Kelly v. Anderson Ridge Associates, No. 29 98 85 (Aug. 15, 1994)

1994 Conn. Super. Ct. 8145
CourtConnecticut Superior Court
DecidedAugust 15, 1994
DocketNo. 29 98 85
StatusUnpublished

This text of 1994 Conn. Super. Ct. 8145 (Kelly v. Anderson Ridge Associates, No. 29 98 85 (Aug. 15, 1994)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelly v. Anderson Ridge Associates, No. 29 98 85 (Aug. 15, 1994), 1994 Conn. Super. Ct. 8145 (Colo. Ct. App. 1994).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION The plaintiff paving contractor brought an action in three counts against the defendant, Anderson Ridge Associates, a subdivider, arising from a road construction contract between the CT Page 8146 parties. In the first count, the plaintiff seeks payment of the balance due on the contract of $13,250. In the first and second counts, the plaintiff seeks payment for extra work in the amount of $40,432.82 performed for the defendant beyond the scope of the contract. In the third count, the plaintiff seeks a judgment foreclosing the mechanic's lien securing payment of the amounts due in the first and second counts. The total amount claimed by the plaintiff is $53,682.82 plus attorney's fees and interest.

In its answer and special defenses, the defendant (1) denied that any balance was due on the contract due to the plaintiff's breach of contract; (2) asserted that no amount is due for extra work as all claimed as extra work was within the scope of the "fixed price" contract; (3) claimed that even if the contract was not for a fixed price, it was not responsible for the extra work as the work was done without written change orders or without authorization.

In its setoff and counterclaim, the defendant asserted that the plaintiff (1) breached the contract by not completing the road in a timely fashion and failing to complete the road in a workman like manner; (2) defrauded the defendant to make payments not due the plaintiff; (3) violated the Connecticut Unfair Trade Practices Act and filed an invalid lien on the defendant's property.

On or about March 25, 1988, the plaintiff submitted a bid to construct a road in a recently approved subdivision in Sherman, Connecticut. The bid specifications and price were based upon engineering plans, known as the Rogers' Plans, provided to the plaintiff on defendant's behalf, which plans had been approved by the Town of Sherman as a component of the subdivision approval. Despite this background, these plans were never referenced in or attached to the ultimate written contract which the parties signed.

After that bid submission, the plaintiff entered into contract negotiations with Fred Kleinberg, a lawyer and partner of the defendant, Anderson Ridge Associates. Mr. Kleinberg provided Mr. Kelly with a draft contract rider which contained language that the scope of work under the contract would include "minor changes required by authorities that have jurisdiction." Mr. Kelly requested that the provision be removed from the rider as he would not be responsible for such changes. The provision was deleted from the final contract. In spite of the fact that CT Page 8147 the provision making Kelly responsible for minor changes was deleted from the final contract, the defendant maintains that the contract requires Kelly to bear the cost of all changes ordered by the Town as the contract was a "fixed price, turnkey" contract.

There is no language in the contract that the plaintiff would build the road on a "fixed price, turnkey." However, the defendant relies on paragraphs 2 and 3 of the rider to the contract, requiring that:

2. G.H. Kelly Son (the `Contractor') shall be responsible for complying with all applicable laws, ordinances, rules, regulations and the like relating to its work, including all requirements set forth on the annexed Addendum to Sherman Island Wetlands Application (`Addendum'); however, the owner shall be responsible for paying all fees for all necessary permits customarily paid for by an owner. All labor and materials required to complete the work described on the addendum (including without limitation the driveway work, sedimentation basin and pond) shall be performed and supplied by the Contractor.

3. All work and materials performed and supplied by the Contractor will meet or exceed all applicable specifications and requirements of all governments and agencies having jurisdiction, including without limitation the Town of Sherman, the State of Connecticut, the Planning Zoning Commission, the Inland Wetlands and Water Courses Commission, and the Board of Selectmen; Contractor agrees to keep all such agencies currently informed as to the progress of its work.

The court rejects the contention that the contract was for a fixed price or a turnkey type of job. First, the contract which was drawn by the plaintiff did not use those terms. Second, to the extent there is any ambiguity, it must be construed against the party who drafted the agreement, in this case the defendant which drafted two of the three pages of the agreement.Sturman v. Socha, 191 Conn. 1, 9 (1983). Third, what was the basis of the bargain, if not the Rogers' Plans? Since the contract contained almost no specifications, how could the plaintiff know what was to be built and how and where it was to be built if not by reference to the Rogers' plans which were given to him as the basis from which he was to make his initial bid. Fourth, in determining the intent of the parties to the agreement, it defies logic that despite the fact that the plaintiff negotiated out a provision which would have left the CT Page 8148 plaintiff contractor responsible for "minor" changes required by the Town of Sherman, the parties intended that he would still be liable at his expense to bear the cost of any major changes required by the Town of Sherman. This court observes that the so-called Rogers' Plans are detailed, plotting the location of the roadway and subdivided lots and the elevations of the roadway. These plans were never referred to in the contract of the parties but were shown to the plaintiff before he made his first proposal to bid the job. The contract provides that "any alterations or deviations from the above specifications involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate." The defendant does not concede that many of the "extras" were outside the contract scope but claims that the plaintiff cannot recover for them, in any event, because the orders for them were not in writing. The court finds that no written change orders were requested by the defendant or made out for the bulk of the extra work performed and billed during the course of the project. "Provisions in a written contract requiring written orders for changes in the work or for extra work may be waived by the parties so that the owner becomes liable for changes or extras done by oral direction." Von Langendorff v. Riordan,147 Conn. 524, 528. By their course of conduct, the parties waived their right to written change orders. "[T]he provisions of a written contract can be waived by a subsequent oral agreement."General Electric Supply Co. v. SNETCO, 185 Conn. 583,604. Direction for the performance of work not called for by their contract has sometimes been interpreted as a waiver of the requirement for written approval. Wexler Construction Co. v.Housing Authority, 144 Conn. 187, 193. "[T]he parties to a written contract . . . are as free to alter it after it has been made as they were to make it . . . . [Citations omitted.] To this end oral agreements will be as effective as written ones. [Citation omitted.] And implied agreements satisfactorily established will have all the force of express ones."O'Loughlin v. Poli, 82 Conn. 427, 432. "`[T]he parties to a written contract . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Electric Supply Co. v. Southern New England Telephone Co.
441 A.2d 581 (Supreme Court of Connecticut, 1981)
Von Langendorff v. Riordan
163 A.2d 100 (Supreme Court of Connecticut, 1960)
Hess v. Dumouchel Paper Co.
225 A.2d 797 (Supreme Court of Connecticut, 1966)
Wexler Construction Co. v. Housing Authority
128 A.2d 540 (Supreme Court of Connecticut, 1956)
Sturman v. Socha
463 A.2d 527 (Supreme Court of Connecticut, 1983)
Malone v. Santora
64 A.2d 51 (Supreme Court of Connecticut, 1949)
O'Loughlin v. Poli
74 A. 763 (Supreme Court of Connecticut, 1909)
Blakeslee v. Board of Water Commissioners
183 A. 887 (Supreme Court of Connecticut, 1936)
First Hartford Realty Corp. v. Ellis
434 A.2d 314 (Supreme Court of Connecticut, 1980)
McAllister v. Nichols
474 A.2d 792 (Supreme Court of Connecticut, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
1994 Conn. Super. Ct. 8145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelly-v-anderson-ridge-associates-no-29-98-85-aug-15-1994-connsuperct-1994.