Opdyke & Butler v. Silver

245 P.2d 306, 111 Cal. App. 2d 912, 1952 Cal. App. LEXIS 1314
California Court of Appeal·Decided June 23, 1952·No. Civ. 8120·Published·Cited by 10 cases

Opinion

VAN DYKE, J.

Respondents, a copartnership, as plaintiffs, brought this action against appellant to recover an alleged balance due upon an oral contract. They alleged that on March 15, 1950, they entered into a written contract with appellant to do certain construction work in the remodeling of a building. They next alleged that on the same day and by mutual oral agreement the written contract was abandoned, and that the parties thereupon orally agreed upon the terms of a new contract; that they then adopted new plans and specifications to designate the work to be performed under the oral agreement and that respondents’ compensation was to *913 be on the basis of cost plus 10 per cent. Further alleging that cost of the completed work, plus 10 per cent, amounted to $24,253.79' and that only $17,652.38 had been paid, they prayed judgment for the difference. Appellant answered, admitting that the written contract had been entered into and that the compensation thereunder had been cost of the completed work, plus 10 per cent, but appellant alleged that the written contract provided for a maximum limit as to cost of $15,900. He denied that this contract had been abandoned and alleged that all the work that had been done by respondents had been done pursuant to it and under plans and specifications made a part of it. The controversy between the parties centered around this matter of the alleged abandonment of the written agreement and the substitution of an oral contract in lieu thereof. The trial court found that on March 15, 1950, the parties had entered into a written contract and that under it respondents were to perform certain construction work for appellant at cost plus 10 per cent, with total cost not to exceed $15,900; that on the same day and by mutual oral agreement the written contract was abandoned, new plans and specifications were prepared, orders for new and different work were given to respondents and that the parties orally agreed upon a new contract whereby the work was to be done in conformity with the new plans and specifications and the new orders at cost plus 10 per cent, without a maximum limit; that the work had been done, and that the difference between the amount paid and the. amount earned amounted to $6,-600.52. Judgment accordingly followed.

It is not disputed that on the date alleged a written contract was entered into; that plans and specifications as drawn by an architect were, made a part of it and that the contract so .executed was full and complete as a construction contract. It contained the usual provisions for supervision of the work by the architect as the work progressed, for the making of progress payments based upon statements for labor and materials incorporated in the work, furnished by the contractor from time to time and approved by the architect. Appellant was given the contractual right to order changes in the work, - the contract price to be adjusted accordingly but it was stipulated that all such orders' and adjustments should be in writing and that claims for extra cost must be made in writing before executing the work involved. It is appellant’s contention that although numerous and material changes were made in the work to be done by respondents during the course *914 of construction, beginning quite early in the history of the work, yet that these changes were made under the written contract; that though they may have justified claims for extra cost neither these changes nor anything else occurring worked an abandonment of the written contract and the mutual adoption of an oral contract. Appellant, therefore, argues that respondents’ recovery would have to be in accordance with the written contract limited by the maximum price save for allowable extras, less allowable deductions, where changes worked a saving. Appellant argues further that, there being no support in the record for the court’s finding of abandonment of the written agreement, it results that the proof made by respondents was wholly inadequate to support findings or judgment, since it consisted of a running account of work done and material installed by respondents and their subcontractors without consideration of the maximum price. On the contrary, respondents contend, in line with the findings and judgment of the trial court, that the written contract was abandoned, that the oral contract substituted therefor contained no maximum nor other contract price save cost of labor and material plus 10 per cent and that, therefore, it was proper to prove the amount earned and unpaid by the introduction of their ledger account of such cost of labor and material.

Free access — add to your briefcase to read the full text and ask questions with AI

Opdyke & Butler v. Silver, 245 P.2d 306, 111 Cal. App. 2d 912, 1952 Cal. App. LEXIS 1314 (Cal. Ct. App. 1952).

245 P.2d 306 (Opdyke & Butler v. Silver) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bohm v. Horsley Co. (In Re Groggel)
333 B.R. 261 (W.D. Pennsylvania, 2005)
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
Amelco Electric v. City of Thousand Oaks
98 Cal. Rptr. 2d 159 (California Court of Appeal, 2000)
C. Norman Peterson Co. v. Container Corp. of America
172 Cal. App. 3d 628 (California Court of Appeal, 1985)
Lipson v. Adelson
456 N.E.2d 470 (Massachusetts Appeals Court, 1983)
Pallardy v. Link's Landing, Inc.
536 S.W.2d 512 (Missouri Court of Appeals, 1976)
Daugherty Co. v. Kimberly-Clark Corp.
14 Cal. App. 3d 151 (California Court of Appeal, 1971)
Connersville Country Club v. F. N. Bunzendahl, Inc.
222 N.E.2d 417 (Indiana Court of Appeals, 1967)