Jozovich v. Central California Berry Growers Assn.

183 Cal. App. 2d 216, 6 Cal. Rptr. 617, 1960 Cal. App. LEXIS 1742
CourtCalifornia Court of Appeal
DecidedJuly 28, 1960
DocketCiv. 18618
StatusPublished
Cited by11 cases

This text of 183 Cal. App. 2d 216 (Jozovich v. Central California Berry Growers Assn.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jozovich v. Central California Berry Growers Assn., 183 Cal. App. 2d 216, 6 Cal. Rptr. 617, 1960 Cal. App. LEXIS 1742 (Cal. Ct. App. 1960).

Opinion

TOBRINER, J.

Respondent here guaranteed to produce a machine under a contract which provided for an intermediate payment on April 1st and a later final payment on May 1st under certain conditions. Appellant failed to make the April 1st payment; respondent nevertheless, continued to work on the machine. Our principal question turns on whether the trial court’s judgment for the intermediate installment can be sustained despite respondent’s continued attempted performance and his ultimate failure. Because the contract provided for the guaranteed production of a single entity, a functioning machine, we do not believe the intermediate payment constituted a severable, divisible obligation, and we hold that recovery of that installment, after the date of final payment, must be conditioned upon the expected and guaranteed performance. Nor can respondent successfully contend that he was prevented from fulfilling the contract by appellant’s refusal to permit him to work after June 23d; the extension of time from May 1st until June 23d for the completion of the machine granted respondent a reasonable time and he was entitled to no more. Finally, while the trial court allowed recovery for the reasonable value of the respondent’s services and his equipment, we hold that such relief in quasi contract was precluded by the presence of the express contract.

The litigation emanates from respondent’s attempt in the latter part of 1954, or early part of 1955, to construct a machine which would effectuate the quick freezing of individual strawberries. The parties recognized that such a machine would be revolutionary to the strawberry industry. Although respondent had neither constructed nor observed such a machine, he orally agreed to build one. The machine was to have the capacity to freeze 2,000 pounds of strawberries per *219 hour. The parties orally agreed that respondent retain any patent rights on the machine and that appellant pay $21,454.09 for it.

In 1955 respondent commenced work on this project, and, although appellant used the machine for the last three months of the 1955 strawberry season, its capacity did not exceed between 500 and 800 pounds per hour. In December, 1955, respondent accepted $11,000 “as payment for the IQF machine . . . with the understanding that any balance due . . . is subject to performance of certain conditions and agreements ...”

In January, 1956, however, appellant and respondent reached a new agreement, 1 calling for the improvement and *220 modification of the machine. Respondent signed the contract in the latter part of January or the first part of February; appellant executed it in the latter part of March.

On February 22, 1956, respondent commenced the task of modification. Although he concurred with the advice of independent engineers that the addition of 50 more tons of refrigeration would produce the requisite capacity, respondent did not add the refrigeration unit, allegedly because it would not fit within the building. In any event, from March 2d to April 16th respondent did not work on the machine despite his admitted knowledge that the contract date of May 1st fixed the beginning of the strawberry season; respondent offered as an excuse for this period of inactivity the fact that he awaited delivery of equipment, ordered in October, 1955, which became involved in bankruptcy proceedings. Respondent later testified that the prerequisite shop work also constituted a factor in the delay, and further admitted that the parts tied up in the bankruptcy litigation could be obtained elsewhere. While respondent could not recall the recommendation of independent engineering advisors that the addition of a 50 h.p. compressor would solve the capacity problem, he admitted his agreement with appellant for installation of such a compressor and his actual installation of only a 20 h.p. compressor. Respondent testified that upon payment of funds “promised us” he could have paid for, and installed, the 50 h.p. compressor, and that such a compressor would have facilitated the machine to attain its capacity. On May 1st, respondent did finally obtain this 50 h.p. compressor. He further claimed the earlier delay resulted from appellant’s tardiness in signing the contract; his omission to install it after May 1st, he attributed both to *221 appellant’s failure to make the April 1st contractual payment and to appellant’s continued utilization of the machine.

When, on approximately April 1, 1956, respondent asked Perez, appellant’s assistant freezer supervisor, for the $10,454.09 due under the contract, Perez answered, “We’ll see.” Nevertheless respondent continued working on the machine. According to Perez, when the capacity of the machine still remained at approximately 800 pounds per hour, respondent, at a board of directors’ meeting of appellant association on June 16, 1956, informed the board that he intended to install a disc in the machine to enable it to attain the desired capacity, but that if this did not work he did not know the answer. Appellant’s witnesses testified that at the meeting of the board, the directors told respondent he would be accorded one more week to complete the machine. Respondent testified he does “not recall” his being at the meeting, although he admits “I could be wrong there.” Subsequently appellant’s attorney on June 21st formally notified respondent in writing that June 23d constituted a deadline. Respondent’s installation of the disc proved to be abortive, and, after June 23d, appellant refused respondent access to the machine. After that date appellant abandoned all use of the machine.

Respondent’s amended complaint rested upon two counts: the first pleaded the written contract, previously set forth ; appellant’s failure to make the April 1st payment; appellant’s termination of respondent’s access to the machine after June 23d; respondent’s willingness and ability to perform his obligations under the contract, and closed with a request for payment of $10,454.09. The second count, with the exception of the request for $10,454.09, realleged all of the foregoing, but it additionally pleaded the $10,454.09 to be due for labor and materials to January 12, 1956; that $5,000 constituted the amount necessary to complete the machine; that respondent expended $4,000 in attempting to complete the machine prior to June 23d, and that this amount represented the reasonable value of parts and labor.

The court gave judgment to respondent for $10,454.09 on his first cause of action; on his second cause of action the court ordered appellant to return to respondent those parts he had installed in the machine subsequent to January 1, 1956, but awarded, in the event appellant failed to comply, a judgment *222 of $3,687.17 on this second cause; on appellant’s cross-complaint for damages the court denied any recovery.

At a post-trial proceeding appellant argued that the judge had changed his position in regard to the second cause of action, modifying a memorandum decision which refused relief to respondent on the second count. Appellant likewise complained that the court improperly refused it a stay of execution. In view of our disposition of this ease, however, the post-trial proceedings become immaterial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Piedmont Capital Management v. McElfish
California Court of Appeal, 2023
Piedmont Capital Management, L.L.C. v. McElfish
California Court of Appeal, 2023
Atigeo LLC v. Samson (In re Blixseth)
599 B.R. 106 (D. Montana, 2019)
Armstrong Petroleum Corp. v. Tri-Valley Oil & Gas Co.
11 Cal. Rptr. 3d 412 (California Court of Appeal, 2004)
C. Norman Peterson Co. v. Container Corp. of America
172 Cal. App. 3d 628 (California Court of Appeal, 1985)
Didier v. American Casualty Co.
261 Cal. App. 2d 742 (California Court of Appeal, 1968)
Leiter v. Eltinge
246 Cal. App. 2d 306 (California Court of Appeal, 1966)
Mullinix v. Morse
406 P.2d 298 (Nevada Supreme Court, 1965)
Lines v. Marin Municipal Water District
228 Cal. App. 2d 155 (California Court of Appeal, 1964)
Ryan v. Mike-Ron Corp.
226 Cal. App. 2d 71 (California Court of Appeal, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
183 Cal. App. 2d 216, 6 Cal. Rptr. 617, 1960 Cal. App. LEXIS 1742, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jozovich-v-central-california-berry-growers-assn-calctapp-1960.