Blakeslee v. Board of Water Commissioners

183 A. 887, 121 Conn. 163, 1936 Conn. LEXIS 106
CourtSupreme Court of Connecticut
DecidedFebruary 5, 1936
StatusPublished
Cited by45 cases

This text of 183 A. 887 (Blakeslee v. Board of Water Commissioners) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blakeslee v. Board of Water Commissioners, 183 A. 887, 121 Conn. 163, 1936 Conn. LEXIS 106 (Colo. 1936).

Opinion

Maltbie, C. J.

Early in the century plans began to be developed by the defendant board of water commissioners to provide an additional water supply for the city of Hartford. As matured they involved the construction of a large reservoir system which would impound the waters of two streams tributary to the Farmington River. This might injuriously affect the owners of certain mill and power sites upon the river, and an agreement was made with them in accordance with which, under specific legislative authority, the board was to construct upon another tributary of the river a compensating reservoir which would be so operated as to equalize the flow of the river. 16 Special Laws, p. 390. The contract to construct the dam for this reservoir was duly awarded to the plaintiffs by the board, and was signed August 23d, 1915. They began work under the contract and were carrying it on when this country became a participant in the world war. The costs of material and labor had at that time advanced and were advancing very rapidly, due to war conditions, and the plaintiffs encountered serious difficulties in procuring them. The basis of their claim in this action as stated in their complaint is that, confronted with these difficulties, which were not and could not have been foreseen when the contract was made, they notified the defendant that it would be impossible to continue the work at the prices specified in the contract; that the defendant agreed with the plaintiffs that if they proceeded with the work the defendant would waive the penalties which were fixed in the contract for a failure to complete it within the time specified and that, if proper legislative *168 authority could be secured, the defendant would do all in its power to change the compensation provided in the contract so as to prevent the plaintiffs from suffering any actual loss; that, relying upon this promise and assurance, the plaintiffs did continue with the work; that in 1919, before the completion of the contract, a legislative act was passed (Public Acts, 1919, Chap. 187), under the terms of which payment to the plaintiffs of a sufficient sum to save them from loss was authorized, but that the defendant has refused to pay the plaintiffs’ claim for such loss. To the complaint a demurrer was filed, and from a judgment for the defendant consequent upon the sustaining of that demurrer and the refusal of the plaintiffs to plead over, an appeal was taken to this court. The ruling of the trial court was held to be erroneous and the case remanded for further proceedings. Blakeslee v. Water Commissioners, 106 Conn. 642, 139 Atl. 106. Thereafter the complaint was amended by adding a second count, but a demurrer to this count was sustained. The case was referred to a state referee, who, after extended hearings, made his report. The defendant filed a remonstrance and has appealed from a judgment for the plaintiffs following the substantial overruling of that remonstrance.

In the remonstrance the defendant attacked several of the findings of the referee and sought many additions to the report. The trial court made certain corrections in and additions to it. Any discussion of the further changes which the appellant now seeks to have made would unduly prolong this opinion, and it must suffice to say that few changes or additions can be made by us which would materially affect the issues of law presented for our determination and those we do make are incorporated in this opinion without specific reference. summarize the principal facts *169 so as to present in general the issues of law, leaving, however, certain elements in the case for discussion in connection with the claims of the parties. At all times during the progress of the work upon the compensating reservoir it was urgently important that it should be completed and ready for operation as soon as possible under existing conditions. Before July 17th, 1917, Caleb M. Saville was chief engineer in charge of the work, but on that day was appointed manager under an ordinance of the city directing the board to appoint such an official, to have charge, subject to its orders and instructions, of the engineering, construction and management of the water system, and to perform such other duties as might be imposed upon him by the board. Revised Ordinances of Hartford, 1920, § 280. The plaintiffs commenced work under the contract awarded to them about September 1st, 1915, and proceeded in a satisfactory manner until the summer of 1916. Beginning at that time, due to general conditions in the labor market, the plaintiffs began to encounter difficulties in procuring labor, and their difficulties in that respect increased; and it also became very difficult for them to secure necessary materials due to conditions produced by the war abroad and eventually by the entry of this country into it. Under these circumstances and with the prospect of their indefinite continuance, the plaintiffs, after repeated discussions among themselves, reached the conclusion that they were within their rights in shutting down the work while the war continued.

