Interior Technology v. Baker Prop. Ld., No. Cv96 0053588s (Feb. 9, 1999)

1999 Conn. Super. Ct. 1483
CourtConnecticut Superior Court
DecidedFebruary 9, 1999
DocketNos. CV96 0053588S, CV96 0053763S
StatusUnpublished

This text of 1999 Conn. Super. Ct. 1483 (Interior Technology v. Baker Prop. Ld., No. Cv96 0053588s (Feb. 9, 1999)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interior Technology v. Baker Prop. Ld., No. Cv96 0053588s (Feb. 9, 1999), 1999 Conn. Super. Ct. 1483 (Colo. Ct. App. 1999).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION CT Page 1484
The court has before it two matters involving the same defendant and arising out of the same circumstances. They have been consolidated for purposes of trial. Interior Technologies Inc. (ITI), one of the plaintiffs, has brought a three-count complaint against the defendant, Baker Properties Limited Partnership (Baker), the first count seeking to foreclose a mechanic's lien, the second count alleges a breach of contract, while the third count is a claim for unjust enrichment. The second complaint was filed by Allstate Erectors, Inc. (Allstate), a subcontractor of ITI. The complaint lies in two counts, the first being to foreclose a mechanic's lien and the second count a claim for unjust enrichment.

Baker has responded to both complaints, the pleadings are closed and the matter has come before the undersigned for disposition.

ITI entered into a contract with Baker to install a new metal roof over an old metal roof on property owned by Baker and located at 60 Marsh Hill Road in the Town of Orange. In addition, the contract called for the construction of a truck wash facility and the erection of a canopy over the loading dock. The dispute concerns only the metal roof and does not relate to the other two items.

Allstate, acting as subcontractor of ITI, performed the actual labor involved in the installation of the metal roof. The testimony indicated that neither party had little if any experience in installing a metal roof over an old one.

The materials for the project were fabricated by American Builders, Inc. (ABC) under a contract with ITI. ABC filed its own mechanic's lien which has been dismissed as being untimely.

The court will first consider the validity of both mechanic's liens. The mechanic's lien filed by ITI was recorded on the Land Records of the Town of Orange on March 6, 1995, while the lien of Allstate was recorded on January 18, 1995.

In order for a mechanic's lien to be valid, the person performing the services or furnishing the materials must, within 90 days after ceasing to do so, lodge with the Town Clerk wherein the building the subject of such services or furnishing of CT Page 1485 materials is located, a certificate in writing, describing the premises, the amount claimed as a lien, the name or names of the person or persons against whom the lien is being filed, and the date of the commencement of the performance of the services or furnishing of materials. It must also be stated that the amount claimed is justly due. In addition, the certificate of lien must be subscribed and sworn to by the claimant and, within the same time or prior to but not later than 30 days after lodging the certificate, serve a true and attested copy on the owner. See Connecticut General Statutes § 49-34.

The only dispute centers around whether the liens were recorded within 90 days after the services or materials were furnished or completed. The Allstate lien was recorded on January 18, 1995 and the lien of ITI was recorded on March 6, 1995. Based on these recordings, insofar as Allstate is concerned, work would have had to be completed by October 20, 1994 and the work performed by ITI completed by December 8, 1994.

The question here is one of substantial completion. "The rule is one to be applied fairly to both the lienor and the owner. If, after the work is substantially done, the claimant for material furnished or services rendered shall not unreasonably delay the completion of the work, the date of beginning of the sixty-day period will be taken as the date when the work was substantially done. No trivial or inconsequential service or work done after the substantial completion of the building will extend the time for claiming the lien, or revive an expired lien when an unreasonable period has elapsed since the substantial completion." The Martin Tire Rubber Co. v. The Kelly Tire Rubber Co., 99 Conn. 396, 399-400.

