Kitchel v. Acree

216 Cal. App. 2d 119, 30 Cal. Rptr. 714, 1963 Cal. App. LEXIS 1995
CourtCalifornia Court of Appeal
DecidedMay 14, 1963
DocketCiv. 20801
StatusPublished
Cited by24 cases

This text of 216 Cal. App. 2d 119 (Kitchel v. Acree) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kitchel v. Acree, 216 Cal. App. 2d 119, 30 Cal. Rptr. 714, 1963 Cal. App. LEXIS 1995 (Cal. Ct. App. 1963).

Opinion

SULLIVAN, J.

In this action on a building contract, plaintiffs and cross-defendants (hereinafter called appellants) appeal from a judgment, after a nonjury trial, which with one minor exception denies them recovery on their complaint and' awards defendants • and cross-complainants (hereinafter called respondents) the sum of $1,750 on their cross-complaint together with costs of suit and other relief.

Appellants, who are building contractors, entered into a contract- with respondents to construct a house on respondents’ real property. On November 25, 1959, appellants filed a complaint for foreclosure, seeking the recovery of $11,384 alleged as the balance due and unpaid on said contract, reasonable attorney’s fees, and the foreclosure of their contractor’s lien theretofore filed against respondents’ property. Respondents did -not file; their answer and cross-complaint until September 21, 1960. In the meantime, pursuant to a written agreement between the parties, the respondent paid appel *121 lants an additional $9,000 on the general understanding that such payment would be without prejudice to the respective claims of the parties.

Eespondents in their answer alleged that an additional $9,000 had been paid on the contract, leaving an unpaid balance of only $57.50 on the alleged contract price of $22,-557.50; denied that the work had been properly completed or that the conditions of the contract had been fully performed; alleged that the unpaid balance of $57.50 was far less than the amount of damages sustained by respondents as a result of the improper completion of the work; denied that appellants’ claim of lien had been properly recorded; and alleged that Parcel Two of the real property described in the complaint was not connected with or subject to the claim of lien.

Eespondents also filed a cross-complaint in three counts; The first count sought $2,500 damages for allegedly defective and unworkmanlike work and $348.59 because of appellants’ failure to install certain wiring, water pipes and to connect certain utilities; the second count sought reimbursement for $600 in additional interest paid on the construction loan as a result of the delay in completing the house; and the third count sought a decree quieting respondents' title to the above-mentioned Parcel Two which respondents maintained was not properly subject to appellants' lien. Appellants’ answer to the cross-complaint, while denying the material allegations of the first two counts, admitted that appellants claimed no interest in Parcel Two and that their claim of lien was filed in error as to such parcel.

The trial court found in substance that the total contract price was $22,557.50 of which $57.50 was unpaid; that the house was not substantially completed until December 31, 1959 (after commencement of this action) and that the work was not done in accordance with the plans and specifications; that the claim of lien did not cover Parcel Two which was not connected with Parcel One or benefited by the work thereon; that Parcel One was not subject to the lien because it had been prematurely recorded; that because of defective work, respondents had been damaged in the sum of $1,500 by reason of the installation of a cornice, and in the sum of $250 by reason of the installation of asphalt tile, in an unworkmanlike manner; but that the other claims of damage set forth in respondents’ cross-complaint had not been proved by sufficient evidence. The court concluded that appellants *122 were entitled to recover the sum of $57.50 with interest but were not entitled to any lien on any of the real property; that respondents were entitled to recover the sum of $1,750 without interest but with costs; and that respondents were entitled to a judgment quieting title. Judgment was entered accordingly.

Appellants here make no attack on that part of the judgment denying them recovery in excess of $57.50 and the remedy of lien foreclosure. Their sole contention on appeal is that the court committed error in awarding respondents damages on the cross-complaint. Respondents on their part have conceded both in their brief and on oral argument that there is no evidence to support the court’s finding of $250 damages resulting from appellants’ failure to install the asphalt tile according to the plans and specifications. Thus the parties present to us a single narrow issue: Is the award of $1,500 damages for appellants’ failure to install the cornice in a workmanlike manner supported by the law and the evidence ? As to this issue, we point out that the dispute between the parties is confined to damages awarded, appellants making no claim that the evidence was insufficient to support the court’s finding that this particular work was improperly performed.

