Camrosa County Water District v. Southwest Welding & Manufacturing Co.

49 Cal. App. 3d 951, 123 Cal. Rptr. 93, 1975 Cal. App. LEXIS 1267
California Court of Appeal·Decided July 16, 1975·No. Civ. 45533·Published·Cited by 6 cases

Opinion

Opinion

LORING, J. *

On September 13, 1972, Camrosa County Water District (Camrosa) filed ah action against Southwest Welding and Manufacturing Company, a corporation (Southwest) and General Insurance Company of America, a corporation (General) 1 for damages “in excess of $5,000 according to proof’ for breach of warranty of the quality of five water tanks. Southwest and General answered on October 20, 1972, and denied liability. At nonjury trial Southwest and General admitted liability. The *954 court filed notice of intended decision to render judgment in favor of Camrosa for $22,728 and directed counsel for plaintiff to prepare findings and judgment. Southwest and General objected to any finding of damage in excess of $17,628. The objection was overruled and findings were made and judgment entered fixing damages in the amount of $22,728. Southwest and General appeal, from the judgment.

Contentions

Appellants contend:

I The finding that the reasonable cost of repairs was $22,728 is not supported by the evidence.

II Evidence of damage is relevant only if it bears on the detriment proximately resulting from the breach of contract.

III Camrosá’s damage as established by the evidence amounts to only $17,628.

Facts

Camrosa and Southwest entered into a written contract under which Southwest agreed to construct five water tanks at a total lump sum price of $295,017 with a three-year warranty of quality. General provided a three-year warranty bond. The three-year warranty expired on March 31, 1972. On January 24, 1972, Camrosa inspected the tanks and found what it believed to be defective areas in the vinyl lining coatings of the interior of the reservoir surface. On January 31, 1972, .Camrosa sent Southwest a letter advising it of the defects and requested that the necessary repairs be made (plaintiff’s exhibit 6). On April 20, 1972, the attorneys for Southwest sent Camrosa a letter advising that Southwest would not undertake to correct the interior vinyl lining work (plaintiff’s exhibit 9). In April 1972, Camrosa requested and received bids from three companies to do the repair work for $19,525, $27,982 and $30,048. The low bid of $19,525 was submitted by Calblasco.

At trial (Dec. 17-20, 1973) Camrosa offered evidence from Calblasco over defendants’ objection that the cost of doing the repair work at time of trial would be $29,092, an increase of $9,567 over the low bid which' Calblasco submitted in April 1972. This difference was *955 attributable to increased costs and increased deterioration during the 19-month interval between the date of submission of the bid and the date of trial. Camrosa made no effort to repair the tanks prior to trial. Southwest did not admit liability to make the repair until date of trial.

Discussion

Southwest and General argue that as a matter of law Camrosa’s damage cannot exceed Calblasco’s low bid at the time the breach occurred and the cost which Camrosa would have incurred to make repairs at that time. Southwest and General argue that Camrosa had a duty to minimize the loss and make the repairs at the time the breach of warranty was discovered and that Camrosa could not collect the costs of such repairs as of the date of trial. Southwest and General conclude that the court’s finding that Camrosa was entitled to $22,728 is not supported by the evidence. They argue that Camrosa was not entitled to more than $17,628, 2 and, that as a matter of law, this court should modify the judgment to reduce it to that figure. As far as it goes, the position of Southwest and General is based upon substantial authorities ( Valencia v. Shell Oil Co., 23 Cal.2d 840 [147 P.2d 558]; Kitchel v. Acree, 216 Cal.App.2d 119 [30 Cal.Rptr. 714]; Sackett v. Spindler, 248 Cal.App.2d 220 [56 Cal.Rptr. 435]; 14 Cal.Jur.2d 731, 732) which however are not controlling here. Camrosa acknowledges that it is under a “disability to recover for avoidable loss” (22 Am.Jur.2d, Damages, § 30, pp. 50-51) which could have been avoided by “exercising reasonable diligence and ordinary care” (Guerrieri v. Severini, 51 Cal.2d 12 [330 P.2d 635]), but contends that it was not under a duty to go to “extraordinary or unusual lengths to minimize damages” (Guerrieri v. Severini, supra), and that it is not obligated “to assume [and perform] the burden which the adverse wrongdoer has violated, nor to incur relatively large expenses on that account.” (Dutra v. Cabral, 80 Cal.App.2d 114, 122 [181 P.2d 26]; see also Gerwin v. Southeastern Cal. Assn, of Seventh Day Adventists, 14 Cal.App.3d 209 [92 Cal.Rptr. 111].)

Camrosa further argues that Southwest and General had the burden of proving that Camrosa had the ability to lessen the actual damages incurred and that a person who is financially unable to make such expenditure is not required to do so (Jordan v. Talbot, 55 Cal.2d 597, 611 *956 [12 Cal.Rptr. 488, 361 P.2d 20, 6 A.L.R.3d 161].) Camrosa further argues that Southwest and General did not plead or prove that Camrosa violated a duty to minimize damage; that such a defense must be pleaded. (Vitagraph, Inc. v. Liberty Theatres Co., 197 Cal. 694, 699 [242 P. 709]; Hunter v. Croysdill, 169 Cal.App.2d 307, 318 [337 P.2d 174].)

Free access — add to your briefcase to read the full text and ask questions with AI

Camrosa County Water District v. Southwest Welding & Manufacturing Co., 49 Cal. App. 3d 951, 123 Cal. Rptr. 93, 1975 Cal. App. LEXIS 1267 (Cal. Ct. App. 1975).

49 Cal. App. 3d 951 (Camrosa County Water District v. Southwest Welding & Manufacturing Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related