Zemp Const. Co. v. HARMON BROS. CONST. CO.

82 S.E.2d 531, 225 S.C. 361, 1954 S.C. LEXIS 50
CourtSupreme Court of South Carolina
DecidedJune 2, 1954
Docket16876
StatusPublished
Cited by9 cases

This text of 82 S.E.2d 531 (Zemp Const. Co. v. HARMON BROS. CONST. CO.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zemp Const. Co. v. HARMON BROS. CONST. CO., 82 S.E.2d 531, 225 S.C. 361, 1954 S.C. LEXIS 50 (S.C. 1954).

Opinion

Brailseord, Acting Associate Justice.

This is an appeal by Harmon Brothers Construction Company and its surety, National Surety Corporation of New York, from a judgment for $4,000 recovered against them by Zemp Construction Company.

The controversy arose out of the construction of five motor storage garages at National Guard Armories in South Carolina. The prime contract was between appellant Harmon Brothers Construction Company and the Government of the United States. In brief, this contract provided for the construction of five garages for the sum of $23,799 each, to *363 be paid in monthly instalments as the work progressed. Appellant sub-let the construction of three of the garages to respondent Zemp Construction Company. The written agreement between these parties (not included in the record on appeal) apparently consisted of a proposal and acceptance, which simply provided that respondent would construct three of the garages, according to the specifications of the prime contract, in consideration of the payment by appellant of $21,500 each.

Construction was commenced by respondent about June 1, 1948. Bills for materials purchased were sent directly to appellant and paid by it. Some comparatively small items were purchased for cash by respondent.

On July 9th appellant made an advance of $1,000 to respondent and two weeks later made an advance of $800. These two advances were followed by four consecutive weekly payments, the last of which was made on August 12, 1948. These advances or partial payments, which aggregated $6,-300, were apparently made on the oral requests of Mr. Zemp, president of the respondent corporation. Further advances were requested and refused. Respondent ceased work and all five of the garages covered by the prime contract were completed by appellant.

The complaint alleges that appellant’s failure to make further advances, although “heavily indebted” to respondent, was a violation of the “sub-contract and the agreements thereunder” after which a new agreement was made between the partiés, in substance:

That appellant would complete the construction, using and employing respondent’s workmen, machinery and equipment ; and

That appellant would reimburse respondent for all labor and other costs paid by it, pay to respondent a reasonable rental for its machinery and equipment, and pay to respondent the amount due it under the sub-contract at the time the new arrangement was made.

*364 The complaint claims the sum of $6,651.06 to be due appellant under the “sub-contract and the agreements, terms and conditions thereunder”.

The answer denies that there was any agreement between the parties except the original sub-contract and alleges that appellant was forced to complete the garages at a loss to itself when respondent, without justification, abandoned the construction.

Three of the exceptions impute error to the Circuit Judge in failing to direct a verdict for the defendants or to order judgment for them notwithstanding the verdict. In considering these exceptions this Court is confined to the sole issue of whether it was error to refuse appellants’ motion for the direction of a verdict on the ground on which such motion was rested at the trial. Bohumir Kryl Symphony Band v. Allen University, 196 S. C. 173, 12 S. E. (2d) 712. Thomas v. Atlantic Coast Line Ry. Co., 221 S. C. 462, 71 S. E. (2d) 403. We quote the motion for the direction of a verdict:

“If your Honor pleases, the defendants at this time move for a directed verdict in their favor, upon the ground that there is not sufficient evidence upon which a jury could find that there was any contract, which Mr. Harmon made with Mr. Zemp, and which Mr. Harmon violated.”

As already pointed out, the written contract between the parties simply called for the construction of three garages by respondent for a fixed price. Early in Mr. Zemp’s testimony, he was asked to state the agreement between the parties as to when payments on the contract price would be made. This was objected to upon the ground that such testimony would vary the terms of the contract, which contemplated payment on completion.

The able presiding Judge ruled that testimony as to such an agreement was competent, since the written contract only fixed the total consideration and was silent as to when it should be paid. The correctness of this ruling is not before us because no exception was taken to it.

*365 It follows that the question of whether there was “sufficient evidence upon which a jury could find that there was any contract * * * which Mr. Harmon violated” must be considered in the light of the testimony on this point. It is susceptible of these inferences:

Appellant knew that respondent had very little capital to invest in the jobs and agreed to pay for materials and to make periodic advances to respondent as the work progressed. Although there was no specific agreement as to when such advances were to be made nor upon what evidence, the parties adopted the practice of weekly advances on requests of Mr. Zemp. When further payment was finally refused it was not for the reason that request therefor was premature. According to Mr. Zemp, he was put off for approximately one week on the ground that appellant was short of funds, before being told that payment was withheld because appellant did not know whether the amount of work claimed had been done.

Respondent claims to have had $8,600 invested in the construction, not including such items as equipment used, transportation and overhead and supervisory expense, at the time of this refusal.

Mr. Zemp testified that the appellant “had a large margin in the job” and that advances were never requested for “over 60% of what was due”.

Estimates submitted to the Government by appellant and approved by it indicated that as of the 1st of August the three garages covered by the sub-contract were fifty-two per cent complete. While this estimate included materials on the site, the average cost of these for the completed garages was only $11,547.10 (according to appellant’s auditor) and Mr. Harmon testified that “not near all” had been purchased when appellant took over the work several weeks after the estimate had been submitted.

*366 Without further comment on the evidence, we think that it presented a jury issue as to whether there was an agreement between the parties as to advance payments and whether such agreement was violated by appellant.

“The failure to pay an instalment of the contract price as provided in a building or construction contract is a substantial breach of the contract, and gives the contractor the right to consider the contract at an end, to cease work, and to recover the value of the work already performed.” 9 American Jurisprudence, page 53. See Annotation: Ann. Cas. 1916 C 54.

There is an additional reason why it was proper to overrule the motion for the direction of a verdict.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silver v. Aabstract Pools & Spas, Inc.
658 S.E.2d 539 (Court of Appeals of South Carolina, 2008)
Ingle v. Kuszmaul
Court of Appeals of South Carolina, 2005
State v. Gulledge
487 S.E.2d 590 (Supreme Court of South Carolina, 1997)
Beckham v. Short
365 S.E.2d 42 (Court of Appeals of South Carolina, 1988)
Butler v. Sea Pines Plantation Co.
317 S.E.2d 464 (Court of Appeals of South Carolina, 1984)
M & W Masonry Construction, Inc. v. Head
562 P.2d 957 (Court of Civil Appeals of Oklahoma, 1977)
Easler v. Pappas
166 S.E.2d 808 (Supreme Court of South Carolina, 1969)
Brown v. Carmanni
110 S.E.2d 543 (Court of Appeals of Georgia, 1959)
Wynn v. Coney
102 S.E.2d 209 (Supreme Court of South Carolina, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
82 S.E.2d 531, 225 S.C. 361, 1954 S.C. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zemp-const-co-v-harmon-bros-const-co-sc-1954.