beginning of April 2017. The next step entailed stripping the future building sites of vegetation and topsoil and excavating an on-site borrow pit. The on-site borrow pit would be used to mine materials that would, in turn, be used on the property to raise the building and parking area elevations to meet the CUP requirements. Cheyne subcontracted this work to a Montana excavating company, Basin Industrial Services, Inc., (“Basin”). Basin was not licensed in Idaho. On May 18, 2017, McCarthy sent Stark Invoice No. 2435 for the work performed on Bid items 3 and 4. The invoice totaled $112,725.77, which closely resembled the original bid amounts. Stark paid it in full on May 22, 2017. During excavation of the on-site borrow pit, Cheyne and Basin came to the conclusion that there would not be enough fill material generated from the on-site borrow pit to adequately raise the elevations of the building sites and parking areas consistent with the CUP.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Borah v. McCandless
205 P.3d 1209 (Idaho Supreme Court, 2009)
Mosell Equities, LLC v. Berryhill & Co.
297 P.3d 232 (Idaho Supreme Court, 2013)
Pierson v. Sewell
539 P.2d 590 (Idaho Supreme Court, 1975)
Obray v. Mitchell
567 P.2d 1284 (Idaho Supreme Court, 1977)
Hackett v. Streeter
706 P.2d 1372 (Idaho Court of Appeals, 1985)
Harrington v. McCarthy
420 P.2d 790 (Idaho Supreme Court, 1966)
Jones v. Micron Technology, Inc.
923 P.2d 486 (Idaho Court of Appeals, 1996)
BMC West Corp. v. Horkley
174 P.3d 399 (Idaho Supreme Court, 2007)
Electrical Wholesale Supply Co. v. Nielson
41 P.3d 242 (Idaho Supreme Court, 2001)
Benninger v. Derifield
129 P.3d 1235 (Idaho Supreme Court, 2006)
ACI Northwest, Inc. v. Monument Heights, LLC
342 P.3d 618 (Idaho Supreme Court, 2015)
Mary Pandrea v. Kenneth Barrett
369 P.3d 943 (Idaho Supreme Court, 2016)
Ballard v. Kerr, M.D, Silk Touch Laser
378 P.3d 464 (Idaho Supreme Court, 2016)
Taylor v. Riley
403 P.3d 636 (Idaho Supreme Court, 2017)
Lunneborg v. My Fun Life, Corp.
421 P.3d 187 (Idaho Supreme Court, 2018)
Nye v. Katsilometes
447 P.3d 903 (Idaho Supreme Court, 2019)
Alsco v. Fatty's Bar
461 P.3d 798 (Idaho Supreme Court, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
McCarthy Corporation v. Stark Investment Group, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccarthy-corporation-v-stark-investment-group-idaho-2021.