Diamond Swimming Pool Co. v. Broome

166 S.E.2d 308, 252 S.C. 379, 1969 S.C. LEXIS 245
CourtSupreme Court of South Carolina
DecidedMarch 12, 1969
Docket18890
StatusPublished
Cited by15 cases

This text of 166 S.E.2d 308 (Diamond Swimming Pool Co. v. Broome) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diamond Swimming Pool Co. v. Broome, 166 S.E.2d 308, 252 S.C. 379, 1969 S.C. LEXIS 245 (S.C. 1969).

Opinions

Littlejohn, Justice.

This is an action to foreclose a mechanic’s lien.

Diamond Swimming Pool Company, the plaintiff herein, entered into a written contract with the defendant Eugene M. Broome setting forth certain dimensions and specifications for the construction of a swimming pool and patio in consideration of the sum of $3,000 paid in cash and a balance [381]*381of $4,975 due upon completion of construction. According to the plaintiff, the contract signed was the result of a redrafting of an earlier proposed contract which dealt with a larger pool at a higher price.

At the time construction commenced, Broome furnished a landscape drawing by which he directed the plaintiff’s construction foreman to build the pool. Upon completion of the project a balance of $3,475 of the agreed consideration remained unpaid, and the defendants refused to make payment.

The plaintiff instituted the present action based on the written contract as allegedly modified by the landscape drawing furnished by Broome. The defendants answer denying any modification of the written contract. They further answered that the pool is much smaller than the one contracted for, that the patio is defective and was not built according to the specifications in the contract, and that they will have to pay more to correct the pool size and the defects in the patio than the $3,475 which the plaintiff seeks to recover.

The matter was heard before Honorable Harry M. Lightsey, Master in Equity for Richland County. The plaintiff contended that the first written contract submitted was for a larger pool at a higher cost; that this contract was rewritten and, through error in the course of rewriting, only the first two pages were rewritten leaving portions of the specifications for the larger pool; and that in any event the contract was modified with respect to the size of the pool by the landscape plan furnished by Broome. After hearing testimony and personally inspecting the construction site, the master found that the contract was effectively modified by the supplying of the landscape plans with instructions to use them, and that the plaintiff substantially performed the contract as modified. He further found that the patio is defective and that the imperfection therein entitles the defendants to a setoff in the amount of $1,275 against the amount due of $3,475.

[382]*382The county court in a short order adopted the master’s report in every respect, and the defendants appeal to this court. They allege error in the master’s findings, concurred in by the lower court, in (1) holding that the original contract was modified by the landscape drawing; (2) holding that there was error in the re-drafting of the original contract; (3)holding that the plaintiff substantially complied with the contract; and (4) holding that $1,275 was the proper amount to be allowed by way of setoff.

The court or any of the parties to an action to foreclose a mechanic’s lien may require that questions of fact be submitted to a jury. (Section 45-273 of the 1962 Code of Laws). Failure to request a jury trial, however, does not change the essential nature of the foreclosure proceedings established by statute. Confirmation of the master’s findings by the court below gave those findings the same force and effect as the verdict of a jury, unless the court, as the trier of fact, committed some error of law leading to an erroneous conclusion, or the evidence is reasonably susceptible of the opposite conclusion only. We consider the exceptions in this light.

The first question presented concerns the finding that the written contract was modified by Broome’s direction to build the pool and patio by a landscape drawing which he submitted to the foreman. The plan is a detailed landscaping scheme for a considerable amount of property of which the swimming pool area is only a relatively small part. The plaintiff’s foreman on the project, among other witnesses for the plaintiff, testified that Broome instructed him to build the pool in accordance with the drawing; and Broome himself admits so instructing the foreman. The plaintiff contends that both the contract and the drawing could not be consistently followed. The defendant argued that the contract could have been followed and that the landscape plan was to be used only as a general guide for placement of the pool on the property.

[383]*383The master had the benefit of hearing and observing the witnesses in this case; in addition he inspected and personally observed the construction project in dispute. We cannot say that his conclusion that the contract was modified so as to fit the pool and patio into the comprehensive scheme represented by the drawing was without evidentiary support. In making this determination the master may have considered, among other things, the fact that the defendants observed the construction from time to time and interposed no objection until the project was completed.

Because we agree with the master and the lower court that submission of the drawing by Broome constituted modification of the contract with respect to the size of the pool, we find it unnecessary to deal with the question of the adequacy of the evidence supporting a finding that an error was made in redrafting the original contract. The written contract was superseded by the modification, at least with respect to the only contractual specification here in controversy, to wit, the size of the pool.

The third question raised by the defendant concerns the master’s finding that the plaintiff substantially performed the contract. Because the defendants take the position that the contract terms dealing with the size of the pool were neither modified by the landscape drawing nor intended to be changed by the redrafting of the written contract, they use the dimensions and specifications incorporated in the original written contract as the basis for comparison with the pool actually built. In so doing they conclude that substantial performance was not obtained.

Having determined that the contract was modified, however, it is the modified contract which must be compared with actual performance. The evidence is that the landscape drawing calls for a pool containing 924 square feet. The pool actually constructed, if the outside coping is included (as the testimony reveals is a frequently used way of quoting pool sizes), contains 946 square feet and without inclusion of the coping contains 788 square feet.

[384]*384The doctrine of substantial performance was conceived for the case where a plaintiff’s partial performance has already given to a defendant substantially all that he bargained for and is of such a nature that it cannot be returned. E. g., 17A C. J. S. Contracts § 508 (1963). Justice can best be achieved in such a case by a setoff against the contract price rather than by denial of recovery of the contract price. The master in this case listened to conflicting evidence on the inclusion of the coping in pool measurements and then visited the actual construction site. We cannot say that his finding of substantial performance was without evidentiary support.

The final. question as stated in appellants’ brief is as follows: “After a definite finding that there was a defect in the patio, was there any competent testimony to fix the amount necessary to correct the defect at $1,275 ?” In exception No. 6 the question is stated somewhat differently:

“6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clardy v. BODOLOSKY
679 S.E.2d 527 (Court of Appeals of South Carolina, 2009)
Watts Construction Company v. Feltes
Court of Appeals of South Carolina, 2006
Ingle v. Kuszmaul
Court of Appeals of South Carolina, 2005
Coastal Seafood Co. v. Alcoa South Carolina, Inc.
381 S.E.2d 502 (Court of Appeals of South Carolina, 1989)
Aiken County v. BSP Division of Envirotech Corp.
866 F.2d 661 (Fourth Circuit, 1989)
Baker v. Aetna Insurance Company
262 S.E.2d 417 (Supreme Court of South Carolina, 1980)
Wallace Concrete Pipe Co. v. McGregor Downs, L. P.
251 S.E.2d 759 (Supreme Court of South Carolina, 1979)
Black v. Clark
243 S.E.2d 808 (Court of Appeals of North Carolina, 1978)
McLeod v. Sandy Island Corp.
216 S.E.2d 746 (Supreme Court of South Carolina, 1975)
E & S INVESTMENT CORP. v. Richland Bowl, Inc.
216 S.E.2d 522 (Supreme Court of South Carolina, 1975)
Diamond Swimming Pool Co. v. Broome
166 S.E.2d 308 (Supreme Court of South Carolina, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
166 S.E.2d 308, 252 S.C. 379, 1969 S.C. LEXIS 245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diamond-swimming-pool-co-v-broome-sc-1969.