Wexler Construction Co. v. Housing Authority

128 A.2d 540, 144 Conn. 187, 1956 Conn. LEXIS 264
CourtSupreme Court of Connecticut
DecidedDecember 27, 1956
StatusPublished
Cited by48 cases

This text of 128 A.2d 540 (Wexler Construction Co. v. Housing Authority) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wexler Construction Co. v. Housing Authority, 128 A.2d 540, 144 Conn. 187, 1956 Conn. LEXIS 264 (Colo. 1956).

Opinion

Daly, J.

The substituted complaint is in four counts. The court sustained the defendant’s demurrer to the first and fourth counts and rendered judgment that the allegations were insufficient. Each of those counts alleged the following facts: On May 13, 1950, the plaintiff, as general contractor, and the defendant, as the owner, entered into a written contract for the erection of a moderate rental housing project, in accordance with plans and specifications furnished by the defendant, for a contract price of $466,809, subject to additions and deductions. The contract provided that work should be started on May 18, 1950, and that the project, exclusive of landscaping, should be completed in 150 days, and the landscaping in 40 days thereafter. On or about *189 May 13, 1950, the plaintiff, as general contractor, made an oral agreement with the Candor Construction Company, hereinafter called Candor, as subcontractor, wherein the latter agreed to supply all labor, material and equipment necessary to perform the excavation and site development work, in accordance with the plans and specifications furnished by the defendant, for a contract price of $44,000, subject to additions and deductions. This oral agreement was confirmed by a written agreement between the parties dated June 1, 1950. The plaintiff and Candor commenced work under the contracts on or about May 18, 1950.

As the job progressed, it became apparent that the plans and specifications for the excavation and site development work had been prepared without any clear idea either of the results sought to be accomplished or of the conditions which would result if the plans and specifications were carried into effect. It became necessary, therefore, to redesign the work on a day-to-day basis during the construction. The efforts to do this consisted of a series of attempts to solve problems as they arose, and no clear conception of ultimate objectives was ever developed. Consequently, the work as completed was of an extremely costly nature. In addition, the inability to develop a suitable comprehensive plan resulted in a constant stopping and starting of the work. Finally, on or about December 19, 1951, it became necessary to stop the work completely. As of then, the excavation and site development work for a major portion of the site had been completed “in accordance with the defendant’s directives to plaintiff Wexler in part by Candor as plaintiff Wexler’s subcontractor and in part by plaintiff Wexler with its own forces.” A substantial amount *190 of corrective work remained to be done in this area. In the remaining portion of the site, for which no adequate revisions of the contract plans had been prepared, the site development work was incomplete.

On December 19, 1951, at a meeting between representatives of the plaintiff and the defendant, at which representatives of Candor were present, it was agreed that the defendant would have revised plans and specifications for the correction and completion of the site development work prepared and that the plaintiff would submit a proposal for the performance of it and a statement of claims for extra compensation for the work performed up to that date. Thereafter, the defendant had various revised plans and specifications for the completion •of the site development work prepared, but ultimately rejected all of them. On or about March 12, 1952, the defendant requested the plaintiff to subunit its final periodical payment estimate. On that •date all of the work to be performed by the plaintiff under its contract of May 13, 1950, except the site -development work, had been duly performed and •completed. On April 30, 1952, Candor forwarded to the plaintiff its claim. On May 2, 1952, Candor agreed not to enforce collection of its claim against ■the plaintiff except from the proceeds of any recovery by the plaintiff from the defendant on Candor’s behalf or from the proceeds of the plaintiff’s right of exoneration or reimbursement against the -defendant. On or about May 2, 1952, the plaintiff forwarded to the defendant its claim. At the time ■this suit was brought, two years after the completion date originally scheduled, the site development work was still not completed. The excavation ■and site development work performed by Candor, -and by the plaintiff with its own employees, bore no *191 recognizable resemblance to that called for by the contract plans and specifications. In addition, it was performed under conditions not contemplated by anyone at the time the contract of May 13,1950, between tbe plaintiff and the defendant was signed. The payment provisions in that contract which were properly allocable to excavation and site development work were entirely inapplicable.

The defendant, it was alleged, became obligated to pay the plaintiff the reasonable value of the excavation and site development work performed, that value to be determined in the light of the conditions under which the work was performed. The reasonable value of the work was $276,466.81. The total amount of the payments received by the plaintiff from the defendant which were properly allocable to the work was $97,794.54. In the first count the plaintiff sought recovery in quantum meruit and claimed as damages $178,672.27, the difference between $276,466.81 and $97,794.54, plus interest. In the fourth count it sought recovery of this sum, claiming that it was entitled to receive it as compensation for site development work which was not shown on the contract plans and specifications furnished by the defendant.

