Cianci Constr. Co. v. Griffin Constr. Co., No. 27 77 93 (Feb. 4, 1991)

1991 Conn. Super. Ct. 1461
CourtConnecticut Superior Court
DecidedFebruary 4, 1991
DocketNo. 27 77 93
StatusUnpublished

This text of 1991 Conn. Super. Ct. 1461 (Cianci Constr. Co. v. Griffin Constr. Co., No. 27 77 93 (Feb. 4, 1991)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cianci Constr. Co. v. Griffin Constr. Co., No. 27 77 93 (Feb. 4, 1991), 1991 Conn. Super. Ct. 1461 (Colo. Ct. App. 1991).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION This action for damages arises out of a contractual arrangement between the plaintiff K. E. Cianci Construction Company ("Cianci Construction") and the defendant Griffin Construction Co., Inc. ("Griffin Construction") whereby the plaintiff as a subcontractor undertook to perform certain exterior site work and excavation for the construction of a truck terminal for New Penn Motor Express ("New Penn") in Southington. Kenneth C. Cianci ("Cianci") is the president and owner of Cianci Construction. Cianci Construction maintains that it is entitled to damages for the unpaid balance on the written contract as well as for certain extras.

The first count of the complaint1 as amended which is in three counts alleges the following: first, on or after May 1, 1987, Cianci Construction, as a subcontractor, entered into an agreement with Griffin Construction, as the contractor, pursuant to which Cianci Construction agreed to perform certain exterior site and excavation work necessary in connection with the construction of the New Penn truck terminal for which Griffin Construction agreed to pay Griffin Construction the contract price of $511,000.00. This contract was amended in July 19872 by a provision substituting eight inches of processed gravel in place of eight inch bank run gravel under all bituminous concrete surfaces and the contract amount was increased to $526,750.00. The plaintiff next alleges that it undertook and completed its performance in compliance with its agreement with Griffin construction except for certain portions of the contract from which it was "either excused or prevented from performing." Cianci Construction further alleges that there is an outstanding balance of $35,750.00 due it from Griffin Construction which, despite demand, the latter has refused to pay and is, therefore, CT Page 1462 in breach of its agreement.

As to the first count the defendant admits the initial allegation to the extent that it alleges a contract was entered into between the parties on or after May 1, 1987 which was later amended sometime in July 1987 and, in doing so, alleges that the terms of the contract and Cianci Construction's obligation under it are fully set out in the written contract of July 1987. The defendant denies the remainder of the allegations in the first count.

In the second count, which is for extras, the plaintiff repeats its allegations of the contractual arrangement between the parties as well as its subsequent completion in accordance with its subcontract agreement except for the portions of which it was "either excused or prevented from performing." It goes on to allege that in addition to performing under the subcontract, Cianci Construction later agreed to supply extra and additional labor, materials and services on the New Penn project, not ordered by its subcontract agreement and/or for which Griffin Construction agreed to pay it. Although it had satisfactorily performed all of the "agreed-upon extras and additional labor, materials and services" for which the plaintiff alleges Griffin Construction owes it the amount of $87,017.15, the defendant has failed, despite demand, to pay that sum and has therefore breached its agreement with the plaintiff concerning such "extra and additional labor, materials and services."

As to the allegations of the second count the defendant repeats its answer to those allegations incorporated from the first count. With reference to the plaintiff's allegation of an agreement between them for Griffin Construction to pay the plaintiff for the extra and additional labor, materials and services on the New Penn project not covered by the written contract agreement, the defendant admits that the plaintiff supplied and performed certain additional labor, materials and services that were not covered by the agreement, it denies the balance of those allegations. The defendant goes on essentially to deny all the remaining allegations of the second count which include the plaintiff's claim of satisfactory completion of such extras and additional work, the amount of $87,017.15 due therefor and that it is in breach of the alleged agreement to pay that amount for them.

The third count of the amended complaint sounds in quantum meruit. The plaintiff first alleges that at some time subsequent to May 1, 1987, it began furnishing labor, materials and related services necessary to perform certain site work, excavation and related work on the construction project known as the New Penn terminal. The plaintiff then alleges that it do so with the full CT Page 1463 knowledge of and/or at the request of the defendant and that the defendant was on notice that it expected to be paid the reasonable value of such items and that the defendant expected or reasonably should have expected to pay for them. It further alleges that the reasonable value of these materials, labor and related services so furnished to Griffin Construction is $625,267.15 of which Griffin Construction has paid $502,500.00, leaving a balance due Cianci Construction in the amount of $122,767.15.

