Walker v. Signal Companies, Inc.

84 Cal. App. 3d 982, 149 Cal. Rptr. 119, 1978 Cal. App. LEXIS 1939
CourtCalifornia Court of Appeal
DecidedSeptember 20, 1978
DocketCiv. 14858
StatusPublished
Cited by50 cases

This text of 84 Cal. App. 3d 982 (Walker v. Signal Companies, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walker v. Signal Companies, Inc., 84 Cal. App. 3d 982, 149 Cal. Rptr. 119, 1978 Cal. App. LEXIS 1939 (Cal. Ct. App. 1978).

Opinion

*989 Opinion

WIENER, J.

This case centers around the written contract for the construction of a house in the residential development, Coronado Cays, between Coronado Landmark, Inc., as contractor, and plaintiffs W. H. Walker and D. Jane Walker (Walkers).

Walkers sued the Signal Companies, Inc. (Signal), Signal Landmark, Inc. (Signal Landmark), Cedric Sanders Corp. (Sanders), Coronado Landmark, Inc. (Coronado Landmark) dba Coronado Cay Co. and Jack Conover (Conover) for breach of contract and fraud. Mrs. Walker sued for intentional and negligent infliction of emotional distress. After a jury trial, judgments in the sum of $ 11,928 and $5,000 were entered in favor of the Walkers against Coronado Landmark and Signal Landmark on the breach of contract and fraud causes of action respectively. Punitive damages of $100,000 were imposed against Coronado Landmark and $115,000 against Signal Landmark. A judgment in the sum of $400 was rendered for Mrs. Walker on her cause of action for negligent infliction of emotional distress against Coronado Landmark, Signal Landmark and Conover, and in favor of all defendants on her cause of action for intentional infliction of emotional distress. A judgment of nonsuit was entered for Conover on the first cause of action and Signal and Sanders on all causes of action.

Coronado Landmark and Signal Landmark appeal from the judgments for breach of contract, fraud and punitive damages. Walkers appeal from the judgment of nonsuit in favor of Signal and Sanders. After our examination of issues raised in both appeals, we conclude the judgment for compensatory damages should be modified and merged into a single judgment of $8,414 and, except as so modified, alljudgments should be affirmed.

The Signal Landmark and Coronado Landmark Appeal Breach of Contract

Sufficiency of the Evidence

The Walkers’ breach of contract claim is based on the building construction contract of August 18, 1972, and is premised on the untimely completion of the residence. The defendants Coronado Landmark and Signal Landmark contend there is insufficient evidence to support that *990 judgment. We approach our task keeping in mind that all conflicts in the evidence must be resolved in favor of the judgment and all reasonable inferences indulged in to uphold the verdict. (Crawford v. Southern Pacific Co. (1935) 3 Cal.2d 427, 429 [45 P.2d 183].)

The Walkers sold their residence in Northern California on October 18, 1971, as part of their program to relocate in the San Diego area after Mr. Walker’s retirement. On July 16, 1972, they signed a contract to buy a house for $77,400 in the Coronado Cays development in Coronado. They gave, their check for $1,000 to Charles Frederick, who acknowledged receipt on behalf of Coronado Cay Company and Signal Landmark, whom he believed to be its general partner. The contract was approved on July 21, 1972, by Jack Conover, a vice president and director of sales and marketing of Coronado Landmark. Frederick had filled in the terms of the sale in the blanks of the form contract including the statement, “Home to be completed by December 31, 1972.” Mr. Walker was aware of the necessity for construction to be completed within the period which would permit a deferral of all or substantially all of the capital gains tax which would otherwise fall due because of the sale of his first residence. 1 He requested a specific date for completion to be set out in the contract.

The Walkers returned to Coronado on August 18, 1972. When they went to the Coronado Cays development, they were advised by an employee of Coronado Landmark that it was necessary for them to sign another contract before construction of their house could start. They then signed as owners another boilerplate contract entitled Building Construction Contract, with Coronado Landmark as contractor in which they agreed to pay $38,500 for the construction of the house previously described in the real estate purchase agreement. Separate escrow instructions for the sale of the land and construction loan were signed on that date with the Bank of America as escrow agent. They were told by a representative of the bank an 80 percent secured real estate loan had been approved.

