Silver v. Aabstract Pools & Spas, Inc.

658 S.E.2d 539, 376 S.C. 585, 2008 S.C. App. LEXIS 13
CourtCourt of Appeals of South Carolina
DecidedJanuary 16, 2008
Docket4334
StatusPublished
Cited by35 cases

This text of 658 S.E.2d 539 (Silver v. Aabstract Pools & Spas, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Silver v. Aabstract Pools & Spas, Inc., 658 S.E.2d 539, 376 S.C. 585, 2008 S.C. App. LEXIS 13 (S.C. Ct. App. 2008).

Opinion

HEARN, C.J.:

Randy Silver (Homeowner) brought an action against Aabstract Pools and Spas, Inc. (Contractor) for breach of contract and conversion. Contractor asserted affirmative defenses and counterclaimed for breach of contract and attorneys’ fees. With the consent of the parties, the circuit court referred the *588 matter to the Master-in-Equity who concluded the payment provisions of the contract were ambiguous. The master ruled in favor of Homeowner on the breach of contract claim and awarded him compensatory damages of $30,000. Contractor appeals. We reverse and remand.

FACTS

On April 11, 2002, Contractor and Homeowner 1 executed a five-page contract requiring Contractor to construct and install a swimming pool, spa, and water feature at Homeowner’s residence for a price of $69,742. The parties’ contract contained five labeled sections: (1) General Specifications: duties Contractor was required to perform; (2) Miscellaneous: duties Homeowner was required to perform, including excavating rock, hauling dirt, masonry work, landscaping, etc; (3) Payment: Homeowner was required to make five separate payments to Contractor upon completion of five corresponding tasks; (4) Agreed Conditions: twenty-five (25) specific conditions mutually agreed to by the parties; and (5) Witnesseth: a reiteration of Contractor’s promise to construct the pool and Homeowner’s promise to pay $69,742 “at the five intervals in accordance with the schedule of values.” The parties initialed and dated each page of the contract.

The relevant contract language provides:

Payment:
Time is of the essence, the work progress payments specified shall be the essence of this agreement.
Total contract price
Schedule of values $69,742,00
Deposit due upon signing contract $ 6,974.20
Phase 1 due upon completion of dig $27,896.80
Phase 2 due upon completion of shoot $17,435.50
Phase 4 due upon completion of deck pour $13,948.40
Final due at completion $ 3,487.10
... The cost plus work is due at completion of the item. *589 Agreed Conditions: ... (14) ... If work progress payments are not made in full by the [Homejowner in the amount and in the manner specified in this agreement, all work by Contractor[ ] and his agents will immediately cease and all equipment ... will be removed from the pool site by Contractor.... [Homejowner shall pay to Contractor all reasonable attorney fees & all costs & expenses incurred to collect any sums past due from [HJomeowner including but not limited to all court costs.

Homeowner paid Contractor the deposit on April 11, 2002, as specified. Contractor completed the Phase 1 digging work and, on April 24, 2002, Homeowner paid Contractor the specified payment. Next, Contractor completed the Phase 2 shoot 2 and, on May 16, 2002, Homeowner paid Contractor the specified payment. Contractor then completed the Phase 4 deck pour; however, Homeowner refused to pay Contractor the specified payment of $13,948.

After Homeowner refused to pay Contractor lor his Phase 4 work, their contractual relationship reached an impasse with Homeowner owing Contractor $19,345. 3 Pursuant to paragraph 14 of the Agreed Conditions, Contractor suspended work on the job and removed his equipment from the site. 4 Homeowner made no further payments to Contractor and did not contact him for nine months.

By a letter dated March 13, 2003, Homeowner’s attorney proposed that his client put $18,000 into the attorney’s trust fund for payment to Contractor upon completion of the pool project. Contractor did not accept Homeowner’s offer. *590 Homeowner commenced this action for breach of contract and conversion. Contractor answered, pleading affirmative defenses 5 and asserting a counterclaim for breach of contract and attorneys’ fees.

