Connecticut Carpentry v. Maranba Bldrs., No. Cv 96-0573579s (Jun. 8, 1999)

1999 Conn. Super. Ct. 7106
CourtConnecticut Superior Court
DecidedJune 8, 1999
DocketNo. CV 96-0573579S
StatusUnpublished

This text of 1999 Conn. Super. Ct. 7106 (Connecticut Carpentry v. Maranba Bldrs., No. Cv 96-0573579s (Jun. 8, 1999)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Connecticut Carpentry v. Maranba Bldrs., No. Cv 96-0573579s (Jun. 8, 1999), 1999 Conn. Super. Ct. 7106 (Colo. Ct. App. 1999).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
Plantiff Connecticut Carpentry Corporation ("Connecticut Carpentry") has brought this action to collect the balance due on three separate contracts it had with defendant Maranba Builders, Inc. ("Maranba"). All three contracts required Connecticut Carpentry to perform services and furnish materials as a subcontractor of Maranba. Maranba was operating as the Construction Manager for the Town of Somers for the renovation and conversion of a high school into an elementary school. Under the first contract Connecticut Carpentry was to supply rough carpentry work at the school for the sum of $129,780.00. (Plaintiffs Ex. 1). Under the second contract, Connecticut Carpentry was to provide toilet accessories, Toilet Partitions, and lockers work at the school for the sum of $86,000.00. (Plaintiffs Ex. 7). Under the third contract plaintiff was to provide for the installation of wood and hollow metal doors and hardware at the school for the sum of $23,700.00. (Plaintiffs Ex. 12). Connecticut Carpentry performed all the above mentioned work required under these three contracts.

In addition to performing all the work provided for in the contracts, plaintiff performed additional services when requested to do so by Maranba. This additional work was requested by Maranba representatives job site and memorialized by the plaintiff in the form of written proposals or estimates sent to CT Page 7107 Maranba. Up until the time that Maranba was removed from the project by the town, Maranba provided written change orders for the extra work performed by Connecticut Carpentry.

In addition, Connecticut Carpentry performed extra work at the oral request of Maranba, although Maranba failed or refused to sign written change orders for that extra work.

The following additional work was provided by Connecticut Carpentry at the request of Maranba.

(A) Extra rough carpentry work as follows:

1. Winter protection (change order, Ex. 2) $2,125.00

2. Repair masonry wall (change order, Ex. 3) $2,879.30

3. Additional wood blocking (change order, Ex. 4) $6,942.59

4. Extra soffits and facia on new garage at oral request of Maranba (Ex. 5) $2,102.00

5. Extra work performed at oral request of Maranba (Ex. 6) $17,883.10

$31, 931.99

Numbers 1, 2 and 3 above are all evidenced by change orders signed by George A. Palacko, project manager for Maranba. Numbers 5 and 6 were performed by Connecticut Carpentry at the verbal request of Maranba. Maranba failed and/or refused to sign the change orders for this work even after the work was completed by Connecticut Carpentry.

(B) Extra work re: toilet accessories as follows:

1. Provide toilet partitions in several rooms (change order, Ex. 8) $3,294.75

2. Extra work to accommodate ceiling heights in bathrooms (Ex. 9) $473.00

3. Cost increase for materials added to contract (Ex. 10) $1,403.00 CT Page 7108

4. Extra work performed (Ex. 11) $409.40

$5,580.15

Number 1 above (Ex. 8) is evidenced by a change order signed by George Palacko.

Numbers 2, 3, and 4 were performed by Connecticut Carpentry at the verbal request of Maranba. Maranba failed and/or refused to sign change orders for this work even after the work was completed by Connecticut Carpentry.

(C) Extra work re: metal doors

1. Installed new hardware at boiler room door (change order, Ex. 13) $285.00

2. Added labor for additional hardware (change order, Ex. 14) $170.00

3. Additional 106 hours spent by employees to make adjustments to doors ($45.00 x 106 hrs.) (Ex. 15) $4.770.00

$5,225.00

Numbers 1 and 2 above (Exs. 13 and 14) are evidenced by change orders signed by George Palacko. The hours listed under #3 were performed at the oral request of Maranba. Maranba, however, failed and/or refused to sign change orders even after the work was completed by Connecticut Carpentry.

Thus, under contract #1, the plaintiff claims it was entitled to the following:

For the base contract $129,780.00 For the extras $31,931.99

$161,711.99

Plaintiff has received the following payments: $130,534.35

Leaving a balance due of: $31,177.64 CT Page 7109

Under contract #2, the plaintiff claims it was entitled to the following:

For the base contract $86,000.00 For the extras $5,580.15

$91,580.15

Plaintiff has received: $77,947.50

Leaving a balance due of: $13,632.65

Under contract #3, the plaintiff claims it was entitled to the following:

For the base contract $23,700.00 For the extras $5,225.00

$28,925.00

Plaintiff has received: $9,647.25

Leaving a balance due of: $19,277.75

Thus, in summary, plaintiff claims that it is owed: B$64,088.04

The court finds that the plaintiff did in fact provide all the work as required under the base contracts. Additionally, it performed all the extra work requested by Maranba as evidenced by the change orders. It also further provided all the extra work orally requested by Maranba, although Maranba failed or refused to sign change orders even after the work was completed by Connecticut Carpentry.

Maranba claims it is not liable for any of the requested payments, and it raises several issues which the court will address.

First: Maranba claims that some of the work was not performed in a workmanlike manner. After hearing all the evidence, the court disagrees.

There was a claim that the work performed by Connecticut CT Page 7110 Carpentry on a roof was flawed. However, Maranba failed to prove that Connecticut Carpentry's work was in any way flawed. Any flaws found with the roof were caused by the work of New Britain Roofing, and not Connecticut Carpentry. Nor did the defendant prove that any other work was performed by Connecticut Carpentry in a less than workmanlike manner.

Second, Maranba claims it is not liable for the requested payments because the "pay when paid" clauses in the three contracts were a condition precedent to Maranba's obligations to pay the plaintiff. The court disagrees. ""Where a debt has arisen, liability will not be excused because, without fault of the creditor and due to happenings beyond his control, the time for payment, as fixed by the contract, can never arrive . . .' "DeCarlo Doll. Inc. v. Dilozir, 45 Conn. App. 633, 642 (1997) citing Restaurants, Contracts, § 301; Williston Contracts, § 799. The Appellate Court in DeCarlo held that where a "pay when paid" clause was in the control of the defendant, he could not be excused for nonperformance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Von Langendorff v. Riordan
163 A.2d 100 (Supreme Court of Connecticut, 1960)
Wexler Construction Co. v. Housing Authority
128 A.2d 540 (Supreme Court of Connecticut, 1956)
Bolmer v. Kocet
507 A.2d 129 (Connecticut Appellate Court, 1986)
Ayotte Bros. Construction Co. v. Finney
680 A.2d 330 (Connecticut Appellate Court, 1996)
DeCarlo & Doll, Inc. v. Dilozir
698 A.2d 318 (Connecticut Appellate Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
1999 Conn. Super. Ct. 7106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/connecticut-carpentry-v-maranba-bldrs-no-cv-96-0573579s-jun-8-1999-connsuperct-1999.