Carolina Mechanical Contractors, Inc. v. Yeargin Construction Co.

198 S.E.2d 224, 261 S.C. 1, 1973 S.C. LEXIS 208
CourtSupreme Court of South Carolina
DecidedJuly 9, 1973
Docket19652
StatusPublished
Cited by6 cases

This text of 198 S.E.2d 224 (Carolina Mechanical Contractors, Inc. v. Yeargin Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carolina Mechanical Contractors, Inc. v. Yeargin Construction Co., 198 S.E.2d 224, 261 S.C. 1, 1973 S.C. LEXIS 208 (S.C. 1973).

Opinions

Littlejohn, Justice:

This action in contract arises out of the construction of McAlister Square Shopping Center in Greenville. Yeargin Construction Company, Inc., the defendant, was the general contractor and subcontracted all of the mechanical work (air conditioning, plumbing, etc.) to Carolina Mechanical Contractors, Inc., the plaintiff.

At issue in the trial were questions involving the nature and extent of agreements between the parties and the validity of claims for additional work asserted by the plaintiff.

The shopping center construction project was started in the spring of 1967 without agreements in writing. The owners, in the fall of 1966, were trying to find a means to finance the project and needed a proposed dollar figure with which to approach lending institutions. The defendant was asked by the owners to give a figure, which at most could only be a rough estimate, and was promised the general contract for the project if it could be financed and built. In order for the defendant to supply the overall figure, it was necessary for it to procure estimated proposals from subcontractors. The plaintiff, as a potential subcontractor of the mechanical work, was asked by the defendant to supply a figure. To accomplish all of this, drawings of other similar shopping centers were used as a basis for arriving at estimated figures. At that point neither the owners, nor the general contractor, nor the subcontractors knew with any detail the requirements of stores and shops that were to be constructed. Plaintiff submitted to the defendant a figure of $1,079,348.00 for the mechanical work. The letter, dated October 19, 1966, submitting the figure, contained the following paragraphs:

[5]*5“We are pleased to quote you a price of One million seventy-nine thousand three hundred forty-eight ($1,079,348-.00) dollars for furnishing and installing Site Utilities, Plumbing, Drainage, Heating and Air Conditioning, Fire Protection and miscellaneous items of mechanical requirements in accordance with the attached outlined specifications.

“Our price for furnishing and installing these mechanical systems is based on the information that has been furnished us to date. The final price shall be adjusted in accordance with the final design requirements.”

After financing was assured, work was started by both the contractor and the subcontractor on oral authorization. Thereafter, on July 14, 1967, the defendant sent a letter to the plaintiff as follows:

“This letter is to authorize you to proceed with any necessary arrangements concerning the performance of mechanical work on the above job. A formal Purchase Order and Subcontract Agreement will be issued to you at a later date when all of the proper details have been worked out.”

Work proceeded on the shopping center under this arrangement until October 16, 1967. By that time, the plaintiff had submitted and the defendant had honored some $500,000.00 in invoices. Payments were made on a cost-plus basis. The arrangement was a satisfactory one and the project proceeded with haste. On October 16, 1967, the defendant submitted to the plaintiff a purchase order and a contract, which were signed by the parties.1 Defendant now [6]*6claims these constituted a final and binding contract, into which merged all prior agreements. On the other hand, plaintiff claims that the contract was merely a memorandum.

The whole project was a “hurry up” undertaking, and many changes in plans were effected on an informal basis. When the shopping center was completed, plaintiff presented some $225,000.00 in claims for extras. This was over and above the $993,753.00 2 referred to in the contract. The defendant approved and paid more than $130,000.00 and disallowed the balance. This suit was commenced to collect the balance of $112,965.64 alleged to be still owed the plaintiff by the defendant.

By agreement of counsel, the case was tried without a jury before the judge. After taking testimony, which required [7]*7six full days, the trial judge took the case under advisement. Thereafter, he granted judgment in favor of the plaintiff in the amount of $33,546.69, with interest. This amount represented a total of ten items; he rejected the rest of plaintiff’s claims. It is from this order that the defendant has appealed.

The defendant challenges the trial judge’s findings that the contract and purchase order of October 16, 1967 was not the sole agreement between the parties; that the alleged extras could be considered in the same category as other extras claimed by plaintiff and paid by the defendant; and that the plaintiff was entitled to $33,546.69 in extras. Defendant also asserts that it is due certain credits and that plaintiff should have been required to account for an alleged contingency fund included in the alleged guaranteed maximum contract price.

From the inception, the financing, planning and construction of the shopping center was done in a piecemeal manner. The record fairly indicates that only a facsimile of the final plans and specifications were completed prior to commencement of construction. This is understandable because the owners did not know in the beginning that tenants would occupy a great portion of the space to be provided. Firm plans and specifications were delivered to the general contractor as definite phases of construction began.

It is apparent from the record that a great deal of confusion existed over what type contract was entered into and, for that matter, as to just what would constitute the contract itself. The record is full of references to a cost-plus contract, to a guaranteed maximum contract, and to a combination guaranteed maximum cost-plus contract. In describing the relationship, the trial judge stated in his order:

“The situation is not one . . . where the parties sought to merge all prior verbal negotiations into a single contract agreement prior to commencing work. Rather, . . . the papers were more like a memorandum of the arrangement [8]*8under which Carolina [plaintiff] had already performed nearly half its work.”

Since the case is one at law, tried by counsel before the trial judge without a jury, the scope of this Court’s review is limited. It is a sound principle of law, approved by this Court, that when an action at law is by agreement of the parties tried by a judge without a jury, his findings of fact have the force and effect of a jury verdict, and are conclusive upon appeal when supported by competent evidence. Beheler v. National Grange Mut. Ins. Co., 252 S. C. 530, 167 S. E. (2d) 436 (1969); Reid v. Hardware Mut. Ins. Co. of Carolinas, Inc., 252 S. C. 339, 166 S. E. (2d) 317 (1969). And this Court will examine the record only to see if there is any competent evidence to support the findings of the judge. Marsh Plywood Corp. v. Graham, 240 S. C. 486, 126 S. E. (2d) 510 (1962).

When the question is: Did the parties assent to a particular writing as the complete and accurate integration of the contract ? the question is one of fact. 3 Corrbin, Contracts § 573 (1960); 9 Wigmore, Evidence, § 2429 (3rd ed. 1940). And whether a paper is a memorandum or a written contract is a question for the jury, to be determined from the whole of the evidence. 3 Corbin, Contracts, § 588 (1960); Walley v. Bay Petroleum Corp., 312 F. (2d) 540 (5th Cir. 1963).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ingle v. Kuszmaul
Court of Appeals of South Carolina, 2005
Cianci Constr. Co. v. Griffin Constr. Co., No. 27 77 93 (Feb. 4, 1991)
1991 Conn. Super. Ct. 1461 (Connecticut Superior Court, 1991)
Lawrimore v. American Health & Life Insurance
276 S.E.2d 296 (Supreme Court of South Carolina, 1981)
Richen-Gemco, Inc. v. Heltra, Inc.
540 F.2d 1235 (Fourth Circuit, 1976)
Crescent Co. of Spartanburg, Inc. v. Insurance Co. of North America
225 S.E.2d 656 (Supreme Court of South Carolina, 1976)
Carolina Mechanical Contractors, Inc. v. Yeargin Construction Co.
198 S.E.2d 224 (Supreme Court of South Carolina, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
198 S.E.2d 224, 261 S.C. 1, 1973 S.C. LEXIS 208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carolina-mechanical-contractors-inc-v-yeargin-construction-co-sc-1973.