Southland Renda JV v. Xylem Water Solutions, U.S.A., Inc.

CourtDistrict Court, D. South Carolina
DecidedMarch 23, 2023
Docket2:21-cv-02550
StatusUnknown

This text of Southland Renda JV v. Xylem Water Solutions, U.S.A., Inc. (Southland Renda JV v. Xylem Water Solutions, U.S.A., Inc.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southland Renda JV v. Xylem Water Solutions, U.S.A., Inc., (D.S.C. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF SOUTH CAROLINA CHARLESTON DIVISION

SOUTHLAND RENDA JV, ) ) Plaintiff, ) ) No. 2:21-cv-02550-DCN vs. ) ) ORDER XYLEM WATERS SOLUTIONS, U.S.A., ) INC., ) ) Defendant. ) _______________________________________)

The following matter is before the court on defendant Xylem Water Solutions, U.S.A., Inc.’s (“Xylem”) motion for partial summary judgment, ECF No. 45. For the reasons set forth below, the court grants the motion for partial summary judgment. I. BACKGROUND This case arises from a contract dispute between a contractor and subcontractor for the Charleston Water System (“CWS”) sewer system improvements to the West Ashley Tunnel portion. ECF No. 1-1, Compl. ¶ 5. CWS contracted with Southland Renda JV (“Southland”) to complete the tunnel. Id. In support of that work, Southland subcontracted with Xylem to purchase pump design services, five model 3400 415- horsepower submersible pumps (the “pumps”), a variety of supporting materials and equipment, various startup and maintenance services related to installation and operation of the pumps, and other similar services and materials including a detailed engineering analysis.1 Id. ¶ 6. The subcontract was for a price of $999,500 and “stipulated that time

1 The Purchase Order—which the parties refer to as the subcontract—is available as an attachment to Xylem’s answer, ECF No. 14-1, and amended answer, ECF No. 17-1. It is also available as an attachment to Xylem’s motion for partial summary judgment. was of critical importance under the Subcontract.” Id. Xylem allegedly failed to perform according to the terms of the subcontract by using non-compliant pumps that required multiple repairs and had issues with installation which caused a seventy-four day “critical path delay” to Southland’s work on the project which resulted in damages of an amount

not less than $1,792,982.78. Id. ¶ 7. Pursuant to the terms of the subcontract, Southland withheld payment of $543,408.152 to offset Southland’s damages. Id. ¶ 8. This lawsuit followed. On July 23, 2021, Southland filed a complaint against Xylem in the Charleston County Court of Common Pleas alleging breach of contract and breach of implied warranties. ECF No. 1-1, Compl. On August 10, 2021, Xylem removed the case to federal court pursuant to 28 U.S.C. §§ 1332(a), 1441. ECF No. 1. On August 25, 2021, Xylem filed its answer to the complaint and counterclaim for breach of contract against Southland and amended its answer and counterclaim the following day on August 26, 2023.3 ECF Nos. 14, 17. Southland answered Xylem’s second counterclaim on

September 15, 2021, ECF No. 24, and filed an amended answer to the first counterclaim

ECF No. 45-2. Additionally, the parties agreed that Attachment “A” was a part of the contract, which is also written on the fully executed purchase order, and available at ECF No. 45-3. The court will reference the subcontract attached to the motion to dismiss, ECF Nos. 45-2, because that attachment includes the fully executed and signed purchase order as well as the fully executed and signed modification to the purchase order. 2 Xylem argues that Southland wrongfully withheld $758,300.15 which includes the $543,408.15 described by Southland along with a missed milestone billing and for sales taxes, which Xylem avers it is entitled to be paid under the purchase order. ECF No. 17, Amend. Answer ¶¶ 8, 29. 3 As far as the court can tell, the key amendment related to the amount Xylem alleges that Southland owes it. In the first counterclaim Xylem sought $668.345.15 less an amount for Southland’s assistance switching out the pumps, ECF No. 14 ¶ 29, whereas in the amended counterclaim Xylem seeks $758,300.15 less that same amount, ECF No. 17 ¶ 29. on October 21, 2021, ECF No. 26. On January 13, 2023, Xylem filed a motion for partial summary judgment. ECF No. 45. Southland responded in opposition on January 27, 2023, ECF No. 46, and Xylem replied on February 3, 2023, ECF No. 48. As such, the motion has been fully briefed and is now ripe for review.