In September, 1917, one of the plaintiffs, Clarence Blakeslee, held two conferences with Saville. Blakeslee told Saville that the plaintiffs had decided to stop work unless assured of two things, that the clause in the contract providing a penalty for failure to complete the work within the time specified would be *170 waived, and that the board would reimburse the plaintiffs for the additional costs of continuing the work arising out of war conditions. The first requirement met little opposition, but as to the second Saville pointed out that the board had no power to increase the plaintiffs’ compensation as fixed by the contract. The possibility of enabling legislation was discussed and the first conference ended with the understanding that Saville would take the matters up with the board and report to Blakeslee. At the second conference some days later, Saville reported that the board would agree to waive the penalty clause, that the reimbursement of additional war costs was a more difficult matter; but that if the plaintiffs would continue and complete the work at contract prices, the board would agree to make such reimbursement if and when it was legally empowered to do so. Relying on the assurance so given, the plaintiffs did continue with the work but at great additional cost beyond the prices fixed in. the contract.

In September, 1918, the plaintiffs, compelled by the increasing , cost to borrow large sums of money to meet current expenses, sought from the board an increase ■in the unit prices for the different types of work specified in the contract, but upon advice of counsel that the board would not be justified in entering into any new arrangement with them, it refused their request. Thereafter an act which could authorize the board to pay to the plaintiffs the costs incurred by them as a result of war conditions beyond the contract price agreed upon for the construction of the dam, and in the'preparation of which counsel for the board collaborated, passed the Legislature and was approved May 2d, 1919. Public, Acts, 1919, Chap. 187. The plaintiffs, having completed the contract in February, 1920, presented to the board ,a statement of such costs. *171 The board referred the statement to Saville with directions to investigate and report.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooke v. Shapiro
D. Connecticut, 2023
Zeigler v. Sony Corp. of America
849 A.2d 19 (Connecticut Superior Court, 2004)
Willow Funding Co., L.P. v. Grencom Associates
779 A.2d 174 (Connecticut Appellate Court, 2001)
Truhe v. Turnac Group, L.L.C.
1999 SD 118 (South Dakota Supreme Court, 1999)
Sandella v. Dick Corp.
729 A.2d 813 (Connecticut Appellate Court, 1999)
Desalle v. A-1 Sign Company, No. Cv91 028 42 S (Aug. 11, 1998)
1998 Conn. Super. Ct. 8727 (Connecticut Superior Court, 1998)
Landscape Mgmt. Ser. v. Farmington Plaza, No. Cv94-0539633s (Sep. 18, 1996)
1996 Conn. Super. Ct. 5331 (Connecticut Superior Court, 1996)
Keeney v. Town of Old Saybrook
676 A.2d 795 (Supreme Court of Connecticut, 1996)
General Acc. Ins. v. J. Fontana Contr., No. Cv 930352475s (Oct. 31, 1995)
1995 Conn. Super. Ct. 12203 (Connecticut Superior Court, 1995)
Bauco v. Dominello, No. Cv 92 0333175s (May 18, 1995)
1995 Conn. Super. Ct. 5645 (Connecticut Superior Court, 1995)
Smith v. J-Mar Builders, Inc., No. Cv94-0246605 (Mar. 14, 1995)
1995 Conn. Super. Ct. 2063 (Connecticut Superior Court, 1995)
Lapuk v. Simons, No. Pjr Cv93 0704542s (Jan. 3, 1995)
1995 Conn. Super. Ct. 225-V (Connecticut Superior Court, 1995)
Muldoon v. Homestead Insulation Co.
650 A.2d 1240 (Supreme Court of Connecticut, 1994)
Kelly v. Anderson Ridge Associates, No. 29 98 85 (Aug. 15, 1994)
1994 Conn. Super. Ct. 8145 (Connecticut Superior Court, 1994)
Scarpa v. Casner, No. 69106 (May 17, 1994)
1994 Conn. Super. Ct. 5330 (Connecticut Superior Court, 1994)
A.D.C. Constr. Co. v. Millstone, Inc., No. Cv90-0700782-S (Feb. 14, 1994)
1994 Conn. Super. Ct. 1333 (Connecticut Superior Court, 1994)
Pds Engineering Const. v. Double Rs, No. Cv90-0378684 (Dec. 19, 1991)
1991 Conn. Super. Ct. 10306 (Connecticut Superior Court, 1991)
Okee Industries v. E. Building Con., No. Cv-89-700585 (Dec. 17, 1990)
1990 Conn. Super. Ct. 4785 (Connecticut Superior Court, 1990)
Petrucci Construction Co. v. Leepson, No. 23 26 48 (Sep. 13, 1990)
1990 Conn. Super. Ct. 1772 (Connecticut Superior Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
183 A. 887, 121 Conn. 163, 1936 Conn. LEXIS 106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blakeslee-v-board-of-water-commissioners-conn-1936.