George Aeree, one of the respondents, testified under examination by his own counsel that the cornice around the -exterior of the house was not completely boxed in; that according to the contract, the cornice was to fully cover or box in the eaves; and that appellants left large seams and openings, thus permitting birds to build nests within the enclosed area. Mr. Aeree further testified that he had been a carpenter for 10 years, and that in his opinion the house was less valuable because of the work on the cornice than it would have been had the work been properly done. He stated that in his opinion as the owner, the value of the house was “ [a] minimum of $2,500” less than what it would have been had such work been done correctly.

At this point in his testimony, respondent was asked for the basis of his opinion. He answered, without objection, that it was based on estimates of the cost of repairing the condition received by him from various contractors whom he had examine it. He was then asked from whom he had received the estimates, to which counsel for appellants objected on the ground that any estimates would be hearsay. The court overruled the objection as being premature since only the names *123 of the contractors were called for. Respondent was then asked who had given him an estimate and named Wallace Smith, a plastering contractor.

The following testimony was then given: “Q. And what was his estimate as to what it would cost to do such work? Mr. Millspaugh : I will object to that as calling for hearsay. The Court : Well I think Mr. Joseph stated the law correctly. It is overruled. The Witness: He gave me an estimate of $1200, and that the carpenter work—that didn’t include the carpenter work that was to be done, and I estimate that the carpenter work would be $300 minimum.” 1

On cross-examination, respondent explained that he obtained an estimate from a plasterer because he found the estimates of building contractors too high.

Respondents concede that the opinion evidence of Mr. Aeree as to the diminution of the value of his house in the amount of $2,500 “did not directly provide sufficient evidence to support” their cause of action for damages, but insist that since it was received without any objection of appellants “the door was then open” for respondent “to then give supporting testimony concerning estimates and opinions as to the cost ’ ’ of putting the cornice in proper condition. Respondents have not furnished us with a single citation of authority in support of their above position.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Pelton CA3
California Court of Appeal, 2024
People v. Portillo
California Court of Appeal, 2023
People v. Garcia CA3
California Court of Appeal, 2023
Grasshopper House v. Bosworth CA2/4
California Court of Appeal, 2015
People v. Aller CA3
California Court of Appeal, 2015
People v. Hobbs CA2/4
California Court of Appeal, 2014
In re Caleb P. CA2/5
California Court of Appeal, 2013
Contra Costa Water District v. Bar-C Properties
5 Cal. App. 4th 652 (California Court of Appeal, 1992)
People v. Hayes
172 Cal. App. 3d 517 (California Court of Appeal, 1985)
Hoover Community Hotel Development Corp. v. Thomson
167 Cal. App. 3d 1130 (California Court of Appeal, 1985)
Lehr v. Crosby
123 Cal. App. Supp. 3d 1 (Appellate Division of the Superior Court of California, 1981)
Walker v. Signal Companies, Inc.
84 Cal. App. 3d 982 (California Court of Appeal, 1978)
Glendale Federal Savings & Loan Ass'n v. Marina View Heights Development Co.
66 Cal. App. 3d 101 (California Court of Appeal, 1977)
Camrosa County Water District v. Southwest Welding & Manufacturing Co.
49 Cal. App. 3d 951 (California Court of Appeal, 1975)
Martin v. State Personnel Board
26 Cal. App. 3d 573 (California Court of Appeal, 1972)
Jones v. Kvistad
19 Cal. App. 3d 836 (California Court of Appeal, 1971)
Tahoe National Bank v. Phillips
480 P.2d 320 (California Supreme Court, 1971)
Windeler v. Scheers Jewelers
8 Cal. App. 3d 844 (California Court of Appeal, 1970)
Houghton v. Kerr Glass Manufacturing Corp.
261 Cal. App. 2d 530 (California Court of Appeal, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
216 Cal. App. 2d 119, 30 Cal. Rptr. 714, 1963 Cal. App. LEXIS 1995, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kitchel-v-acree-calctapp-1963.