O'Loughlin v. Poli

74 A. 763, 82 Conn. 427, 1909 Conn. LEXIS 71
CourtSupreme Court of Connecticut
DecidedDecember 17, 1909
StatusPublished
Cited by26 cases

This text of 74 A. 763 (O'Loughlin v. Poli) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Loughlin v. Poli, 74 A. 763, 82 Conn. 427, 1909 Conn. LEXIS 71 (Colo. 1909).

Opinion

Prentice, J.

The complaint contains two counts. The first sets out the execution by the plaintiff, a building contractor, and the defendant, a property-owner, of a written *429 contract, whereby the former agreed to construct for the latter a theater building in New Haven, according to plans and specifications made a part of the contract, for the consideration of $81,000. It alleges the plaintiff’s performance, and that $16,700 of the contract price is overdue and unpaid. The second was for the recovery of the reasonable value of extra work. ■ Judgment was rendered for the plaintiff upon each count. No question is presented as to the action of the court upon the second. Under the first count the court permitted recovery for $13,391.93 with interest, as the unpaid portion of the reasonable value of the building to the defendant. This amount was arrived at in the manner hereinafter indicated. Two quite independent questions are thus suggested: first, whether or not, upon the facts found, the plaintiff was entitled to a recovery of said sum; and second, if he was, whether that recovery could be had under the first count as framed.

Upon the trial no objection was made to any of the plaintiff’s evidence upon the ground of variance; no claim was presented by the defendant that the pleadings were insufficient for the plaintiff’s recovery thereon of whatever the facts in evidence disclosed him to be entitled to recover; and the brief of defendant’s counsel before us expressly states that it is conceded for the purpose of the case "that the plaintiff may recover on the doctrine of substantial performance, and that he is entitled to recover ‘the reasonable value of the work and materials so furnished, estimated with reference to the contract price, and to the resulting benefit to the defendant,’ in accordance with the law as laid down in Jones & Hotchkiss Co. v. Davenport, 74 Conn. 418, 420,” 50 Atl. 1028. The concession thus stated is more fully elaborated in the brief, so that it clearly appears that all pleading questions involved are waived, provided the plaintiff’s recovery is based, not upon a quantum meruit, but upon a contract, and the amount thereof is estimated with reference to the contract *430 price. We are thus at liberty to pursue the broader inquiry as to the correctness of the court’s action within the range thus permitted.

The defendant objects to the court’s award, (1) because the plaintiff was allowed too great a sum for his performance, by reason of the adoption of an erroneous rule for its determination; (2) because a credit for a payment on account was refused; and (3) because judgment was rendered against the defendant upon his counterclaim for delay in the completion of the building.

In arriving at the amount for which recovery was had under the first count, the court, after having found the balance of the original contract price which remained unpaid, and that it would cqst $89 to conform the work to the specifications in three minor details, deducted the latter sum from such balance, and rendered judgment for the amount thus determined. The propriety of the court’s action in respect to these three minor deficiencies is conceded. It is urged that further deductions, amounting to $5,000, should have been made, and that in not making them the court ignored that factor in the rule formulated in Jones & Hotchkiss Co. v. Davenport, 74 Conn. 418, 420, 50 Atl. 1028, which requires that the reasonable value of the work and material furnished should be estimated with reference to the contract price, as well as to the resulting benefit to the defendant.

The situation out of which this claim arises is, briefly, as follows: At the time the contract was executed, the defendant agreed with the plaintiff on certain modifications and alterations in the plans and specifications which had been prepared by the defendant’s architect and were embodied by reference in the contract. This agreement was made, as the plaintiff testified, in consideration of the plaintiff’s reduction of his bid from $86,000 to $81,000 and his assumption of the contract at that figure. Subsequently the modifications and changes which were the subject of *431 this oral agreement were reaffirmed by the defendant, and carried out by the plaintiff upon the orders and with the approval and consent of both the defendant and his architect. At the time the written contract was executed and the oral agreement made, it was understood and agreed between the defendant and his architect on the one hand, and the plaintiff on the other, that these modifications and alterations were left to be worked out during the performance of the work. As the work progressed details and drawings were made and furnished to the plaintiff by the architect for some of the modifications air., alterations thus agreed upon. All the others were ordered by the architect and the defendant. One of the modifications consisted of the substitution, for what is known as a Gustavino arch in the foyer, of other construction, which resulted in a saving of $3,000 to the plaintiff. Other modifications thus made resulted in a saving of $2,000. None of these changes were made upon the written order of either owner or architect. The contract provided that no alterations should be made in the work except upon written order of the architect or owner, the amount to be paid by the owner, or allowed by the contractor, by virtue of such alterations, to be stated in the order. The court finds that this provision in the contract was waived by the defendant. It also finds that there was no evidence to show that the building as constructed was of less value to the defendant by reason of any of the departures from the original plans and specifications which were within the terms of the oral agreement:

