C. Norman Peterson Co. v. Container Corp. of America

172 Cal. App. 3d 628, 218 Cal. Rptr. 592, 1985 Cal. App. LEXIS 2550
CourtCalifornia Court of Appeal
DecidedSeptember 26, 1985
DocketA015136
StatusPublished
Cited by23 cases

This text of 172 Cal. App. 3d 628 (C. Norman Peterson Co. v. Container Corp. of America) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. Norman Peterson Co. v. Container Corp. of America, 172 Cal. App. 3d 628, 218 Cal. Rptr. 592, 1985 Cal. App. LEXIS 2550 (Cal. Ct. App. 1985).

Opinion

Opinion

ANDERSON, J. *

This is an action for breach of construction contract and for the reasonable value of labor and materials. Defendant, Container *633 Corporation of America (hereafter CCA or the Owner), appeals from a judgment awarding plaintiff, C. Norman Peterson Co. (hereafter CNP or the Contractor), damages in the amount of $2,898,687.47, plus interest. CNP has cross-appealed. 1

Facts

A. Introduction

In 1976, CCA contracted with CNP for performance of a mill modernization project at CCA’s papermill located in Santa Clara, California. The mill recycles waste paper into carton materials. CCA supplied the major items of equipment, and CNP supplied the labor and materials necessary to enlarge the building and to install new machinery.

Basically, CNP was to complete the project in 18 months. During the first 14 months, the work was to be performed while the papermill was in operation. During the next two months, work was to be performed while the mill was shut down. This shutdown period was the most critical phase of the project; time was of the essence during this period so the mill could be restarted. There was then to be a two-month cleanup period. CCA concedes the project was completed essentially on time, and the court found that CCA paid CNP $5,544,400 for its performance. A dispute arose over additional amounts, CCA eventually acknowledged it owed an additional $500,178, but CNP filed suit on November 28, 1978.

At trial, 2 CNP contended it was entitled to recover its total costs expended in completing the project due to numerous errors and changes in the construction drawings, which resulted in extra work having to be performed by CNP. CCA, while conceding there were many revisions to the drawings, contended that both parties were aware at the outset that revisions would have to be made, that there was no material change in the scope of the work to be performed, and that the contract set forth the procedure for compensation for performing extra work. Following 16 days of hearings, judgment was entered in favor of CNP for $2,898,687.47 plus interest, representing CNP’s total costs expended plus overhead and profit, less receipts.

*634 B. Precontract Period

In early 1976, CCA solicited bids from eight contractors for the modernization of its papermill, based upon drawings prepared for CCA by its engineer, Industrial Mechanical Corporation (hereafter IMC) and its architect, Richard J. Huyck and Associates (hereafter Huyck). These drawings were marked for “bidding purposes only.” CNP submitted a bid and, on April 20, 1976, CCA sent CNP a letter of intent informing CNP that it had been chosen as the general contractor on the project. Work commenced on the project on May 1, 1976, before the execution of a formal written contract on June 10, 1976.

On April 26, 1976, personnel from CNP, CCA and IMC met to review the mechanical drawings for the project. It was agreed that the drawings were then inadequate for construction purposes, but it was necessary to issue them in their then current form so work could begin by May 1. CNP was promised revised drawings within two or three weeks. In early June 1976 CNP asked about the revised drawings. IMC indicated that some would be completed within 30 days, with the remainder to be completed in 60 days. This deadline, too, was missed. As discussed, infra, there were further delays before these drawings were completed.

C. The Contract

On June 10, 1976, the parties entered into a formal written contract, consisting of a general “construction agreement” and a series of more specific “contract documents” (including drawings prepared by the Owner), attached to the construction agreement. According to the trial court’s findings, some of the more relevant parts of the contract provided: (1) that CCA would pay CNP for actual net cost of the work, plus a fee of $300,000 and that CNP guaranteed that such cost plus fee would not exceed $4,789,000; 3 (2) that CNP would proceed with utmost dispatch in its performance, and complete the work as soon as possible but no later than October 18, 1977; time was of the essence with respect to the completion date; 4 (3) that CNP would construct the facility in accordance with the contract documents and *635 the 234 drawings which were attached to and made a part of the contract; 5 and (4) that CCA would reduce the 10 percent retention to 5 percent retention when CNP, in CCA’s opinion, had satisfactorily performed over 50 percent of the contract work. 6

Section 1-04 of the contract’s general conditions provided, in part, that the contract documents were complementary and “are intended to include all items required for the proper execution and completion of the work.” The general conditions and supplemental general conditions contained provisions relating to change orders (supplemental general condition § 1-57.4), claims procedures (id., at § 1-57.5) and the architect’s status in the event of contract or performance disputes (general condition § 1-08).

D. Performance

The contract called for completion of the project by October 18, 1977. The work was, in fact, performed during three distinct phases: (1) from May 1, 1976, through September 6, 1977, preliminary work was performed while the papermaking machines remained in operation; (2) the critical shutdown was completed during the period between September 7, 1977, and November 1, 1977; and (3) the final cleanup phase was completed by January 1, 1978. Although the original completion deadline of October 18, 1977, was not met, CCA concedes that the contract was performed by CNP essentially on time. Further, CCA acknowledges that numerous changes were made during the course of the contract. The dispute ultimately is over the method for determining the costs of those changes.

1. Drawings

(a) Delay in Drawings

The drawings which IMC had promised CNP in early June would be completed within 30-60 days were not finished on time; thereafter there were further delays in their delivery. IMC made further promises (on Aug. 10, 11, Sept. 2, 23 and Nov. 11, 1976), each time pushing the delivery date *636 for the completed drawings back another 30-60 days, with an eventual promised delivery date of January 1, 1977. 7

(b) Drawing Review

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner Construction Co. v. MJ Flaherty Co.
34 Mass. L. Rptr. 171 (Massachusetts Superior Court, Suffolk County, 2017)
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
243 Cal. App. 4th 571 (California Court of Appeal, 2015)
Wong v. Stoler
California Court of Appeal, 2015
Wong v. Stoler CA1/1
237 Cal. App. 4th 1375 (California Court of Appeal, 2015)
Bohm v. Horsley Co. (In Re Groggel)
333 B.R. 261 (W.D. Pennsylvania, 2005)
MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co.
115 P.3d 41 (California Supreme Court, 2005)
J.A. Jones Construction Co. v. Lehrer McGovern Bovis, Inc.
89 P.3d 1009 (Nevada Supreme Court, 2004)
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
Amelco Electric v. City of Thousand Oaks
98 Cal. Rptr. 2d 159 (California Court of Appeal, 2000)
General Motors Corp. v. Northrop Corp.
685 N.E.2d 127 (Indiana Court of Appeals, 1997)
Ben-Zvi v. Edmar Co.
40 Cal. App. 4th 468 (California Court of Appeal, 1995)
LK Comstock & Co., Inc. v. Becon Const. Co., Inc.
932 F. Supp. 906 (E.D. Kentucky, 1993)
CMSH Co., Inc. v. Antelope Development, Inc.
223 Cal. App. 3d 174 (California Court of Appeal, 1990)
Pecaflor Construction, Inc. v. Landes
198 Cal. App. 3d 342 (California Court of Appeal, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
172 Cal. App. 3d 628, 218 Cal. Rptr. 592, 1985 Cal. App. LEXIS 2550, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-norman-peterson-co-v-container-corp-of-america-calctapp-1985.