Connersville Country Club v. F. N. Bunzendahl, Inc.

222 N.E.2d 417, 140 Ind. App. 215
CourtIndiana Court of Appeals
DecidedJanuary 24, 1967
Docket20,250
StatusPublished
Cited by10 cases

This text of 222 N.E.2d 417 (Connersville Country Club v. F. N. Bunzendahl, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Connersville Country Club v. F. N. Bunzendahl, Inc., 222 N.E.2d 417, 140 Ind. App. 215 (Ind. Ct. App. 1967).

Opinion

Bierly, J.

— This action arose out of a contract whereby appellee was to provide certain earth-moving equipment and labor which was to be used in the construction of a second nine hole golf course at the appellant’s club. The contract in question, among other things provided:

“. . . Regardless of the cost thereof to said F. N. Bunzendahl, Inc., no cost to Connersville Country Dlub [sic] shall exceed the maximum payment by Connersville Country Club as hereinafter provided.
“In consideration thereof, Connersville Country Club agrees to pay F. N. Bunzendahl, Inc., a minimum sum of Twenty Thousand ($20,000.00) Dollars and in no event more than Twenty-Five Thousand ($25,000.00) Dollars.”

*217 Following this above passage, the contract specifies the rates to be charged for the various pieces of equipment and the procedure to be followed in billing. At the conclusion of the billing section of the contract, the following language relating to the minimum-maximum is again found.

“. . . When said 9 hole golf .course is completed, said Connersville Country Club shall pay the 10% remaining unpaid on said billing within 30 days, subject to the limitation that all of said payments made to F. N. Bunzendahl, Inc., shall never exceed the sum of $25,000.00. In the event said billing shall be less than the sum of $20,000, said F. N. Bunzendahl, Inc., shall be paid a sum sufficient to constitute the total payment of $20,000.00 at the time of the last payment as herein provided.”

The complaint, filed by the appellee in the trial court is entitled:

“Complaint To Foreclose Mechanic’s Lien And for Damages.”

Contained therein are four separate paragraphs, the first of which we must take particular notice, for it is on this paragraph alone that the trial court entered its judgment. Within said paragraph it is alleged that the appellant, sometime prior to March 30, 1962, had employed Robert Simmons as an Architect-Supervisor to design and supervise the construction of the new nine hole golf course. That prior to March 30, 1962, Robert Simmons prepared plans of the new nine hole golf course, showing the location, length and physical features of each of the nine holes. That on March 30, 1962, the appellant and appellee entered into a written, contract, which contained, among other things, a provision that the appellee receive a minimum of $20,000.00, and a maximum of $25,000.00, for the use of certain equipment and labor. Pursuant to said contract, the appellee began to furnish said equipment and labor, but shortly thereafter, the appellant made certain changes and alterations in the construction plans of the nine hole golf course in many different ways. *218 That the Appellant made payments to the appellee, but appellee contended that there remained due and owing the sum of $17,249.41, for the use of equipment and for labor furnished by the appellee at the appellant’s special instance and request. Said amount has been demanded by appellee, but refused by appellant, and that by reasons of the long and unreasonable delay, appellee alleges it is entitled to interest thereon from August 29, 1962, until the date of payment. Appellee further alleged that on September 18, 1962, and within sixty days from the time said equipment and labor was furnished, appellee filed its notice of intention to hold a mechanic’s lien on the property in question. In addition, appellee prays for the recovéry of a reasonable attorney fee in the amount of $2500.00. The final rhetorical paragraph submitted a demand for $17,249.41, with 6% interest, attorney fees of $2500.00, and foreclosure of the mechanic’s lien.

The appellee’s second paragraph of complaint proceeded upon the theory of quantum meruit for recovery of the reasonable value of the equipment provided in excess of the contract maximum on the theory that the contract had been abandoned.

The third paragraph of complaint alleges a breach of the written contract and seeks damages arising from that breach, while the fourth paragraph alleges that the appellant did not return one of the pieces of equipment, which was rented to it under the contract, in good condition and thereby seeking damages in the amount of its diminished value less normal depreciation.

The trial court found for the appellee on paragraph one of its complaint, but failed to find for either party on paragraphs two, three and four of said complaint. Judgment was entered by the court for $19,398.81, and foreclosure of the mechanic’s lien.

*219 The court, having heard the evidence, argument of counsel, and having taken the cause under advisement, among his several findings stated:

“. . . and the Court, being now fully advised in the premises, now finds for the plaintiff on its first paragraph of complaint against the above defendant, and that the material allegations thereof have been proven and are true.”

The salient features of the court’s decree and judgment follows:

“IT IS FURTHER ORDERED, ADJUDGED AND DECREED by the Court that thereafter plaintiff entered into the performance of said contract but that from time to time thereafter defendant made certain changes, additions and alterations in the construction of said additional nine-hole golf course different and as additions to the original plans therefor.
“IT IS FURTHER ORDERED, ADJUDGED AND DECREED by the Court that the above plaintiff, pursuant to said written agreement, and as modified and changed by defendant as aforesaid, did furnish the earth moving equipment, operators therefor, and the other equipment and materials required of it by the above defendant in the construction of said additional nine-hole golf course on said above described real estate.
“IT IS FURTHER ORDERED, ADJUDGED AND DECREED by the Court that the work and labor so performed by plaintiff as aforesaid and the use of plaintiff’s machinery and materials in the construction of said additional nine-hole golf course on defendant’s above described real estate constituted the construction by the plaintiff of valuable, permanent and lasting improvements to defendant’s above described real estate.
“IT IS FURTHER ORDERED, ADJUDGED AND DECREED by the Court that defendant made partial payment to plaintiff on said contract, as modified as aforesaid, but that there remains due and owing to plaintiff from defendant for and on account of the earth moving equipment, labor performed by the operators therefor, and for other equipment and materials so furnished by plaintiff to defendant, at defendant’s special instance and request, the *220 sum of Fifteen Thousand Five Hundred Two Dollars and Eight Cents ($15,502.08).
“IT IS FURTHER ORDERED, ADJUDGED AND DECREED by the Court that by reason of long and unreasonable delay in the payment thereof, plaintiff is entitled to interest thereon from the 29th day of August, 1962, at the rate of six per cent (6%) per annum, in the amount of One Thousand Three Hundred Ninety Six Dollars Seventy Three Cents ($1,396.73).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Blakley Corp. v. EFCO Corp.
853 N.E.2d 998 (Indiana Court of Appeals, 2006)
Gorbett v. Claycamp
553 N.E.2d 475 (Indiana Supreme Court, 1990)
Gorbett v. Claycamp
543 N.E.2d 401 (Indiana Court of Appeals, 1989)
Thatcher Engineering Corp. v. Bihlman
473 N.E.2d 1022 (Indiana Court of Appeals, 1985)
Matter of Penn-Dixie Industries, Inc.
22 B.R. 794 (S.D. New York, 1982)
Gorbett v. Estelle
438 N.E.2d 766 (Indiana Court of Appeals, 1982)
Allied Structural Steel Co. v. State
265 N.E.2d 49 (Indiana Court of Appeals, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
222 N.E.2d 417, 140 Ind. App. 215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/connersville-country-club-v-f-n-bunzendahl-inc-indctapp-1967.