II. STANDARD Summary judgment shall be granted if the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine dispute as to any material fact and that the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(c). “By its very terms, this standard provides that the mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247–48 (1986). “Only disputes over facts that might affect the outcome of the suit under the governing law will properly preclude the entry of summary judgment.” Id. at 248. “[S]ummary

judgment will not lie if the dispute about a material fact is ‘genuine,’ that is, if the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Id. “[A]t the summary judgment stage the judge’s function is not himself to weigh the evidence and determine the truth of the matter but to determine whether there is a genuine issue for trial.” Id. at 249. The court should view the evidence in the light most favorable to the non-moving party and draw all inferences in its favor. Id. at 255. III. DISCUSSION Xylem seeks partial summary judgment confirming it is owed a contract balance of $756,644.37 (the “contract balance”) pursuant to the express terms of the purchase order. ECF No. 45 ¶ 5. In explanation, that amount arises from the contract price of $999,500 plus sales tax of $88,299.224—totaling $1,087,799.22—for which Southland has issued only one payment to Xylem of $331,154.85. Id. ¶ 4. Xylem claims that it is entitled to apply its contract balance as a setoff against any amount the jury may

determine Xylem owes to Southland for the alleged project delays. Id. ¶ 6. If partial summary judgment is granted, “the remaining issue to be tried will be what, if any damages, Southland can prove it suffered.” ECF No. 48 at 1–2. Southland disputes this claim and argues that since Xylem did not create invoices for taxes for over six years and because it failed to invoice its final payment for over two years, there exists a question of fact about whether Xylem has waived its claims related to these invoices. ECF No. 46 ¶ 1. Additionally, Southland argues that Xylem committed a prior material breach because Xylem took over two years to complete a project that required performance within twenty-two weeks. Id. Xylem contests Southland’s conclusions by indicating there is no evidence of intentional waiver because it has

invoiced Southland for the full amount due notwithstanding the allegedly delayed contract. ECF No. 48 at 2. Additionally, Xylem disagrees with Southland’s interpretation of prior material breach requiring forfeiture of all monies owed to Xylem— instead it argues that the law provides that Southland may recoup damages from the breach as an offset of the total money owed, which should not impact the total contract price at issue in the motion for partial summary judgment. Id.

4 Xylem reaches this number by applying the sales tax rates for the respective periods. ECF No. 45-1 at 3. Specifically, the 2015 invoice was subject to an 8.5 percent sales tax rate. Id. The sales tax applicable for the invoices filed between October 2019 and March 2021 was 9 percent. Id. at 3–4. In total, the total sales tax due on the purchase order comes to $88,299.22. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Monster Daddy, LLC v. Monster Cable Products, Inc.
483 F. App'x 831 (Fourth Circuit, 2012)
Diamond Swimming Pool Co. v. Broome
166 S.E.2d 308 (Supreme Court of South Carolina, 1969)
Lyles v. BMI, Inc.
355 S.E.2d 282 (Court of Appeals of South Carolina, 1987)
Lawrimore v. American Health & Life Insurance
276 S.E.2d 296 (Supreme Court of South Carolina, 1981)
Bonnette v. State
282 S.E.2d 597 (Supreme Court of South Carolina, 1981)
Clardy v. BODOLOSKY
679 S.E.2d 527 (Court of Appeals of South Carolina, 2009)
Schulmeyer v. State Farm Fire & Casualty Co.
579 S.E.2d 132 (Supreme Court of South Carolina, 2003)
Ellis v. Taylor
449 S.E.2d 487 (Supreme Court of South Carolina, 1994)
Ellie, Inc. v. Miccichi
594 S.E.2d 485 (Court of Appeals of South Carolina, 2004)
Strickland v. Strickland
650 S.E.2d 465 (Supreme Court of South Carolina, 2007)
Coastal Seafood Co. v. Alcoa South Carolina, Inc.
381 S.E.2d 502 (Court of Appeals of South Carolina, 1989)
Pee Dee Stores, Inc. v. Doyle
672 S.E.2d 799 (Court of Appeals of South Carolina, 2009)
Janasik v. Fairway Oaks Villas Horizontal Property Regime
415 S.E.2d 384 (Supreme Court of South Carolina, 1992)
Madren v. Bradford
661 S.E.2d 390 (Court of Appeals of South Carolina, 2008)
General Sprinkler Corp. v. Loris Industrial Developers, Inc.
271 F. Supp. 551 (D. South Carolina, 1967)
Wallace v. Day
700 S.E.2d 446 (Court of Appeals of South Carolina, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Southland Renda JV v. Xylem Water Solutions, U.S.A., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/southland-renda-jv-v-xylem-water-solutions-usa-inc-scd-2023.