In its answer to the third count, the defendant admits its first allegation. While it admits "that the plaintiff furnished labor, materials and related services with its knowledge," it denies that "all of said labor, materials and related services were furnished at its request" and although, the defendant admits that while "it had notice that the plaintiff expected to be paid reasonable value . . .," it denies that "it should have expected or reasonably should have expected to pay the plaintiff for same." (emphasis added) The defendant essentially denies the remaining allegations as to the amount claimed as being the reasonable value of these items as well as the amount claimed to be due the plaintiff. The defendant also filed two special defenses.3

As already indicated the plaintiff seeks money damages. It maintains that it is entitled to recover $122,767.15; it breaks this amount down to $37,750.00 as remaining due to it on the written contract and $87,015.15 as the amount due to it for the claimed extras. In addition, it seeks interest at the rate of ten percent per year under General Statutes 37-3a4 in the event the court should award it less than $117,000.00. There it points to the fact that it filed an offer of judgment on November 20, 1989, wherein it offered to take judgment against the defendant in the amount of $117,000.00. The defendant did not accept that offer of judgment and in that connection it contends that if the court should award damages in excess of $117,000.00 it is then entitled to interest at a larger rate in accordance with General Statutes52-192a(b).5 The defendant, on the other hand, concedes that it is indebted to the plaintiff but only in the amount of $17,908.50. Griffin Construction reaches this figure by deducting from the amounts claimed to be due by the plaintiff those amounts attributable to the plaintiff's defective work under the written contract as well as certain credits allegedly due to the defendant.

It should be useful at this juncture to set out certain facts to serve as background for the later analysis of specific issues involved in this case which will be supplemented as circumstances require. In the spring of 1987 Cianci Construction submitted a bid of $511,000.00 to Griffin Construction to become the subcontractor to do the work and supply the materials and labor on the New Penn trucking terminal project on Canal Street in CT Page 1464 Southington.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Al Johnson Construction Company v. The United States
854 F.2d 467 (Federal Circuit, 1988)
Carolina Mechanical Contractors, Inc. v. Yeargin Construction Co.
198 S.E.2d 224 (Supreme Court of South Carolina, 1973)
Brusegaard v. Schroeder
199 N.W.2d 921 (North Dakota Supreme Court, 1972)
C. F. Bolster Co. v. J. C. Boespflug Construction Co.
334 P.2d 247 (California Court of Appeal, 1959)
Boland v. Vanderbilt
102 A.2d 362 (Supreme Court of Connecticut, 1953)
Duley v. Plourde
365 A.2d 1148 (Supreme Court of Connecticut, 1976)
Bell v. Bihary
362 A.2d 963 (Supreme Court of Connecticut, 1975)
Gutowski v. City of New Britain
327 A.2d 552 (Supreme Court of Connecticut, 1973)
Sasso v. Ayotte
235 A.2d 636 (Supreme Court of Connecticut, 1967)
Nixon v. Gniazdowski
138 A.2d 796 (Supreme Court of Connecticut, 1958)
Vincenzi v. Cerro
442 A.2d 1352 (Supreme Court of Connecticut, 1982)
Steinman v. Maier
427 A.2d 828 (Supreme Court of Connecticut, 1980)
Nass v. Town of Duxbury
99 N.E.2d 54 (Massachusetts Supreme Judicial Court, 1951)
Jacobson Electric Co. v. Rome Fastener Corporation
238 A.2d 415 (Supreme Court of Connecticut, 1968)
Swartz v. General Motors Corp.
378 N.E.2d 61 (Massachusetts Supreme Judicial Court, 1978)
Stanton v. Grigley
418 A.2d 923 (Supreme Court of Connecticut, 1979)
Stephanofsky v. Hill
71 A.2d 560 (Supreme Court of Connecticut, 1950)
Citerella v. United Illuminating Co.
266 A.2d 382 (Supreme Court of Connecticut, 1969)
Robert Lawrence Associates, Inc. v. Del Vecchio
420 A.2d 1142 (Supreme Court of Connecticut, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
1991 Conn. Super. Ct. 1461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cianci-constr-co-v-griffin-constr-co-no-27-77-93-feb-4-1991-connsuperct-1991.