Didier v. American Casualty Co.

261 Cal. App. 2d 742, 68 Cal. Rptr. 217, 1968 Cal. App. LEXIS 1801
California Court of Appeal·Decided May 2, 1968·No. Civ. No. 31135·Published·Cited by 2 cases

Opinion

COLLINS, J. pro tern.*

The appeal arises out of one judgment entered with respect to two separate actions brought by Mildred Didier, as administratrix of the estate of her husband, Michael E. Didier, deceased, who, at the time of death on February 22, 1961, was licensed as a general construction contractor, doing business under the name of M. E. Didier Company. In one case (SWC 4090) American Casualty Company of Reading, Pennsylvania (American) is the defendant; in the other ease (SWC 4092) United States Fidelity and Guaranty Company (U.S.F. & G.) is the defendant. In each action plaintiff asked for declaratory relief and for judgment that each defendant holds funds as constructive trustee for her late husband’s probate estate.

In 1960 plaintiff’s intestate was the successful bidder on two separate school building projects.1 Thereafter he entered into contracts which obligated him to furnish two sets of surety bonds for each project. The material and labor and faithful performance bonds on the Los Angeles City High School District project (University High School and Alexander Hamilton High School) were furnished by American. Prior thereto M. E. Didier and his wife Mildred Didier (plaintiff herein) executed a “General Agreement of Indemnity” in favor of American which covered all bonds and undertakings theretofore and thereafter to be furnished by American in Didier’s behalf. Similar bonds on the Los Angeles City High School District project were furnished by U.S.F. & G. Likewise the Didiers executed a “General Indemnity Agreement” in favor of U.S.F. & G. before the bonds were furnished.

At the time of his death Didier had been performing construction work on the high school district project for approxi[746] inately-nine months and on the city school district project for approximately three months.

On March 6, 1961, the contract supervisor for the high school district sent letters to the Didiers and to American stating that he was informed that neither the M. E. Didier Company nor the estate of M. E. Didier was prepared, or in a position, to continue the construction work and that it would seem to devolve upon the surety to take the necessary steps under its performance bond to complete the project; attention was called to a contract provision for a definite completion date and liquidated damages for any overrun of such period. Request was made of all parties addressed that information as to their plans be furnished at the earliest possible date.

On March 14, 1961, American’s attorney replied stating that the contractor’s organization “has had a complete failure of organization and is no longer prepared nor has the ability to continue the projects to completion”; that an audit of the books indicated inability to meet obligations as they arise, and that the payables far exceed the cash position. American stated that it elected to exercise its rights under the General Agreement of Indemnity for an assignment and transfer of all the contractor’s rights under the contract, and stated its intention to continue the completion of the project either directly or by means of a nominee.

On March 20, 1961, the board of education authorized recognition of the “default assignment” filed by American.2 Thereafter, American undertook to complete the work, using as its subcontractor, Kenneth Didier, decedent’s son. American submitted to the district a request for payment for the work performed by Didier during February 1961, and was paid $30,256 on an earned bill of $33,556.18 (10 percent retainage was withheld until completion of the work pursuant to the contract), The entire sum is claimed by plaintiff as an asset of the probate estate, although in March 1961 she had consented to the completion of the work by American. Ameri[747] can ultimately paid $93,431.20 in excess of all amounts paid by the school district pursuant to the contract.3

With respect to the Gates School project, the contracting officer on March 6, 1961, sent notifications to the Didiers and to U.S.F.& G. similar to those sent on the same date to the Didiers and to American, mutatis mutandi. Thereafter a three-way understanding was effected under which R. J. Daum Co. made an agreement with the board of education to complete the job, and U.S.F.& G. agreed to pay Daum $20,000 in addition to the cost of completing the work, and also agreed to pay all bills incurred prior to the take-over by Daum. On April 24, 1961, Daum submitted to the board a request for payment of all work completed to that date in the amount of $24,976 and this request was honored by the board. ($2,497.02—the 10 percent retainage provided in the Didier contract was withheld.) Plaintiff claims the entire sum as an asset of the probate estate, and argues that although it was paid to Daum, the latter was merely the conduit used by U.S.F. & G., which latter asserts that its loss under the indemnity agreement amounted to $55,365.46. Plaintiff also asserts that certain materialmen were paid twice for the same services because the amounts had been included in a previous report of performance. We treat the latter contention, even if valid, as of no relevance to the appeal, especially so since the school district was not made a party to the action.

It is plaintiff’s basic claim on appeal that the two construction contracts, being personal in nature, ceased to exist on February 22, 1961, the date of death of the contractor, and that all moneys earned by him but not paid up to that date are assets of his probate estate, subject to administration in a pending probate proceeding and that defendants hold these moneys as constructive trustees for the benefit of the probate estate.

The controlling issue in these eases is whether the construction contracts called for the performance of purely personal acts which could not be performed by others with the result that the contractor’s death discharged the obligation, or whether the contracts called for services of such a character that they may be as well performed by others in case the contractor dies before performance is had.

In California there are two appellate court decisions which [748] require consideration because opposite conclusions were reached.

Free access — add to your briefcase to read the full text and ask questions with AI

Didier v. American Casualty Co., 261 Cal. App. 2d 742, 68 Cal. Rptr. 217, 1968 Cal. App. LEXIS 1801 (Cal. Ct. App. 1968).

261 Cal. App. 2d 742 (Didier v. American Casualty Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kelly v. Teeters CA1/2
California Court of Appeal, 2015
Charles B. Webster Real Estate v. Rickard
21 Cal. App. 3d 612 (California Court of Appeal, 1971)