The construction contract provided for commencement of construction within five days after the owner obtained financing and the issuance of a building permit; construction was to be completed within 180 calendar *991 days from commencement subject to excusable delays; and time was of the essence to both parties. The building permit was issued on August 11, 1972; construction started on October 3, 1972, one day before the close of the escrow.

The house had to be completed by April 1, 1973, i.e., 180 days after October 3, 1972, unless extended for excusable delays. The last day for the beneficial income tax consequences was April 17, 1973.

Construction proceeded slowly. Trenching was started on October 3; the slab was completed on November 19, 1972. No further progress was made until the last week of January 1973. By March 14, 1973, the electrical, heating, framing and roofing work had been inspected and approved by the City of Coronado. However, even as late as April 17, 1973, the house was still not finished. Numerous doors were not installed, considerable painting had to be done, no carpets or floor coverings had been installed and the toilets were not hooked up. We will not set out the 41 items listed by Mr. Walker describing the incomplete status of the residence as of that date when he communicated his unhappiness to Signal Landmark. According to his testimony, construction was still incomplete in the early part of August with substantial completion occurring at the end of August. He signed the notice of completion on September 4.

The primary factual question presented to the jury was whether the date for completion was extended because of excusable delays. After our review of each item in the contract which permits delay, we conclude there is substantial evidence to support the verdict. Part of the delay was allegedly due to a lumber shortage. Evidence was presented that sufficient lumber was available at the job site to frame the house following the pouring of the slab had the construction project been organized properly. There was only one possible day of delay because of labor shutdowns. Defendants rely primarily on the inclement weather, the 40 days of “measurable” rain in Coronado. A vice president of Signal Landmark in charge of construction testified to “. . . several days of inclement weather preventing work.” He admitted that it was unfortunate that the usual and customary practice of maintaining a log to determine the effect of the weather on the progress of construction was not followed. He also admitted that rain itself might not be a factor depending on the stage of completion of construction. In light of the quality of the testimony as to bad weather and the effect of that weather on the construction of *992 plaintiffs’ house, the jury was entitled to give, it little weight.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brewer v. Impact Biomedicines CA4/1
California Court of Appeal, 2025
Credit Card Services v. Chuang CA2/3
California Court of Appeal, 2023
Waverly Kaffaga v. Thomas Steinbeck
938 F.3d 1006 (Ninth Circuit, 2019)
Mulitz v. L.A. Stucco, Inc. CA2/4
California Court of Appeal, 2016
Izell v. Union Carbide Corp.
231 Cal. App. 4th 962 (California Court of Appeal, 2014)
Izell v. Union Carbide
California Court of Appeal, 2014
Allen v. Packer CA2/1
California Court of Appeal, 2013
Citizens Federal Bank v. United States
66 Fed. Cl. 179 (Federal Claims, 2005)
Citizens Federal Bank, FSB v. United States
59 Fed. Cl. 507 (Federal Claims, 2004)
Zanakis-Pico v. Cutter Dodge, Inc.
47 P.3d 1222 (Hawaii Supreme Court, 2002)
Kaplan v. Coldwell Banker Residential Affiliates, Inc.
59 Cal. App. 4th 741 (California Court of Appeal, 1997)
Stevens v. Owens-Corning Fiberglas Corp.
49 Cal. App. 4th 1645 (California Court of Appeal, 1996)
Freeman & Mills, Inc. v. Belcher Oil Co.
900 P.2d 669 (California Supreme Court, 1995)
Hunter v. Up-Right, Inc.
864 P.2d 88 (California Supreme Court, 1993)
People v. Morse
21 Cal. App. 4th 259 (California Court of Appeal, 1993)
Tavaglione v. Billings
847 P.2d 574 (California Supreme Court, 1993)
Myers Building Industries, Ltd. v. Interface Technology, Inc.
13 Cal. App. 4th 949 (California Court of Appeal, 1993)
Douglas v. Ostermeier
1 Cal. App. 4th 729 (California Court of Appeal, 1991)
Las Palmas Associates v. Las Palmas Center Associates
235 Cal. App. 3d 1220 (California Court of Appeal, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
84 Cal. App. 3d 982, 149 Cal. Rptr. 119, 1978 Cal. App. LEXIS 1939, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walker-v-signal-companies-inc-calctapp-1978.