Following a bench trial, the master concluded the contract language stating Homeowner’s payment obligations under the contract was “at best, ambiguous,” and that any ambiguity must be construed against Contractor, as drafter of the contract. The master entered judgment in favor of Homeowner on the breach of contract claim and awarded compensatory damages of $30,000. The master denied Homeowner’s conversion claim and Contractor’s counterclaim. Subsequently, the master denied Contractor’s motion to reconsider, alter or amend the order. This appeal followed.

STANDARD OF REVIEW

An action to construe a contract is an action at law. Pruitt v. S.C. Med. Malpractice Liability Joint Underwriting Ass’n, 343 S.C. 335, 339, 540 S.E.2d 843, 845 (2001). Likewise, “[a]n action for breach of contract seeking money damages is an action at law.” R & G Constr., Inc., v. Lowcountry Reg’l Transp. Auth., 343 S.C. 424, 430, 540 S.E.2d 113, 117 (Ct.App.2000). When reviewing a judgment made in a law case tried by a master without a jury, the appellate court will not disturb the master’s findings of fact unless the findings are found to be without evidence reasonably supporting them. See Karl Sitte Plumbing Co., Inc. v. Darby Dev. Co. of Columbia, Inc., 295 S.C. 70, 77, 367 S.E.2d 162, 166 (Ct.App.1988). However, “[a] reviewing court is free to decide questions of law with no particular deference to the trial court.” Hunt v. S.C. Forestry Comm’n, 358 S.C. 564, 569, 595 S.E.2d 846, 848-49 (Ct.App.2004).

LAW/ANALYSIS

I. Ambiguity of Contract Language

Contractor first argues it was an error of law for the master to find that the payment terms of the contract were ambiguous. We agree.

*591 “It is a question of law for the court whether the language of a contract is ambiguous.” S.C. Dep’t of Natural Res. v. Town of McClellanville, 345 S.C. 617, 623, 550 S.E.2d 299, 302-03 (2001).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson Discount Housing, LLC v. John M. Hornbeck, III
Court of Appeals of South Carolina, 2026
Mark G. Thompson v. Clay Killian
Supreme Court of South Carolina, 2025
SLF III – Hardeeville, LLC v. RSV – Hardeeville, LLC
Court of Appeals of South Carolina, 2025
Marc K. Knapp v. James Douglas Jenkins, IV
Court of Appeals of South Carolina, 2025
Portrait Homes v. Pennsylvania National Mutual
Court of Appeals of South Carolina, 2023
Gee v. Delta Speir Plantation LLC
390 F. Supp. 3d 645 (D. South Carolina, 2019)
Mears Grp., Inc. v. Kiawah Island Util., Inc.
372 F. Supp. 3d 363 (D. South Carolina, 2019)
Robert Robertson v. Huddle House
Court of Appeals of South Carolina, 2018
In re Devey
590 B.R. 706 (D. South Carolina, 2018)
Le Feather v. White
Court of Appeals of South Carolina, 2018
English v. Sexton
Court of Appeals of South Carolina, 2017
Dudek v. Ferro
Court of Appeals of South Carolina, 2017
Vance v. Horry Electric Cooperative
Court of Appeals of South Carolina, 2016
Bluffton Towne Center, LLC v. Gilleland-Prince
772 S.E.2d 882 (Court of Appeals of South Carolina, 2015)
First National Bank v. Callihan
Court of Appeals of South Carolina, 2015
Williams v. Government Employees Insurance
762 S.E.2d 705 (Supreme Court of South Carolina, 2014)
Xu Dong Sun v. Wang
Court of Appeals of South Carolina, 2014
City of Conway v. Gerald Builders
Court of Appeals of South Carolina, 2013

Cite This Page — Counsel Stack

Bluebook (online)
658 S.E.2d 539, 376 S.C. 585, 2008 S.C. App. LEXIS 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/silver-v-aabstract-pools-spas-inc-scctapp-2008.