Ingle v. Kuszmaul

CourtCourt of Appeals of South Carolina
DecidedJune 15, 2005
Docket2005-UP-393
StatusUnpublished

This text of Ingle v. Kuszmaul (Ingle v. Kuszmaul) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ingle v. Kuszmaul, (S.C. Ct. App. 2005).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals


John Ingle, d/b/a Ingle & Company, Respondent,

v.

Ken Kuszmaul, Environmental Specialties, Inc., Indiana Lumbermen’s Mutual Insurance Co., Spartanburg Sanitary Sewer District, Spartanburg Water System and Spartanburg Metropolitan District, Defendants,

of whom Ken Kuszmaul and Environmental Specialties, Inc., are, Appellants.


Appeal From Spartanburg County
Larry R. Patterson, Circuit Court Judge


Unpublished Opinion No. 2005-UP-393
Submitted May 1, 2005 – Filed June 15, 2005


AFFIRMED IN PART AND REVERSED IN PART


Adam Fisher, Jr., of Greenville, for Appellants. 

Charles Preston Edwards, of Spartanburg, for Respondent.

PER CURIAM:  John Ingle sued Environmental Specialties, Inc. (ESI) and Ken Kuszmaul alleging breach of contract.  After a bench trial, the trial court awarded Ingle $56,471 on the contract and $16,805.76 in attorney’s fees and costs.  ESI and Kuszmaul appeal.  We affirm in part and reverse in part.[1]

FACTS

ESI contracted to build a project for Spartanburg Sanitary Sewer District.  This contract required ESI to obtain a payment bond.  ESI obtained the bond from Indiana Lumbermen’s Mutual Insurance Co. 

Kuszmaul, on behalf of ESI, contacted John Ingle about performing subcontract work on the project.  Ingle and ESI entered into an oral agreement under which Ingle agreed to construct a pre-engineered building, including laying the foundation and installing yard pipe to the building. 

ESI, Kuszmaul, and Ingle later disagreed on the amount ESI contracted to pay Ingle for his work.  Ingle filed a mechanic’s lien on the sewer district’s property seeking payment of $56,471 plus costs and attorney’s fees.  Ingle then filed a complaint and lis pendens seeking to foreclose on the mechanic’s lien or, in the alternative, seeking payment pursuant to the payment bond.  The trial court issued a consent order pursuant to the parties’ agreement to dismiss the mechanic’s lien and lis pendens, in exchange for the sewer district’s deposit of approximately $75,000 into escrow pending resolution of the parties’ dispute. 

Ingle filed an amended complaint against Kuszmaul, ESI, and Lumbermen’s alleging ESI owed him $56,471 for work performed.  Ingle also sought incidental and consequential damages and attorney’s fees and costs. 

ESI, Kuszmaul, and Lumbermen’s answered Ingle’s complaint, denying all material allegations and asserting counterclaims including:  (1) breach of contract; (2) breach of warranty; (3) negligence; and (4) quantum meruit.  Kuszmaul and ESI claimed Ingle’s work contained numerous defects, and was not performed in a timely manner.  Kuszmaul and ESI alleged they suffered actual, consequential, and special damages because Ingle’s performance damaged their relationship with the sewer district.  In addition, Kuszmaul and ESI claimed damages as a result of performing or hiring other subcontractors to perform work Ingle did not complete.  Kuszmaul and ESI also alleged that due to the absence of a statutory or contractual provision permitting the award of attorney’s fees, Ingle was not entitled to fees. 

The trial court found the parties entered into a contract entitling Ingle to receive $72,000 for his services.  The court thus awarded Ingle $56,471, the unpaid balance due under the contract,[2] and $16,805.76 in attorney’s fees and costs.  In addition, the trial court found for Ingle on all counterclaims and set-offs. 

STANDARD OF REVIEW

An action for breach of contract is an action at law.  Sherman v. W & B Enters., Inc., 357 S.C. 243, 247, 592 S.E.2d 307, 309 (Ct. App. 2003).  In an action at law, tried without a jury, our jurisdiction extends only to the correction of errors of law.  Kemp v. Rawlings, 358 S.C. 28, 34, 594 S.E.2d 845, 848 (2004).  Therefore, we will not disturb the trial court’s findings of fact unless they are wholly unsupported by the evidence.  Id.

LAW/ANALYSIS

I.  Breach of Contract

ESI and Kuszmaul (hereinafter referred to collectively as ESI) argue the trial court erred in finding Ingle did not breach the contract and in finding ESI breached the contract.  ESI asserts the parties agreed to a contract price of $47,000, rather than $72,000, and ESI did not breach the contract by failing to pay Ingle the additional $56,471.  In addition, ESI claims Ingle failed to perform under the terms of the contract.  We disagree.

We find evidence existed to support the trial court’s findings of a contract price of $72,000 and ESI’s breach of the contract.  The amount due under a contract is for the fact finder.  J.J. Lawter Plumbing v. Wen Chow Int’l Trade & Inv., Inc., 286 S.C. 49, 55, 331 S.E.2d 789, 792 (Ct. App. 1985).  The failure to make payment as provided in a contract constitutes a substantial breach of the contract.  Zemp Constr. Co. v. Harmon Bros. Constr. Co., 225 S.C. 361, 366, 82 S.E.2d 531, 533 (1954). 

Ingle testified he sent a fax outlining the work he proposed to do on the project.  Ingle stated that after he sent the fax, he and Kuszmaul had a conversation concerning the cost of Ingle’s work.  Ingle maintained he quoted Kuszmaul a price of $72,000 for the work and Kuszmaul agreed to the price.  Kuszmaul admitted he did not pay at least two of the invoices he received from Ingle.  There is evidence to support the trial court’s findings of the contract price and ESI’s breach of contract.

In addition, we find evidence to support the trial court’s finding that Ingle did not breach the contract.  ESI asserts Ingle breached the contract by failing to complete the work he contracted to perform.  One who prevents a condition of a contract cannot rely on the other party’s resulting nonperformance in an action for breach of contract.  Champion v. Whaley, 280 S.C. 116, 120, 311 S.E.2d 404, 406 (Ct. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diamond Swimming Pool Co. v. Broome
166 S.E.2d 308 (Supreme Court of South Carolina, 1969)
Carolina Mechanical Contractors, Inc. v. Yeargin Construction Co.
198 S.E.2d 224 (Supreme Court of South Carolina, 1973)
Zemp Const. Co. v. HARMON BROS. CONST. CO.
82 S.E.2d 531 (Supreme Court of South Carolina, 1954)
Sherman v. W & B ENTERPRISES, INC.
592 S.E.2d 307 (Court of Appeals of South Carolina, 2003)
Kemp v. Rawlings
594 S.E.2d 845 (Supreme Court of South Carolina, 2004)
Champion v. Whaley
311 S.E.2d 404 (Court of Appeals of South Carolina, 1984)
Seckinger v. Vessel, Excalibur
483 S.E.2d 775 (Court of Appeals of South Carolina, 1997)
J. J. Lawter Plumbing v. Wen Chow International Trade & Investment, Inc.
331 S.E.2d 789 (Court of Appeals of South Carolina, 1985)
Belton v. State
529 S.E.2d 4 (Supreme Court of South Carolina, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Ingle v. Kuszmaul, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ingle-v-kuszmaul-scctapp-2005.