Sitkin v. Smith

276 P. 521, 35 Ariz. 226, 66 A.L.R. 645, 1929 Ariz. LEXIS 139
CourtArizona Supreme Court
DecidedApril 23, 1929
DocketCivil No. 2795.
StatusPublished
Cited by10 cases

This text of 276 P. 521 (Sitkin v. Smith) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sitkin v. Smith, 276 P. 521, 35 Ariz. 226, 66 A.L.R. 645, 1929 Ariz. LEXIS 139 (Ark. 1929).

Opinion

ROSS, J.

This action grows out of a building contract, dated October 19th, 1926, in which Sam A. Smith as contractor agreed to furnish all material and provide all work according to specifications and drawings, and to complete within ninety days from date of contract, under the direction and to the satisfaction of her architect, a brick residence for Frances *228 B. Sitkin, on lot 4, block 19, Story addition to the city of Phoenix, for $6,300. November 2d, 1927, Frances B. Sitkin, joined by her husband, Frank L. Sitkin, brought this action against Smith and his surety, the Employers’ Liability Assurance Corporation, Limited, alleging that they had paid to the defendant Smith $1,600 cash, to mechanic lienholders who had filed on residence for labor and material, $5,523.04, and the sum of $61.40 costs, also, at defendants’ request, $50.17 for hardware, or a total of $7,236.61; that while they took possession on April 2d, .1927, the building was not completed then or at all; that because of defective workmanship in the plastering of the living and dining room, it was necessary to repaint them at a cost of' $135; that other undone work (enumerated) cost plaintiffs $112.50; that omitted work (enumerated) cost $164.50. Allowances for difference between the material used and that specified, and for labor, are claimed in the sum of $451.08, and damages for delay in completing building $150.

The prayer of the complaint was for judgment for the difference between the total of the above items, $8,249.69, and the contract price of $6,300, or $1,949.69.

The defendant Smith answered admitting the contract price was $6,300; that plaintiff had paid him and others for his account $7,060.50; but he alleges that under the directions of the plaintiffs he made changes and alterations in said building at an additional cost in labor and material (itemizing such costs) of $1,375.13, and asked for judgment on his counterclaim in the sum of $614.63.

The Employers’ Liability Assurance Corporation, Limited, demurred and pleaded the general issue. Smith obtained a verdict against plaintiffs for $551.30 on his counterclaim, upon which judgment was entered. A separate judgment was entered in favor of the Employers’ Liability Assurance Corporation, *229 Limited, for its costs. No appeal was perfected from the latter judgment, and we will not consider points raised or suggested as to the surety’s liability under its bond.

No questions are involved as to the sufficiency of the pleadings. The plaintiffs do-insist, however, that error was committed in permitting the defendant to introduce oral evidence of changes and alterations in the drawings and specifications, in the absence of a showing that such changes and alterations were ordered in writing by the architect or ordered and agreed to in writing by the owner before made. It is claimed that such evidence varied the terms of the written agreement as expressed in the contract and the drawings and specifications attached thereto. Article III of the building contract, so far as it directly affects the question, reads:

“No alterations shall be made in the work shown or described by the drawings and specifications except upon a written order of the Architects, and when so made, the value of the work added or omitted shall be computed by the Architects, and the amount so ascertained shall be added to or deducted from the contract price. ’ ’

In the specifications among the general conditions is this one:

“The contractor shall not vary from the drawings and specifications. Should the owner at any time during the progress of the work request any alterations, or additions to or deviations or omissions from the work included in the specifications, such request shall be acceded to by the contractor and the same shall in no way affect or make void the contract. No such alterations, additions, deviations or omissions which affect the price or the time for completion as agreed upon shall be done, however, without a written order from the owner.”

Provisions like the above in building contracts are very common. They are binding upon the parties, *230 neither of whom may show by parol testimony that the agreement, at the time of its execution or before, was otherwise than as therein expressed. But that does not prevent the parties from subsequently making another and different agreement, or from orally altering, changing or modifying the written contract when they mutually agree thereon.

As is said of a building contract in O’Loughlin v. Poli, 82 Conn. 427, 74 Atl. 763:

“No principle of law is more firmly established than that, whenever parties enter into an agreement and reduce it to writing, the writing must be held to merge the preceding negotiations, and be taken as the exclusive evidence of their final understanding, so that evidence of verbal propositions or agreements anterior to or contemporaneous with its execution will not be received to modify or vary its terms. Galpin v. Atwater, 29 Conn. 93, 97; Hildreth v. Hartford, M. & R. Tramway Co., 73 Conn. 631, 635, 48 Atl. 963. But the parties to a written contract of the character of the one under review are as free to alter it after it has been made as they were to make it and all attempts on their part by its terms to tie up their freedom of dealing with each other will be futile. West Haven Water Co. v. Redfield, 58 Conn. 39, 41, 18 Atl. 978; Bartlett v. Stanchfield, 148 Mass. 394, 395, 2 L. R. A. 625, 19 N. E. 549. To this end parol agreements will be as effective as written ones. West Haven Water Co. v. Redfield, supra. And implied agreements satisfactorily established will have all the force of express ones. Bartlett v. Stanchfield, 148 Mass. 394, 2 L. R. A. 625, 19 N. E. 549; Clark’s Architect, Owner and Builder, 279.”

Plaintiff Prank L. Sitkin admitted while testifying that defendant Smith made several of the changes and alterations in question upon his oral order and request during the construction of the building. Under the terms of the contract, if plaintiffs intended to rely upon it as written they should have made their request or order for changes in writing, but, having *231 themselves disregarded the contract in that respect and secured the acquiescence therein of the contractor, they certainly consented to waive that condition. Evidence of subsequent agreements as to changes and alterations did not vary the terms of the written contract, but proved a modification thereof by mutual consent. The only objection to this kind of testimony was made upon the cross-examination of plaintiff Frank L. Sitkin. Defendant’s evidence concerning the alterations and changes admitted by plaintiffs to have been made at their request, and to other changes and alterations, went in without any objection whatever.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Truhe v. Turnac Group, L.L.C.
1999 SD 118 (South Dakota Supreme Court, 1999)
Pioneer Roofing Co. v. Mardian Construction Co.
733 P.2d 652 (Court of Appeals of Arizona, 1986)
Eng v. Stein
599 P.2d 796 (Arizona Supreme Court, 1979)
O'Malley Investment and Realty Co. v. Trimble
422 P.2d 740 (Court of Appeals of Arizona, 1967)
Harrington v. McCarthy
420 P.2d 790 (Idaho Supreme Court, 1966)
Peterson v. First National Bank
417 P.2d 728 (Court of Appeals of Arizona, 1966)
In Re Estate of MacDonald
417 P.2d 728 (Court of Appeals of Arizona, 1966)
Freeman v. Stanbern Construction Co.
106 A.2d 50 (Court of Appeals of Maryland, 1954)
Gallaway v. Smith
220 P.2d 857 (Arizona Supreme Court, 1950)