The evidence offered to establish the parol agreement was objected to by the defendant, upon the ground that its purpose and effect was to vary the written contract. The court ruled that the testimony was inadmissible for such a purpose, but admitted it as bearing upon what it was claimed subsequently took place between the parties with reference to its subject-matter. The questions in *432 volved in this ruling, and in the action of the court in declining to reduce the amount of the plaintiff’s recovery by reason of the changes with which the parol agreement was concerned, find their answer in the same legal principles, and may be considered together.

No principle of law is more firmly established than that whenever parties enter into an agreement and reduce it to writing, the writing must be held to merge the preceding negotiations, and be taken as the exclusive evidence of their final understanding, so that evidence of oral propositions or agreements anterior to or contemporaneous with its execution will not be received to modify or vary its terms. Galpin v. Atwater, 29 Conn. 93, 97 ; Hildreth v. Hartford, M. & R. Tramway Co., 73 Conn. 631, 635, 48 Atl. 963. But the parties to a written contract, of the character of the one under review, are as free to alter it after it has been made as they were to make it, and all attempts on their part by its terms to tie up their freedom of dealing with each other will be futile.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greenwich Plaza, Inc. v. Whitman and Ransom, No. 9505-4081 (Mar. 19, 1996)
1996 Conn. Super. Ct. 2418 (Connecticut Superior Court, 1996)
Greenwich Plaza v. Whitman Ransom, No. Cvno 9505-4081 (Mar. 19, 1996)
1996 Conn. Super. Ct. 1453 (Connecticut Superior Court, 1996)
Kelly v. Anderson Ridge Associates, No. 29 98 85 (Aug. 15, 1994)
1994 Conn. Super. Ct. 8145 (Connecticut Superior Court, 1994)
Petrucci Construction Co. v. Leepson, No. 23 26 48 (Sep. 13, 1990)
1990 Conn. Super. Ct. 1772 (Connecticut Superior Court, 1990)
S.H.V.C., Inc. v. Roy
450 A.2d 351 (Supreme Court of Connecticut, 1982)
General Electric Supply Co. v. Southern New England Telephone Co.
441 A.2d 581 (Supreme Court of Connecticut, 1981)
Bead Chain Manufacturing Co. v. Saxton Products, Inc.
439 A.2d 314 (Supreme Court of Connecticut, 1981)
S.H.V.C., Inc. v. Roy
428 A.2d 806 (Connecticut Superior Court, 1981)
S. H. v. C., Inc. v. Roy
428 A.2d 806 (Connecticut Superior Court, 1981)
Gordon v. Indusco Management Corp.
320 A.2d 811 (Supreme Court of Connecticut, 1973)
Connersville Country Club v. F. N. Bunzendahl, Inc.
222 N.E.2d 417 (Indiana Court of Appeals, 1967)
J. R. Gray Co. v. Ritchey Flying Service, Inc.
358 S.W.2d 396 (Court of Appeals of Texas, 1962)
Taft Realty Corp. v. Yorkhaven Enterprises, Inc.
150 A.2d 597 (Supreme Court of Connecticut, 1959)
Bradford Novelty Co. v. Technomatic, Inc.
112 A.2d 214 (Supreme Court of Connecticut, 1955)
Opdyke & Butler v. Silver
245 P.2d 306 (California Court of Appeal, 1952)
Blakeslee v. Board of Water Commissioners
183 A. 887 (Supreme Court of Connecticut, 1936)
Baier v. Smith
181 A. 618 (Supreme Court of Connecticut, 1935)
Sitkin v. Smith
276 P. 521 (Arizona Supreme Court, 1929)
Mills v. Roto Co.
133 A. 913 (Supreme Court of Connecticut, 1926)
Clover Manufacturing Co. v. Austin Co.
125 A. 646 (Supreme Court of Connecticut, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
74 A. 763, 82 Conn. 427, 1909 Conn. LEXIS 71, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oloughlin-v-poli-conn-1909.