The testimony of Allstate's president, Roland Deschaime, indicates that he was last on the roof on December 8, 1994 in the company of a representative of Baker. The only work performed on that date was the repair of a pinhole. Furthermore, the testimony discloses that the roof was finished before Christmas and that he was called back in January to correct certain conditions relating to leakage. The last time his firm performed any work of any substance was in March of 1994. There are no invoices after that. There were approximately four visits to the site after March 1994. From January 1994 through March of 1994 an appreciable amount of repair work was done. There is no evidence of any substantial work being done thereafter. CT Page 1486

The mechanic's lien was recorded on the Orange Land Records on January 18, 1994, a date that is far beyond the 90-day period set forth in § 49-34 of the Connecticut General Statutes.

The court finds that the filing of the mechanic's lien by Allstate Erectors is untimely and therefore void.

ITI also claims that the last date on which work was completed was December 8, 1994. Again, the witness could not testify as to the nature of the work performed. There was no invoice presented to Baker for the work done. In fact, even though ITI claims that work was done during October and November, they have presented no invoice for payment leading the court to believe that any work done was inconsequential. In fact, the last invoice presented for work performed is July 1994. There is no evidence substantiating any work performed during the Fall of 1994. ITI has failed to sustain its burden of proof regarding the timeliness of its lien. The court finds that the mechanic's lien filed by ITI is untimely and therefore void.

Plaintiff ITI's second count alleges a breach of contract. Article II, Section 1a and b of the contract states in pertinent part:

"A. In General: Complete all roofing, metal building systems canopy and metal panel work listed in several parts of the Contract Documents illustrated on attached Schedule C included herein.

B. Comply with all provisions of the contract including contract items on attached schedules `C-1' and C-2.'"

Section "C-2" of the Schedule is entitled "Scope of Work."

Schedule "C-2-1" states in relevant part that:

"The subcontractor shall furnish and install a new standing seam roof over the existing standing seam roof. . . . The subcontractor shall provide a complete roof system that is weather tight and maintains a U.L. 90 wind uplift rating."

Schedule "C-2-2" recites the following:

"The subcontractor shall install structural support purlins over the existing roof. . . . Fasten the new purlins directly CT Page 1487 to the existing purlins. A sliding clip shall be used to connect the standing seam panels to the purlins. All work shall be in accordance with the manufacturer's instructions."

Schedule "C-2", paragraph 3 states that:

"The subcontractors shall furnish and install standing seam panels that will provide a 20 year weather tight warranty. Provide a full executed original 20 year manufacturer's warranty to Baker Properties at the time of substantial completion and/or acceptance of roof installation by Baker Properties. . . . The manufacturer shall inspect and accept the roofing system prior to substantial completion of the project."

Paragraph 4 of Schedule "C-2" states:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Healy
405 A.2d 54 (Supreme Court of Connecticut, 1978)
Monarch Accounting Supplies, Inc. v. Prezioso
368 A.2d 6 (Supreme Court of Connecticut, 1976)
Wexler Construction Co. v. Housing Authority
128 A.2d 540 (Supreme Court of Connecticut, 1956)
The Martin Tire Rubber Co. v. the Kelly Tire Rubber
122 A. 102 (Supreme Court of Connecticut, 1923)
Schleicher v. Schleicher
182 A. 162 (Supreme Court of Connecticut, 1935)
Clark-Fitzpatrick, Inc. v. Long Island Rail Road
516 N.E.2d 190 (New York Court of Appeals, 1987)
Providence Electric Co. v. Sutton Place, Inc.
287 A.2d 379 (Supreme Court of Connecticut, 1971)
National CSS, Inc. v. City of Stamford
489 A.2d 1034 (Supreme Court of Connecticut, 1985)
Burns v. Koellmer
527 A.2d 1210 (Connecticut Appellate Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
1999 Conn. Super. Ct. 1483, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interior-technology-v-baker-prop-ld-no-cv96-0053588s-feb-9-1999-connsuperct-1999.