A copy of the written contract which, the plaintiff alleged, confirmed its oral agreement with Candor for the performance of the excavation and site development work was filed in response to the defendant’s motion for oyer, as provided in the rules. Practice Book § 117. It became, therefore, a part of the pleading to which it related. Morehouse v. Employers’ Liability Assurance Corporation, 119 Conn. 416, 421, 177 A. 568. This written contract contained the following provision: “No allowance for extras will be made to the subcontractor unless *192 the same are first approved in writing from the contractor’s office.” Although the defendant’s demurrer is addressed to the first and fourth counts “and says that the same are insufficient,” it does not challenge the compensability of all of the elements of damage alleged therein. However, as the plaintiff indicates a desire to have the intended issue determined, we shall, for the purpose of this appeal, treat the demurrer as one disputing the sufficiency of the allegations upon which the plaintiff bases its right to recover for the part of the work performed by Candor. The defendant’s ground of demurrer, therefore, is treated as one predicated upon the assumption that the allegations contained in the counts in question did not state or imply that the plaintiff is lawfully indebted to Candor for the work performed by the latter for which the plaintiff seeks recovery. The sole question raised by this appeal is whether or not the court erred in sustaining the demurrer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Law Offices of Charmoy v. Lockery, No. 380135 (Jan. 21, 2003)
2003 Conn. Super. Ct. 1011 (Connecticut Superior Court, 2003)
Primax Properties v. Freedom Homes, No. Cv 02 0099555 S (Dec. 10, 2002)
2002 Conn. Super. Ct. 15721 (Connecticut Superior Court, 2002)
Jackson v. Exxon Mobile Oil Corp, No. Cv 01 0455046 S (Mar. 26, 2002)
2002 Conn. Super. Ct. 3841 (Connecticut Superior Court, 2002)
Boomer v. City of New Haven, No. Cv 001-0451260 S (Sep. 5, 2001)
2001 Conn. Super. Ct. 12436 (Connecticut Superior Court, 2001)
Doe v. Yale University
748 A.2d 834 (Supreme Court of Connecticut, 2000)
Hankard v. Town of Avon, No. Cv 96-0565611s (Jun. 22, 1999) Ct Page 7912
1999 Conn. Super. Ct. 7911 (Connecticut Superior Court, 1999)
Connecticut Carpentry v. Maranba Bldrs., No. Cv 96-0573579s (Jun. 8, 1999)
1999 Conn. Super. Ct. 7106 (Connecticut Superior Court, 1999)
Interior Technology v. Baker Prop. Ld., No. Cv96 0053588s (Feb. 9, 1999)
1999 Conn. Super. Ct. 1483 (Connecticut Superior Court, 1999)
Dudrow v. Ernst Young, No. X01-Cv98-0144211 (Nov. 4, 1998)
1998 Conn. Super. Ct. 12513 (Connecticut Superior Court, 1998)
Kensington Square Ltd. I Ltd. v. Wilson, No. Spnh 9711-52871 (Mar. 27, 1998)
1998 Conn. Super. Ct. 4036 (Connecticut Superior Court, 1998)
Faulkner v. United Technologies Corp.
693 A.2d 293 (Supreme Court of Connecticut, 1997)
Nutrico, Inc. v. Frank's Nursery Crafts, No. Cv96329778 (Mar. 19, 1997)
1997 Conn. Super. Ct. 2734 (Connecticut Superior Court, 1997)
Collins v. Milford Health Care, No. Cv94 04 66 62s (Jul. 17, 1995)
1995 Conn. Super. Ct. 7995 (Connecticut Superior Court, 1995)
Dutra v. Longobardi, No. 35 04 25 (Jan. 5, 1995)
1995 Conn. Super. Ct. 88 (Connecticut Superior Court, 1995)
Benvenuti Oil Co. v. American Nat'l Fire Ins., No. 523609 (Aug. 26, 1994)
1994 Conn. Super. Ct. 8416 (Connecticut Superior Court, 1994)
Kelly v. Anderson Ridge Associates, No. 29 98 85 (Aug. 15, 1994)
1994 Conn. Super. Ct. 8145 (Connecticut Superior Court, 1994)
Connecticut National Bank v. Gagliardi, No. 397427 (Jan. 27, 1992)
1992 Conn. Super. Ct. 301 (Connecticut Superior Court, 1992)
Carmont Properties v. Garthwaite, No. Cv90 0271419 S (Jul. 10, 1991)
1991 Conn. Super. Ct. 6550 (Connecticut Superior Court, 1991)
Cianci Constr. Co. v. Griffin Constr. Co., No. 27 77 93 (Feb. 4, 1991)
1991 Conn. Super. Ct. 1461 (Connecticut Superior Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
128 A.2d 540, 144 Conn. 187, 1956 Conn. LEXIS 264, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wexler-construction-co-v-housing-authority-conn-1956.